Big Black Friday Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

CDT Construction Documents Technologist Questions and Answers

Questions 4

When should a post-occupancy evaluation by the facility manager be performed?

Options:

A.

At the end of the correction period

B.

Three to six months after initial occupancy

C.

Just before the end of the warranty period

D.

One year after substantial completion

Buy Now
Questions 5

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Buy Now
Questions 6

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

Options:

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Buy Now
Questions 7

An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?

Options:

A.

The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.

B.

The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.

C.

The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.

D.

The electrical engineer does not need to control how the work is to be assigned to subcontractors.

Buy Now
Questions 8

What is MasterFormat® keyword index used for?

Options:

A.

Identifying Level 4 sections

B.

Identifying specification format

C.

Locating subject titles and numbers

D.

Specifying correct word usage

Buy Now
Questions 9

As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?

Options:

A.

The client is unfamiliar with this type of project.

B.

The project team consists of multiple new members.

C.

The site presents unusual challenges and constraints.

D.

The contractor is unable to commit to original schedule.

Buy Now
Questions 10

When does a project reach substantial completion?

Options:

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor's final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Buy Now
Questions 11

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Buy Now
Questions 12

When preparing their bid, a contractor organizes their costs into different categories. The following items are examples of which type of cost?

    Permits and inspections

    Mobilization and startup

    Jobsite safety and security procedures, including personnel

    Administrative costs attributable to the work

Options:

A.

Construction

B.

Contingency

C.

Overhead

D.

Insurance

Buy Now
Questions 13

Which Uniform Drawing System (UDS) symbol would be used in a plan view drawing and directs the user to an elevation view?

c

Options:

A.

Option A – a symbol showing a circle with leadered detail and line-type notes

B.

Option B – an oval with “101A” (room or space tag)

C.

Option C – a circular symbol with a triangular pointer and text such as “A1” over “A-201”

D.

Option D – a small cross with a leader to a box labeled “EL”

Buy Now
Questions 14

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Buy Now
Questions 15

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Buy Now
Questions 16

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

Options:

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Buy Now
Questions 17

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Buy Now
Questions 18

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?

Options:

A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.

B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.

C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.

D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).

Buy Now
Questions 19

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Buy Now
Questions 20

You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?

Options:

A.

Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.

B.

Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.

C.

Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.

D.

Construction may begin only after both city and state permits have been issued.

Buy Now
Questions 21

Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?

Options:

A.

Mobilization meeting

B.

Preconstruction meeting

C.

Prebid meeting

D.

Coordination meeting

Buy Now
Questions 22

Which of the following establishes a baseline from which deviations are identified?

Options:

A.

General requirements

B.

Supplementary conditions

C.

Project manual

D.

General conditions

Buy Now
Questions 23

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Buy Now
Questions 24

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

Options:

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Buy Now
Questions 25

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Buy Now
Questions 26

During the bid period, what does the architect issue if it is necessary to modify the procurement documents?

Options:

A.

Addenda

B.

Construction change directives

C.

Change order

D.

RFI response

Buy Now
Questions 27

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Buy Now
Questions 28

How does the architect/engineer control the project cost when not enough information is available to make product decisions during the design phases of a project?

Options:

A.

Alternates

B.

Unit prices

C.

Contingencies

D.

Allowances

Buy Now
Questions 29

Which of the following should be avoided when specifying warranties?

Options:

A.

Requiring or permitting a warranty that strengthens the owner's rights

B.

Requiring minimum warranty coverage available for a particular product

C.

Including language to require warranties extending beyond the contractor's one-year correction period

D.

Relying on a warranty as a substitute for thorough investigation of a product and its manufacturer

Buy Now
Questions 30

What is a fundamental principle required to provide fairness in a competitive bidding process?

Options:

A.

Bid securities provide protection to all bidders for unfair practices of others.

B.

The bid shopping process provides the most beneficial pricing to the owner.

C.

All bids are prepared based on identical conditions, information, and time constraints.

D.

A minimum of three bids are required to assure sufficient competition.

Buy Now
Questions 31

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Buy Now
Questions 32

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Buy Now
Questions 33

In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?

Options:

A.

Project Conception phase

B.

Schematic Design phase

C.

Design Development phase

D.

Construction Documents phase

Buy Now
Questions 34

How do private bidding practices compare or contrast with public bidding practices?

Options:

A.

A private owner may waive any informality in the bidding, except for the performance bond.

B.

Private bids may be opened in private, but the results must be published in a reasonable time.

C.

The laws and regulations for private bidding are the same as for public bidding.

D.

The private owner may award a contract to a responsive and responsible bidder other than the lowest.

Buy Now
Questions 35

Which of the following is NOT a method of specifying?

Options:

A.

Perspective

B.

Proprietary

C.

Performance

D.

Reference standard

Buy Now
Questions 36

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Nov 22, 2025
Questions: 120
CDT pdf

CDT PDF

$25.5  $84.99
CDT Engine

CDT Testing Engine

$30  $99.99
CDT PDF + Engine

CDT PDF + Testing Engine

$40.5  $134.99