Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

ISO-9001-Lead-Auditor QMS ISO 9001:2015 Lead Auditor Exam Questions and Answers

Questions 4

You are carrying out an audit at an organisation seeking certification to ISO 9001 for the first time. The organisation offers health and safety training to

customers.

You are interviewing the Quality Systems Manager (QSM).

You: "What risks and opportunities have the business identified?"

QSM: "I'1l show you. This was discussed with the Managing Director at the latest management review."

Narrative: The QSM shows you the latest management review record and points to the following table:

You: "How is the business planning to address these risks and opportunities?"

QSM: "The MD said that they already knew about them so it was not necessary."

Options:

Buy Now
Questions 5

Which one of the following documents addresses audit time calculation for third-party certification audits?

Options:

A.

ISO 17021-1

B.

ISO 19011

C.

ISO 9000

D.

ISO 9001

Buy Now
Questions 6

During a third-party audit of a pharmaceutical organisation (CD9000) site of seven COVID-19 testing laboratories in various terminals at

a major international airport, you interview the CD 9000's General Manager (GM), who was accompanied by Jack, the legal compliance

expert. Jack is acting as the guide in the absence of the Technical Manager due to him contracting COVID-19.

You: "What external and internal issues have been identified that could affect CD9000 and its quality management system?"

GM: "Jack guided us on this. We identified issues like probable competition of another laboratory organisation in the airport, legal

requirements on COVID-19 continuously changing, the shortage of competent laboratory analysists, the epidemic declining soon,

shortage of chemicals for the analysis. It was quite a good experience."

You: "Did you document these issues?"

GM: "No. Jack said that ISO 9001 does not require us to document these issues."

You: "How did you determine the risks associated with the issues and did you plan actions to address them?"

GM: "I am not sure. The Technical Manager is responsible for this process. Jack may be able to answer this question in his absence."

Select two options for how you would respond to the General Manager's suggestion:

Options:

A.

I would not accept the legal compliance expert answering the question.

B.

I would ask to audit the Technical Manager by phone.

C.

I would delay the audit until the return of the technical manager

D.

I would look for evidence that the actions resulting from the risk assessment had been taken.

E.

I would ask for a different guide instead of the legal compliance expert.

F.

I would ask the consultant to leave the meeting since he is not an employee of the organisation.

Buy Now
Questions 7

Noitol is an organisation specialising in the design and production of e-learning training materials for the insurance market. During an ISO 9001 audit of the development department, the auditor asks the Head of Development about the process used for validation of the final course design. She states that they usually ask customers to validate the product with volunteers. She says that the feedback received often leads to key improvements.

The auditor samples the design records for a recently completed course for the 247 Insurance organisation. Design verification was carried out but there was no validation report. The Head of Development advises that this customer required the product on an urgent basis, so the validation stage was omitted. When asked, the Head estimates that this occurs about 50% of the time. She confirms that they always ask for feedback and often make changes. There is no record of feedback in the design file for the course.

The auditor decides to review the training course design process in more depth.

Select three options that provide a meaningful audit trail for this process.

Options:

A.

How are students advised about prior learning requirements?

B.

How is customer feedback integrated into the course?

C.

How is the cost of the course calculated?

D.

What risks and opportunities have been notified to interested parties?

E.

How is design documentation controlled and managed?

F.

How is technical content of courses verified as correct?

G.

How is the tutor trained to deliver the completed course?

Buy Now
Questions 8

Scenario 5: Mechanical-Electro (ME) Audit Stages

Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.

Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME's revenue dropped significantly. In addition, customers' trust and confidence in the company decreased, and the reputation of the company was damaged.

In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.

A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME's documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.

Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME's representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.

Following the on-site activities and the opening meeting with ME's top management, the audit team structured an audit test plan to verify whether ME’s QMS conformed to Clause 8.2.1 (Customer Communication) of ISO 9001.

To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME's operations.

The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.

Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.

After reviewing the documented information, Li Na claimed that it was not necessary to report the minor nonconformities that were identified; instead, they would be discussed in the next audit phase. Is this acceptable?

Options:

A.

Yes, during the review of documented information, only major nonconformities need to be documented if detected.

B.

Yes, all identified nonconformities throughout the audit need to be documented and communicated at the end of the audit.

C.

No, identification of minor nonconformities or areas of concern that could become nonconformities need to be documented and communicated to the auditee before proceeding to the next audit phase.

Buy Now
Questions 9

Select the word that best completes the sentence:

Options:

Buy Now
Questions 10

Scenario 5: Mechanical-Electro (ME) Audit Stages

Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.

Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME's revenue dropped significantly. In addition, customers' trust and confidence in the company decreased, and the reputation of the company was damaged.

In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.

A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME's documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.

Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME's representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.

Following the on-site activities and the opening meeting with ME's top management, the audit team structured an audit test plan to verify whether ME’s QMS conformed to Clause 8.2.1 (Customer Communication) of ISO 9001.

To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME's operations.

The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.

Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.

According to scenario 5, Li Na conducted group interviews with departmental managers and top management by herself. Is this in accordance with audit best practices?

Options:

A.

Yes, only the audit team leader should conduct group interviews.

B.

Yes, the auditee’s top management is always interviewed by the audit team leader only.

C.

No, two auditors should be present in case of group interviews.

Buy Now
Questions 11

Scenario 1: AL-TAX is a company located in California which provides financial and accounting services. The company manages the finances of 17 companies and now is seeking to expand their business even more The CEO of AL-TAX, Liam Durham, claims that the company seeks to provide top-notch services to their clients Recently, there were a number of new companies interested in the services provided by AL-TAX.

In order to fulfill the requirements of new clients and further improve quality, Liam discussed with other top management members the idea of implementing a quality management system (QMS) based on ISO 9001. During the discussion, one of the members of the top management claimed that the size of the company was not large enough to implement a QMS. In addition, another member claimed that a QMS is not applicable for the industry in which AL TAX operates. However, as the majority of the members voted for implementing the QMS. Liam initiated the project.

Initially, Liam hired an experienced consultant to help AL-TAX with the implementation of the QMS. They started by planning and developing processes and methods for the establishment of a QMS based on ISO 9001. Furthermore, they ensured that the quality policy is appropriate to the purpose and context of AL TAX and communicated to all employees. In addition, they also tried to follow a process that enables the company to ensure that its processes are adequately resourced and managed, and that improvement opportunities are determined.

During the implementation process, Liam and the consultant focused on determining the factors that could hinder their processes from achieving the planned results and implemented some preventive actions in order to avoid potential nonconformities Six months after the implementation of the QMS. AL-TAX conducted an internal audit. The results of the internal audit revealed that the QMS was not fulfilling all requirements of ISO 9001. A serious issue was that the QMS was not fulfilling the requirements of clause 5.1.2 Customer focus and had also not ensured clear and open communication channels with suppliers.

Throughout the next three years, the company worked on improving its QMS through the PDCA cycle in the respective areas. To assess the effectiveness of the intended actions while causing minimal disruptions, they tested changes that need to be made on a smaller scale. After taking necessary actions, AL-TAX decided to apply for certification against ISO 9001.

Based on the scenario above, answer the following question:

Scenario 1 indicates that AL-TAX did not ensure clear and open communication channels with interested parties. Which quality management principle did the organization not follow in this case?

Options:

A.

Evidence-based decision making

B.

Relationship management

C.

Leadership

Buy Now
Questions 12

Match each of the following statements into the table below to show whether they apply to first-party audits, second-party audits or third-party audits:

Options:

Buy Now
Questions 13

Match the process descriptions below to the process names:

Options:

Buy Now
Questions 14

You work for organisation A. You are asked to lead an internal audit of A's quality management system. It has a head office in Plant A1 and a second Plant A2 nearby. Due to the COVID-19 pandemic, production in A2 was discontinued and it was rented to a logistics organisation B, not related to A. There are no A employees working in A2. Organisation A expects to reassume production in A2 as soon as possible.

Which of the following actions would you consider appropriate when planning the internal audit of A's quality management system?

Options:

A.

Visit Plant A2 to interview personnel of company B

B.

Visit Plant A2 to interview B's quality manager

C.

Visit Plant A2 to interview A's security personnel and B's maintenance department

D.

Interview the A2 plant manager, now working in Plant A1

Buy Now
Questions 15

The following actions need to be carried out during a third-party audit planning stage. Which two actions correspond to the individual(s) managing the audit program before the involvement of the audit team leader’

Options:

A.

Prepare the audit plan

B.

Assign responsibilities within the audit team

C.

Prepare the checklists

D.

Provide the resources needed

E.

Review the reports of previous audits

F.

Select the audit team members

Buy Now
Questions 16

Select six of the activities that are specifically required by ISO 17021-1 as part third-party (Certification Body) surveillance audit processes.

Options:

A.

Audit use of certification marks on marketing materials.

B.

Review changes to the QMS since last visit.

C.

Confirm effectiveness of internal audit and management review.

D.

Complete a full document review of the quality management system.

E.

Failing to meet financial responsibilities.

F.

Review the status of previously raised findings and audit effectiveness of any outstanding findings.

G.

Review the calibration status of the instrumentation.

Buy Now
Questions 17

XYZ Corporation is an organisation that employs 100 people. As audit team leader, you are conducting a

certification audit at Stage 1. When reviewing the quality management system (QMS) documentation, you

find that quality objectives have been set for every employee in the organisation except top management.

The Quality Manager complains that this has created a lot of resistance to the QMS, and the Chief Executive

is asking questions about how much it will cost. He asks for your opinion on whether this is the correct

method of setting objectives.

Three months after Stage 1, you return to XYZ Corporation to conduct a Stage 2 certification audit as Audit

Team Leader with one other auditor. You find that the Quality Manager has cancelled the previous quality

objectives for all employees and replaced them with a single objective for himself. This states that "The

Quality Manager will drive multiple improvements in the QMS in the next year". The Quality Manager indicates

that this gives him the authority to issue instructions to department managers when quality improvement is

needed. He says that this approach has the full backing of senior management. He shows you the latest

Quality Improvement Request that was included in the last management review.

After further auditing, the issues below were found. Select three statements that apply to the term 'audit trail'

Options:

A.

Decisions on improvement action timescales not involving departmental managers.

B.

Evaluation of the results of the improvement action not always documented by the Quality Manager.

C.

Limited knowledge of the content of Quality Improvement Requests by departmental staff.

D.

Quality improvements not aligning with the quality policy.

E.

The single quality objective set for the organisation by the Quality Manager.

F.

Top management claim not to be aware of the improvement request (QI/12/20/HR-3) initiated by the Quality Manager.

Buy Now
Questions 18

Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.

A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC's top management and then drafted the audit conclusions.

In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.

Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.

Based on the scenario above, answer the following question:

Scenario 6 indicates that although the top management did not agree with the audit findings, the audit team began preparing the audit report. Is this acceptable?

Options:

A.

No, the audit report should have been prepared before the audit findings were presented in the closing meeting

B.

No, during the closing meeting, the audit team had to inform the auditee about the complaint and appeal handling process

C.

Yes, the audit team had to begin preparing the audit report although the top management did not agree with the audit findings

Buy Now
Questions 19

An audit team of three people is conducting a Stage 2 audit to ISO 9001 of an engineering organisation which manufactures sacrificial anodes for the

oil and gas industry in marine environments. These are aluminium products designed to prevent corrosion of submerged steel structures. As one of

the auditors, you find that the organisation has shipped anodes for Project DK in the Gulf of Mexico before the galvanic efficiency test results for the

anodes have been fully analysed and reported as required by the customer. The Quality Manager explains that the Managing Director authorised the

release of the anodes to avoid late delivery as penalties would be imposed. The customer was not informed since the tests rarely fall below the

required efficiency. You raise a nonconformity against clause 8.6 of ISO 9001.

During the audit team meeting in preparation for the Closing meeting, the second auditor disagreed with the clause of ISO 9001 selected for the

above nonconformity. He thinks it should be clause 9.1.1.

Choose three options for how the audit team leader should best respond to the situation:

Options:

A.

The audit team leader will refer to the quality manager to determine which clause they agree with.

B.

Advise that he will think about the clause and announce his decision during the Closing meeting.

C.

Immediately agree with the second auditor that clause 9.1.1 would be better.

D.

Immediately overule the objection of the second auditor with no discussion of the clause.

E.

Invite you and the second auditor to fully explain your point of view and then decide which clause to select.

F.

Review the evidence with you and the second auditor, and then decide which clause of ISO 9001 would best apply.

G.

Suggest that neither clause is accurate and instead propose clause 9.1.3 as the best one for the nonconformity.

Buy Now
Questions 20

What type of audit evidence are policies and guidelines?

Options:

A.

Confirmative evidence.

B.

Technical evidence.

C.

Documentary evidence.

Buy Now
Questions 21

Which of the following is a record related to the audit program that should be managed and maintained?

Options:

A.

Objective audit evidence and findings

B.

Maintenance and improvement of competence

C.

Schedule of audits

Buy Now
Questions 22

Knowledge and skills are requirements of the auditor's competence. Select two from the following topics of knowledge that apply to every member of an audit team auditing an ISO 9001 quality management system.

Options:

A.

Requirements of ISO 9001

B.

ISO 19011 Audit principles

C.

Organisation's market sector

D.

Organisation's invoicing and profits of the last 5 years

E.

Organisation's processes

F.

Requirements of auditee's interested parties other than customers

Buy Now
Questions 23

An organization has decided to implement a QMS based on ISO 9001. What should they consider when determining internal issues?

Options:

A.

The social and economic environments

B.

The competitive environment

C.

Knowledge

D.

The expectations of suppliers

Buy Now
Questions 24

Who assigns a guide to assist the audit team?

Options:

A.

The certification body

B.

The auditee

C.

The audit team leader

Buy Now
Questions 25

A Health Trust has contracted with Servitup, a catering services organisation which has been certified to ISO 9001 for 1 year. It provides services to ten, small rural

hospitals in remote locations involving purchase and storage of dry goods and fresh produce, preparing meals and loading heated trolleys for ward service by hospital

staff. An auditor is conducting the first sole surveillance audit at one site with the Deputy Catering Manager (DCM).

At the closing meeting attended solely by the DCM, the auditor informs him that he has found numerous gaps in the QMS processes which lead him to consider

recommending suspension of the organisation's certification. He is particularly concerned with the evidence that patient health is being adversely affected by produce

stored beyond its safe consumption date, poor kitchen hygiene and undercooked meals. The DCM says that he cannot make any decisions about these issues in the

absence of the Catering Manager due to illness but will write everything down and report to the Catering Manager.

Which two actions should you take in the context of the audit?

Options:

A.

Close the meeting immediately after the DCM's response and advise that the issues will be addressed at the next surveillance visit.

B.

Call the individual(s) managing the audit programme to explain the situation and recommend immediate suspension of certification to protect the integrity of the Certification Body.

C.

Continue with the meeting, present the audit conclusions and inform the DCM that the organisation will receive the audit report in due course.

D.

Conclude the meeting early and advise that it will be rescheduled once the Catering Manager has returned to work.

E.

Recommend that all personnel should be given urgent in-depth training in the QMS.

F.

Thank the DCM for his time and express an expectation that improvements will be made in the QMS.

Buy Now
Questions 26

In the context of a third-party audit, match the event with the responsibility for conducting it.

Options:

Buy Now
Questions 27

When monitoring customer perceptions, which analysis is helpful to use?

Options:

A.

PEST analysis

B.

Market-share analysis

C.

Gap analysis

D.

Competitive benchmarking

Buy Now
Questions 28

You are conducting a third-party audit to ISO 9001 and the next item on your audit plan is 'internal auditing'.

When reviewing a sample of audit records up to 5 years previously, you find that many contain non-conformance reports and no actions have been taken. You interview the Quality Manager.

You: "I have noted that many of the older files contain non-conformances that have not had any corrective action taken."

Quality Manager: "Because the business is always changing, the departmental managers tell me that the non-conformances are no longer applicable. I made a decision that any non-conformance over 3 years old is automatically closed"

You: "Do you obtain any confirmation beforehand from the appropriate departments that the non-conformances are no longer applicable."

Quality Manager: " No, because they are so old I consider that they are no longer appropriate. Please remember that we take a risk-based approach which means we audit where and when it is considered important to do so.

Select one course of action you would now take from the options.

Options:

A.

Interview Top management to determine whether they were aware of and agreed the actions of the Quality Manager

B.

Review all non-conformances reports related to clause 9.2 of ISO 9001

C.

Interview relevant Departmental managers to assess whether the older non-conformances are still valid.

D.

Raise a non-conformance report against clause 9.2.2.e of ISO 9001

Buy Now
Questions 29

In the context of a third-party certification audit, how can the auditor demonstrate confidentiality? Select two.

Options:

A.

Adhere to the CQI Professional Code of Conduct.

B.

Confirm the confidentiality arrangements with the auditee regarding the use of mobile devices/cameras.

C.

Discuss sensitive personal information with the guides appointed by the auditee.

D.

Remove audit evidence without the permission of the auditee.

E.

Share audit conclusions with competitor organisations.

Buy Now
Questions 30

You are a member of the audit team of a second-party audit of an organisation with 625 employees. The audit procedure recommends using sampling criteria which requires the review of the documented competence for 25 personnel. The audit team leader developed an audit plan allocating one hour to audit the Human Resources department (from 11:30 am to 12:30 pm). She told you that she could not allocate any additional time.

What would you do?

Options:

A.

Extend the audit until 1.00pm and ask for a quick lunch later.

B.

Plan to review less than 25 cases.

C.

Plan to review as many as possible and see if you can extend the audit duration by one day.

D.

Plan to miss lunch and review as many as possible.

Buy Now
Questions 31

You will lead a third-party audit next Monday on ABC, an organisation that provides services for cleaning windows from the outside of tall buildings. They work on demand, and usually have 4-5 orders per week. All documented information on these activities is kept at the central office.

On Friday evening, before the audit, you are informed by mail that customers cancelled all orders for the next week; therefore, the auditors will not have the chance to see them working at the customer's premises, but the field supervisors will be available at the ABC offices.

You have prepared the audit plan and the checklist. Choose the best action you would take:

Options:

A.

Start the audit on Monday at ABC's as planned, interviewing the functions that regularly work at the central office, and plan visits to ABC customers wherever they may be working during the following week.

B.

Ask the Certification Body you work for how to proceed with the audit.

C.

Start the audit on Monday as planned, interviewing the functions that regularly work at the central office, and visit another customer's premises they cleaned the week before.

D.

Complete the audit but ask the quality manager to clean some windows at the ABC's office, simulating the process they carry out at customers' premises.

Buy Now
Questions 32

Which quality management principle does an organization fulfill when it assesses risks, consequences, and impacts before taking action?

Options:

A.

Process approach

B.

Leadership

C.

Improvement

D.

Relationship management

Buy Now
Questions 33

In the context of a third-party audit, match the activity with the party responsible in relation to the audit process.

Options:

Buy Now
Questions 34

Which two of the following are included in the objectives of the 'Stage 1 initial certification audit'?

Options:

A.

To evaluate the performance of monitoring and reviewing activities.

B.

To evaluate the preparedness of the organisation for a Stage 2 audit.

C.

To evaluate the internal audit and management review processes.

D.

To review the quality manual.

E.

To make a decision on certification to ISO 9001:2015.

F.

To evaluate the operational processes of the organisation.

Buy Now
Questions 35

Technical experts must operate under the supervision of:

Options:

A.

The auditee

B.

An auditor

C.

The audit team leader only

Buy Now
Questions 36

Scenario 1: AL-TAX is a company located in California which provides financial and accounting services. The company manages the finances of 17 companies and now is seeking to expand their business even more The CEO of AL-TAX, Liam Durham, claims that the company seeks to provide top-notch services to their clients Recently, there were a number of new companies interested in the services provided by AL-TAX.

In order to fulfill the requirements of new clients and further improve quality, Liam discussed with other top management members the idea of implementing a quality management system (QMS) based on ISO 9001. During the discussion, one of the members of the top management claimed that the size of the company was not large enough to implement a QMS. In addition, another member claimed that a QMS is not applicable for the industry in which AL TAX operates. However, as the majority of the members voted for implementing the QMS. Liam initiated the project.

Initially, Liam hired an experienced consultant to help AL-TAX with the implementation of the QMS. They started by planning and developing processes and methods for the establishment of a QMS based on ISO 9001. Furthermore, they ensured that the quality policy is appropriate to the purpose and context of AL TAX and communicated to all employees. In addition, they also tried to follow a process that enables the company to ensure that its processes are adequately resourced and managed, and that improvement opportunities are determined.

During the implementation process, Liam and the consultant focused on determining the factors that could hinder their processes from achieving the planned results and implemented some preventive actions in order to avoid potential nonconformities Six months after the implementation of the QMS. AL-TAX conducted an internal audit. The results of the internal audit revealed that the QMS was not fulfilling all requirements of ISO 9001. A serious issue was that the QMS was not fulfilling the requirements of clause 5.1.2 Customer focus and had also not ensured clear and open communication channels with suppliers.

Throughout the next three years, the company worked on improving its QMS through the PDCA cycle in the respective areas. To assess the effectiveness of the intended actions while causing minimal disruptions, they tested changes that need to be made on a smaller scale. After taking necessary actions, AL-TAX decided to apply for certification against ISO 9001.

Based on the scenario above, answer the following question:

As stated in scenario 1, AL-TAX tested the effectiveness of the intended actions as part of the QMS improvement through the PDCA cycle. Which stage did it perform in this case?

Options:

A.

Do

B.

Check

C.

Act

Buy Now
Questions 37

Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.

A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC's top management and then drafted the audit conclusions.

In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.

Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.

Based on the scenario above, answer the following question:

The audit team delayed audit activities until DC’s top management submitted their action plans. Is this acceptable?

Options:

A.

No, the audit report should be prepared and submitted to the certification body prior to the submission of action plans by the auditee

B.

Yes, the audit report can be prepared once the auditee submits the action plans in cases of minor nonconformities

C.

Yes, DC’s top management promised the submission of action plans within a short period of time

Buy Now
Questions 38

Takitup is a small fabrication organisation that manufactures steel fencing, stairs and platforms for the construction sector. It has been certified to ISO 9001 for some time and has appointed a new Quality Manager. The audit plan during a surveillance audit covers the organisation's improvement actions and the auditor asks to see the most recent management review meeting minutes.

The auditor finds that the management review report records that none of the improvement actions set by the previous review has been realised for a second time. A new Quality Manager has been brought in at the middle management level to rectify the situation as the organisation is concerned that it might lose its certification.

Select three options that would provide evidence of conformance with clause 10.3 of ISO 9001.

Options:

A.

Outsource more processes to external providers

B.

Removing expensive external providers from the database.

C.

An increase in the number of quality staff.

D.

A quality objective to achieve lower reject rates by quality control.

E.

Considering results from the analysis of the effectiveness of corrective actions to determine improvement opportunities.

F.

The certification body auditor reporting fewer nonconformities.

G.

An enhanced customer satisfaction survey score than in the previous year.

Buy Now
Questions 39

Scenario 2:

Bell is a Canadian food manufacturing company that operates globally. Their main products include nuts, dried fruits, and confections. Bell has always prioritized product quality and has maintained a good reputation for many years. However, the company's production error rate increased significantly, leading to more customer complaints.

To increase efficiency and customer satisfaction, Bell implemented a Quality Management System (QMS) based on ISO 9001. The top management established a QMS implementation team comprising five middle managers from various departments, including Leslie, the quality manager.

Leslie was responsible for assigning responsibilities and authorities for QMS-related roles. He also suggested including a top management representative in the QMS team, but top management declined due to other priorities.

The team defined the QMS scope as:

"The scope of the QMS includes all activities related to food processing."

Leslie established a quality policy and presented it to the team for review before top management approval. Top management also proposed a new strategy for handling customer complaints, requiring biweekly customer surveys to monitor customer perceptions.

Which statement related to the last paragraph of scenario 2 is correct?

Options:

A.

Customer surveys are the best method for obtaining and monitoring customer perceptions.

B.

Top management demonstrated leadership and commitment with respect to customer satisfaction.

C.

Customer surveys should be conducted every week to have a clear understanding of the needs and expectations of customers.

D.

Customer satisfaction is only measured through complaints, making surveys unnecessary.

Buy Now
Questions 40

Which action indicates that an organization is meeting the requirements of ISO 9001 regarding nonconforming outputs?

Options:

A.

Retaining documented information only on the actions taken.

B.

Verifying conformity to the applicable requirements prior to correction of the nonconforming outputs.

C.

Taking appropriate action to nonconforming products and services detected after the delivery of products, during or after the provision of services.

D.

Allowing employees to handle nonconformities based on their own judgment without structured procedures.

Buy Now
Questions 41

You are carrying out an annual audit at an organisation that offers home security services. You are interviewing the Quality Manager (QM)

You: "Would you tell me about your management review process?"

QM: "The senior management team plans to review the management system every six months. The review follows a set agenda and records are maintained."

You: "May I see the records from the last two management reviews?"

Narrative: The Quality Manager gives you the latest record, which shows the last management review took place nine months ago.

The Quality Manager then gives you the previous management review record, which took place one year before the latest review.

You: "Are there any other review reports in the last two years?

QM: "No, these are the only ones."

Options:

Buy Now
Questions 42

Below are four of the seven principles on which ISO 9000 series are based. Match a potential benefit to each of the quality management principles (QMP).

Options:

Buy Now
Questions 43

You are conducting an ISO 9001 audit of a Materials Recycling Facility (MRF). The organisation processes

waste plastics into raw materials for plastic bottle manufacturers. You reach the manual picking line where operators are removing contaminant materials from incoming products, such as plastic bags, plastic film and badly contaminated items that would compromise the recycling process. You interview the line supervisor.

You: "Why are these plastic items being rejected at this stage?"

Auditee: "They do not meet our processing standards."

You: "What is the reason for that?"

Auditee: "These items are likely to damage the machinery down the line. They can also compromise our

quality standards. We need to protect our reputation for good quality output materials."

You: "What happens to the rejected items?"

Auditee: "Some get melted down in another process later on and some are disposed of as waste products that cannot be recycled."

You: "What happens to the waste products?"

Auditee: "I'm not sure. I suppose they go to landfill."

Which two. of the following actions would you take to investigate further?

Options:

A.

Check the process for handling nonconforming items.

B.

Ask to review the percentage of waste materials.

C.

Find out if operators have regular hearing tests.

D.

Determine what happens to the waste products.

E.

Ask about operator PPE (Personal Protective Equipment).

F.

Determine whether there are quality objectives for reducing rejected material.

Buy Now
Questions 44

Whistlekleen is a national dry cleaning and laundry company with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. You find that 80% of complaints originate from five shops in the same region. Most of these complaints relate to damage to customer laundry. The Quality Manager tells you that these are the oldest shops in the company. The cleaning equipment needs replacing but the company cannot afford it at the moment. You learn

that the shop managers were told to dismiss most of the claims on the basis of the poor quality of the laundered materials.

On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.

When reviewing the customer complaint file, you find that the organisation is facing a legal dispute with a customer over damage to an expensive cashmere coat.

Select the best option for how this should be handled by the Quality Management System.

Options:

A.

Settle the court case by negotiation with the customer.

B.

Report the situation to the customer with suggested remedial action.

C.

Make an offer to replace the coat with a new one.

D.

Give an explanation to the customer of what went wrong.

Buy Now
Questions 45

During a second-party audit of a dairy farm (by a potential customer) complying with ISO 9001:2015, the auditor verifies that there is large variability in the daily production of the milking yard. The current agreement with their only customer is to provide 2,000 litres per day. However, in the last two years, they have noticed an increasing variability in daily production.

If they produce less than 2,000 litres, they are penalised with a fine of 1.5 pesos for every litre that they do not provide. If they produce more than 2,000 litres, they use the extra milk to feed the pigs.

This process has been in operation for decades. The dairy farm was founded by the grandfather of the current owners, who did not want to alter the established practices.

The auditor raises a nonconformity on the basis that the process is not under control (Clause 8.1).

If you had been the auditor, which one of the following actions would you have accepted?

Options:

A.

Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer.

B.

Apply the existing process of addressing the risks and opportunities of milk production.

C.

Retain the current contract and try to sell the occasional surplus milk to a second customer.

D.

Analyse the daily dispatch of milk for 7 days to determine its variability.

Buy Now
Questions 46

You are carrying out an audit at a single-site organisation seeking certification to ISO 9001 for the first time. The organisation manufactures

cosmetics for major retailers.

You are interviewing the Manufacturing Manager (MM).

You: "I would like to begin by looking at the cleaning controls."

MM: "We record the cleaning of the equipment at the end of every batch. This document details the minimum cleaning frequency and the

procedures to follow for all areas and each item of equipment. The person who carries out the cleaning puts their initial on the document and records

the time and date alongside."

Narrative: You sample production records over 3-days and note down evidence of nonconformity as per the table below.

Options:

Buy Now
Questions 47

You are carrying out an audit at a single-site organisation seeking certification to ISO 9001 for the first time. The

organisation manufactures cosmetics for major retailers and the name of the retailer supplied appears on the product

packaging. Sales turnover has increased significantly over the past five years. The organisation uses a software programme called SWIFT, which is used to record sales, plan production, purchase supplies, print despatch notes, track new product development, perform traceability exercises, carry out mass balance checks, raise invoices, create budgets, and support financial control.

You are nearing the end of the audit and you are reviewing your audit notes. You notice a recurring trend concerning the SWIFT database as shown below:

You ask the Quality Manager to explain how the SWIFT database is controlled. You learn that the Operations Director is

responsible for determining and progressing SWIFT software updates. You decide to meet the Operations Director (OD).

You: "Good afternoon."

OD: "Good afternoon."

You: "What responsibility do you have concerning the SWIFT database?"

OD: "I maintain it. If anyone wishes to propose an update to the database, they send me an email with

details of their proposal. I then either process the database update myself, or I send the request to the

consultant who designed the database 20 years ago. The necessary software changes are made, and the

amended software is immediately released to users."

You: "Would you explain how the software amendments are controlled?"

OD: "Of course. I personally update every computer myself."

You: "Do you inform the database users of the changes?"

OD: "No I don't. They find out for themselves by using the software, or they come to see me if they have

any questions."

You: "How do you ensure that the database users use the latest version?"

OD: "That's easy, I update every computer myself."

You: "During the audit, I noted there were several versions of SWIFT in use (you refer to your audit

notes)."

OD: "I know. That's because some versions work better than others, and depending on user needs and

experiences, we allow users to revert to using an earlier version if they find it works better for them."

Based on the scenario, which two of the following statements are true? There is evidence of

nonconformity with a requirement defined in ...

Options:

A.

clause 7.1.3 Infrastructure

B.

... clause 7.1.4 Environment for the operation of processes

C.

clause 7.5.1 Documented information - General

D.

... clause 7.5.2 Documented information - Creating and updating

E.

... clause 7.5.3 Control of documented information

Buy Now
Questions 48

Scenario 1: AL-TAX is a company located in California which provides financial and accounting services. The company manages the finances of 17 companies and now is seeking to expand their business even more The CEO of AL-TAX, Liam Durham, claims that the company seeks to provide top-notch services to their clients Recently, there were a number of new companies interested in the services provided by AL-TAX.

In order to fulfill the requirements of new clients and further improve quality, Liam discussed with other top management members the idea of implementing a quality management system (QMS) based on ISO 9001. During the discussion, one of the members of the top management claimed that the size of the company was not large enough to implement a QMS. In addition, another member claimed that a QMS is not applicable for the industry in which AL TAX operates. However, as the majority of the members voted for implementing the QMS. Liam initiated the project.

Initially, Liam hired an experienced consultant to help AL-TAX with the implementation of the QMS. They started by planning and developing processes and methods for the establishment of a QMS based on ISO 9001. Furthermore, they ensured that the quality policy is appropriate to the purpose and context of AL TAX and communicated to all employees. In addition, they also tried to follow a process that enables the company to ensure that its processes are adequately resourced and managed, and that improvement opportunities are determined.

During the implementation process, Liam and the consultant focused on determining the factors that could hinder their processes from achieving the planned results and implemented some preventive actions in order to avoid potential nonconformities Six months after the implementation of the QMS. AL-TAX conducted an internal audit. The results of the internal audit revealed that the QMS was not fulfilling all requirements of ISO 9001. A serious issue was that the QMS was not fulfilling the requirements of clause 5.1.2 Customer focus and had also not ensured clear and open communication channels with suppliers.

Throughout the next three years, the company worked on improving its QMS through the PDCA cycle in the respective areas. To assess the effectiveness of the intended actions while causing minimal disruptions, they tested changes that need to be made on a smaller scale. After taking necessary actions, AL-TAX decided to apply for certification against ISO 9001.

Based on the scenario above, answer the following question:

Which of the following misconceptions about ISO 9001 was present in scenario 1?

Options:

A.

A QMS based on ISO 9001 requires many resources and is time-consuming.

B.

A QMS based on ISO 9001 is only applicable to organizations producing tangible goods.

C.

A QMS based on ISO 9001 is a complex task and requires a lot of documentation.

Buy Now
Questions 49

You, as auditor, are in dialogue with the quality lead and managing director of a small business that supplies specialist laboratory equipment and furniture.

You: "I'd like to look at how you manage change in the organisation. What changes have you made as a

business, say, over the last 12 months?"

Auditee: "We have made some strategic changes, the main one being that we no longer manufacture our

own products in house."

You: "That sounds like quite a significant change. What has been the impact of that?"

Auditee: "We now mainly sell other manufacturers' products, under their brand names, and have outsourced

manufacture of our own brand products to one of our suppliers. Unfortunately, we had to make six members

of our staff redundant. This represents about 20% of our workforce, so this has been quite a challenging

time."

You: "I'm sure. What were the reasons for making the change?"

Auditee: "Our manufacturing section was a small operation, and we struggled to cope with fluctuations in

demand. During busy periods, we found it hard to meet lead times, and in quiet periods we had staff with

little to do. This was having an impact on customer satisfaction and meant we had to charge premium prices

that made our product uncompetitive."

You: "How did you go about the change?"

The auditor asks to speak to the purchasing manager about the selection of the subcontractor to

manufacture the company's own brand products.

You: "How did you choose a supplier to manufacture your products?"

Auditee: "We have had a long-term relationship with a supplier ABC Ltd - we gave them our design

drawings, got them to complete a supplier questionnaire and run a couple of trial batches for us. We were

happy with the result and we have used them ever since."

ISO 9001:2015, clause 8.4.1 outlines situations when controls need to be applied to externally provided processes, products and services. Which one of the following situations is applicable to this scenario?

Options:

A.

Products and services for which the customer(s) supplies materials

B.

A process or part of a process is provided by an external provider as a result of a decision by the organisation.

C.

Products and services are provided directly to the customer(s) by external providers on behalf of the organisation.

D.

Raw materials from external providers are intended for incorporation into the organisation's own products.

Buy Now
Questions 50

You are carrying out an audit at an organisation seeking certification to ISO 9001 for the first time. The organisation offers regulatory consultancy services to manufacturers of cosmetics. The business operates from ten regional offices.

You are nearing the end of the audit and need to decide if sufficient evidence of top management leadership and commitment with respect to the quality management system has been gathered.

Which four of the following would demonstrate top management leadership and commitment with respect to the quality management system?

Options:

A.

Approving company car budgets for the fiscal year

B.

Briefing staff on the development of an improvement culture

C.

Chairing management review meetings

D.

Conducting staff disciplinary meetings

E.

Investing time and money in corrective actions arising from nonconformities

F.

Not attending audit closing meeting

G.

Promoting the importance of following procedures

Buy Now
Questions 51

Which of the following is correct with regard to the internal audit?

Options:

A.

It considers only the effectiveness of the QMS

B.

It has no advisory role within the organization for the improvement of the QMS

C.

It may be conducted on an ongoing basis

Buy Now
Questions 52

In the context of a third-party certification audit, it is very important to have effective communication. Which is not the responsibility of the audit team leader?

Options:

A.

If audit objectives are unattainable, reporting the reasons to the accreditation body.

B.

Planning formal communication arrangements, so an auditee can communicate with the auditor any time during the audit.

C.

Confirming formal communication channels between the audit team and the auditee during the opening meeting.

D.

Communicating the progress, any significant findings and any concerns to the auditee and audit client, as appropriate.

Buy Now
Questions 53

For a third-party, match the Activity with the Responsibility for conducting it.

Options:

Buy Now
Questions 54

Among others, what does Clause 4.4 (Quality Management System and Its Processes) of ISO 9001 require from organizations?

Options:

A.

To change the QMS quarterly

B.

To review the QMS annually

C.

To continually improve the QMS

D.

To conduct a QMS gap analysis every two years

Buy Now
Questions 55

Which one of the following options best describes the purpose of a Stage 1 third-party audit?

Options:

A.

To determine the auditees understanding of ISO 9001.

B.

To get to know the organisation's customers.

C.

To learn about the organisation's procurement processes.

D.

To introduce the audit team to the client.

Buy Now
Questions 56

What is a combined audit?

Options:

A.

Two or more management systems audited together at a single auditee.

B.

Two or more auditing organizations cooperating to audit a single auditee.

C.

Two or more management systems audited simultaneously at several auditees.

Buy Now
Questions 57

Put the following steps of a third-party audit into the correct sequence in which they happen.

Options:

Buy Now
Questions 58

Which two of the following aspects of a quality management system must the organisation continually improve?

Options:

A.

Suitability

B.

Adaptability

C.

Effectiveness

D.

Responsiveness

E.

Efficiency

F.

Applicability

Buy Now
Questions 59

Which type of audit risk is the risk that a significant defect may occur in the QMS, although the organization has internal control mechanisms in place?

Options:

A.

Control risk.

B.

Inherent risk.

C.

Detection risk.

D.

Operational risk.

Buy Now
Questions 60

Match the process descriptions below to the process names:

Options:

Buy Now
Questions 61

A small cleaning services organisation is about to start work on a hospital cleaning contract for the local Health Trust. You,

as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract

requires that a cleaning plan is produced.

You: "How was the cleaning plan for the contract developed?"

Service Manager: "We have a basic template that covers the materials, labour requirements and cleaning methods to be

employed. Some of that is specified by the customer."

You: "How does the plan deal with locations like the intensive care wards and the operating theatres, which are included

in the contract?"

Service Manager: "The basic plan covers general wards, but we will do more frequent cleaning in those areas if the

hospital requests it."

You: "Are you aware of the regulatory requirements for cleaning standards in hospitals?"

Service Manager: "No. We depend on the hospital to look after that side of things in the contract."

You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001.

You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the

cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was

substituted to that specified in the contract. At the follow-up audit, the corrective action proposed was to

"obtain a concession from the Health Trust for use of the new chemical."

Which one of the following options is the reason why you did not accept this action taken?

Options:

A.

Staff have not been trained in the use of the new chemical.

B.

The action assumes that the Health Trust will agree to the change.

C.

The process for making changes to the contract has not been addressed.

D.

The substitute chemical has not been used before in the Health Trust.

E.

The substitute chemical may not be as effective as the original.

Buy Now
Questions 62

You are conducting an audit at an organisation seeking certification to ISO 9001 for the first time. The organisation offers health and safety training to customers. Training courses are offered either as open courses, delivered at a public venue, or online, or as courses that are tailored to meet specific requirements. The business operates from a single office and those who deliver the training are either full-time employees or subcontractors.

You have gathered audit evidence as outlined below. Match the ISO 9001 Clause 8 extract to the audit evidence.

Options:

Buy Now
Questions 63

What should the auditor document during the Stage 1 audit?

Options:

A.

The main processes of the auditee

B.

The interviews with the auditee’s employees

C.

The observations that could result in nonconformities during the on-site audit

Buy Now
Questions 64

Scenario 7: POLKA is a car manufacturing company based in Stockholm, Sweden. The company has around 14,000 employees working in different sectors which help with the design, painting, assembling, and test drives of the final product. The company is widely known for its qualitative products and affordable prices. In order to retain their reputation, POLKA implemented a quality management system (QMS) based on ISO 9001.

Before applying for certification, the company decided to conduct an internal audit to check whether there are any nonconformities in their QMS and if the requirements of ISO 9001 are being fulfilled. The top management appointed Sean, the internal auditor, as the team leader of the internal audit team. Sean required from the top management to have unrestricted access to the employees and executives of POLKA and to the documented information. Furthermore, Sean required to establish a team with a large number of auditors, considering the size and the complexity of the organization. The top management of POLKA agreed with Sean's requirements.

The top management, in cooperation with Sean, assigned 10 more employees to the audit team. Following that. Sean planned the audit activities and assigned the roles and responsibilities to each auditor. They began by interviewing employees of different manufacturing departments to check whether they are aware of the process of the QMS implementation. While conducting these activities, one of the auditors asked Sean for permission to audit the department in which he worked on a daily basis, as he was very familiar with the processes of the department.

Along the way, the teams findings showed that the staff were trained, documented information was updated, and the QMS fulfilled the requirements of ISO 9001. The internal audit took three weeks to complete, and on the last week the audit team held a final meeting

The team shared their results and together drafted the audit report This report was submitted to the top management of the company. The report was maintained as documented information, and was available to the relevant interested parties.

Based on the scenario above, answer the following question:

Based on Scenario 7, the team worked together to draft the final audit report. Is this acceptable?

Options:

A.

Yes, audit team members should contribute to drafting one general report for the findings and conclusions

B.

No, audit team members should draft separate reports for their findings and conclusions

C.

No, it is the responsibility of the audit team leader to draft the audit report

Buy Now
Questions 65

Which of the following three options could be considered potential threats to impartiality in an audit context?

Options:

A.

Competence

B.

Experience

C.

Familiarity

D.

Intimidation

E.

Self-audit

Buy Now
Exam Name: QMS ISO 9001:2015 Lead Auditor Exam
Last Update: Jun 15, 2025
Questions: 217
ISO-9001-Lead-Auditor pdf

ISO-9001-Lead-Auditor PDF

$29.75  $84.99
ISO-9001-Lead-Auditor Engine

ISO-9001-Lead-Auditor Testing Engine

$35  $99.99
ISO-9001-Lead-Auditor PDF + Engine

ISO-9001-Lead-Auditor PDF + Testing Engine

$47.25  $134.99