Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

FIDIC CCM Dumps Questions Answers

CCM exam

Get CCM PDF + Testing Engine

Certified Contract Manager

Last Update Sep 27, 2025
Total Questions : 100 With Comprehensive Analysis

Why Choose ClapGeek

  • 100% Low Price Guarantee
  • 100% Money Back Guarantee on Exam CCM
  • The Latest Information, supported with Examples
  • Answers written by experienced professionals
  • Exam Dumps and Practice Test Updated regularly
$40.5  $134.99

Bundle Includes

Desktop Practice
Test software
+
Questions &
Answers (PDF)
CCM pdf

CCM PDF

Last Update Sep 27, 2025
Total Questions : 100 With Comprehensive Analysis

$25.5  $84.99
CCM Engine

CCM Testing Engine

Last Update Sep 27, 2025
Total Questions : 100

$30  $99.99

How Does ClapGeek Serve You?

Our FIDIC CCM practice test is the most reliable solution to quickly prepare for your FIDIC Designing FIDIC Azure Infrastructure Solutions. We are certain that our FIDIC CCM practice exam will guide you to get certified on the first try. Here is how we serve you to prepare successfully:
CCM Practice Test

Free Demo of FIDIC CCM Practice Test

Try a free demo of our FIDIC CCM PDF and practice exam software before the purchase to get a closer look at practice questions and answers.

CCM Free Updates

Up to 3 Months of Free Updates

We provide up to 3 months of free after-purchase updates so that you get FIDIC CCM practice questions of today and not yesterday.

CCM Get Certified in First Attempt

Get Certified in First Attempt

We have a long list of satisfied customers from multiple countries. Our FIDIC CCM practice questions will certainly assist you to get passing marks on the first attempt.

CCM PDF and Practice Test

PDF Questions and Practice Test

ClapGeek offers FIDIC CCM PDF questions, web-based and desktop practice tests that are consistently updated.

Clapgeek CCM Customer Support

24/7 Customer Support

ClapGeek has a support team to answer your queries 24/7. Contact us if you face login issues, payment and download issues. We will entertain you as soon as possible.

Guaranteed

100% Guaranteed Customer Satisfaction

Thousands of customers passed the FIDIC Designing FIDIC Azure Infrastructure Solutions exam by using our product. We ensure that upon using our exam products, you are satisfied.

FIDIC CCM Last Week Results!

10

Customers Passed
FIDIC CCM

89%

Average Score In Real
Exam At Testing Centre

90%

Questions came word by
word from this dump

Certified Contract Manager Questions and Answers

Questions 1

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

Questions 2

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

Options:

A.

The Commencement Date

B.

The date of the Taking Over Certificate

C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate

D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates

Questions 3

Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]

(2 correct answers apply)

Options:

A.

Continuing effect claims shall be noticed in the same way as "normal" claims, within 28 days after the Claiming Party became aware of the event or circumstance.

B.

In case the Employer is the Claiming Party, then he/she is not obliged to submit interim claims.

C.

In case the Contractor is the Claiming Party, when he/she misses to submit even just a single interim claim, then his/her entitlement is lost.

D.

In general, a fully detailed Claim has to be submitted within 84 days after becoming aware of the event giving rise to the claim.