Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

CCM Certified Contract Manager Questions and Answers

Questions 4

Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]

(2 correct answers apply)

Options:

A.

Continuing effect claims shall be noticed in the same way as "normal" claims, within 28 days after the Claiming Party became aware of the event or circumstance.

B.

In case the Employer is the Claiming Party, then he/she is not obliged to submit interim claims.

C.

In case the Contractor is the Claiming Party, when he/she misses to submit even just a single interim claim, then his/her entitlement is lost.

D.

In general, a fully detailed Claim has to be submitted within 84 days after becoming aware of the event giving rise to the claim.

Buy Now
Questions 5

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 6

Which two statements are true under the FIDIC Red Book (edition 1999)?

(Choose all of the correct answers — multiple possibilities)

Options:

A.

The Performance Certificate is deemed to constitute the acceptance of the Works.

B.

The Performance Certificate constitutes acceptance of the Works and full performance of all obligations of each Party.

C.

The Engineer shall issue the Performance Certificate within 28 days at the latest: by the end of the Defects Notification Periods, and once the Contractor has supplied all the Contractor's Documents and completed and tested all Works including remedying any defects in accordance with the Contract.

D.

The Performance Certificate is deemed to be issued on fulfilment of certain conditions stated in the respective Sub-Clause.

Buy Now
Questions 7

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 8

Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

FIDIC Conditions of Contract for Construction ("Red Book").

B.

FIDIC Conditions of Contract for Plant and Design Build ("Yellow Book").

C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book").

Buy Now
Questions 9

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back-to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:

"Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted."

What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?

Options:

A.

I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.

B.

I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.

C.

I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer's Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even w

D.

I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer's Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to C

Buy Now
Questions 10

What does discharge confirm under the FIDIC Red Book (edition 1999)?

Options:

A.

It confirms interim settlement of all money due to the Contractor

B.

It confirms full and final settlement of all money due to the Contractor.

C.

It confirms the immediate end to the Contract unconditionally whenever issued.

D.

None of the above three statements is correct.

Buy Now
Questions 11

Which two statements reflect an INCORRECT application of a Golden Principle?

Options:

A.

Any deletions of General Conditions (GC) must be replaced with Particular Conditions (PC) that cover the same scope, and do not leave any roles, duties, obligations, rights, and risk allocation undefined.

B.

When applying the FIDIC Red Book or Yellow Book, the Commencement Date shall be within 60 days after the Contractor receives the Letter of Acceptance, in lieu of 42 days.

C.

The Contractor's right to suspend work (or reduce the rate of work) effective after giving not less than 3 months (in lieu of 21 days) notice to the Employer.

D.

Deleting all the clauses in the General Conditions that refer to the DAAB/DAB.

Buy Now
Questions 12

You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

Options:

A.

The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.

B.

The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer's Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.

C.

The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.

D.

The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.

Buy Now
Questions 13

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.

B.

No, because Employers never have specific procurement rules.

C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.

D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.

Buy Now
Questions 14

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

Options:

A.

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.

The Contractor cannot terminate the Contract.

C.

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

Buy Now
Questions 15

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.

B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.

C.

Any amounts to be added and deducted for changes in legislation and changes in cost.

D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.

Buy Now
Questions 16

Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

Options:

A.

If the Contract Price is to be adjusted for rises and falls in the cost of labour, the Contractor is entitled to compensation in such a way that all rises and falls in the costs are compensated fully.

B.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

C.

If Particular Conditions provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8, it can only apply to rises or falls in the costs of labour and Goods.

D.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. Only the Base Date can be taken as the date from which the adjustment should be calculated from.

Buy Now
Questions 17

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

Options:

A.

Yes

B.

No

Buy Now
Questions 18

You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".

For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?

Options:

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.

Buy Now
Questions 19

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that "a Variation shall" be executed on a daywork basis.

Buy Now
Questions 20

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

Options:

A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor's Representative or Employer's Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

Buy Now
Questions 21

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)

Options:

A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.

B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.

C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.

D.

Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.

Buy Now
Questions 22

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

Options:

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.

Buy Now
Questions 23

Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]

Choose all of the correct answers (multiple possibilities).

Options:

A.

Since the design was approved by the Engineer, the Contractor might not be found responsible for such discrepancy, hence, to be fully compensated.

B.

In this situation, the whole of the varied works should be removed, and the original technical content reinstated.

C.

The Contractor shall immediately rectify, ensuring, that the varied work fully complies with the prevailing standards.

D.

In case it is necessary, the Contractor shall prepare designs for works subject to the Value Engineering, hence, it is up to the Contractor to ensure that the works are fit for the purposes, including that the designs are correct, regardless of any approval or "no-objection" of the Engineer.

Buy Now
Questions 24

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Buy Now
Questions 25

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

Options:

A.

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

All key delivery dates of Plant and Materials.

Buy Now
Questions 26

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

Options:

A.

True

B.

False

Buy Now
Questions 27

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

Options:

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor's failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer's response to the Contractor's submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer's final decision on the quantum.

D.

It is the Employer's Representative who must first respond to the claim by the Contractor.

E.

The Engineer's response to a claim by the Contractor is final and binding upon the Employer.

Buy Now
Questions 28

In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]

Choose all of the correct answers (multiple possibilities).

Options:

A.

... the Contractor may send a Notice to the Engineer, that the subject of the Variation was Unforeseeable (having regard to the scope and nature of the Works), hence, the Contractor is not to start implementing the varied work promptly.

B.

... the Contractor is required to commence implementing the varied works and take records of all the details ( ... regarding the details of the varied works executed, expenditures incurred, and impact on progress etc.)

C.

... the Contractor is required to commence implementing the varied works even if it would pose immediate hazard to the safety of public areas surrounding the Site

D.

... the Contractor within 28 days after receiving such instruction shall submit to the Engineer a description of the varied work, a programme for its execution and a proposal for adjustment of the Contract Price.

E.

... the Contractor is not bound to start implementing the varied works right up until the price for the varied works is fully agreed (or determined)

Buy Now
Questions 29

In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)

Options:

A.

The Engineer

B.

The Engineer's Resident Engineer

C.

The Employer

D.

The Employer's Representative

Buy Now
Questions 30

Giving "Notice" .... [2017 edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

... is not a compulsory obligation, but "highly recommended".

B.

... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.

C.

... is a special obligation for the Engineer only, in order to enable him/her to manage the implementation of the contract.

D.

... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Aug 17, 2025
Questions: 100
CCM pdf

CCM PDF

$29.75  $84.99
CCM Engine

CCM Testing Engine

$35  $99.99
CCM PDF + Engine

CCM PDF + Testing Engine

$47.25  $134.99