Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

CCM Certified Contract Manager Questions and Answers

Questions 4

Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

Options:

A.

If the Contract Price is to be adjusted for rises and falls in the cost of labour, the Contractor is entitled to compensation in such a way that all rises and falls in the costs are compensated fully.

B.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

C.

If Particular Conditions provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8, it can only apply to rises or falls in the costs of labour and Goods.

D.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. Only the Base Date can be taken as the date from which the adjustment should be calculated from.

Buy Now
Questions 5

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Buy Now
Questions 6

In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 7

The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.

Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 8

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both ' Notice ' and ' Other Communications ' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Buy Now
Questions 9

Applying FIDIC Silver Book (edition 1999), which one of the following elements shall not form part of the time Programme/revised programme?

Options:

A.

The intended order of the works.

B.

The sequence and timing of inspections and tests.

C.

The remedial work (if any) instructed under Sub-Clause 7.6.

D.

Review periods under Sub-Clause 5.2.

Buy Now
Questions 10

In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an " ad-hoc " basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)

Options:

A.

Ad-hoc DAAB

B.

DAB

C.

Ad-hoc DB

D.

Ad-hoc arbitration

Buy Now
Questions 11

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 12

Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?

Options:

A.

The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).

B.

The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.

C.

Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.

Buy Now
Questions 13

(Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?)

Options:

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer’s Requirements very well to see if the Works can be built on that location according to the Employer’s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer’s Requirements very thoroughly after the contract closes and see if the Employer’s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999; in both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer’s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after the contract close to report on any errors, mistakes or conflicts in the Employer’s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; the Contractor has to review and verify the Employer’s Requirements more strictly before submitting the tender.

Buy Now
Questions 14

Giving " Notice " .... [2017 edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

... is not a compulsory obligation, but " highly recommended " .

B.

... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.

C.

... is a special obligation for the Engineer only, in order to enable him/her to manage the implementation of the contract.

D.

... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.

Buy Now
Questions 15

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

Options:

A.

True

B.

False

Buy Now
Questions 16

(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 17

Which one of the following statements best describes the requirements of Time for Completion?

Options:

A.

This is the Contractor ' s fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.

B.

This is the Contractor ' s fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

C.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

D.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.

Buy Now
Questions 18

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor failed to renew the Tender Security.

B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.

C.

The Employer had submitted a claim under Sub-Clause 20.2.

D.

The Engineer had issued instruction to replace part of the Works.

E.

The Contractor failed to extend the validity of the Performance Security.

Buy Now
Questions 19

(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))

Options:

A.

The Bill of Quantities

B.

The Specifications

C.

The Breakdown of Lump-Sum

D.

Schedule of Subcontractors

E.

The form of Contract Agreement

Buy Now
Questions 20

(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 21

(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))

Options:

A.

In all these cases, the stakeholder not performing a required action within the allocated time limit loses all of his/her related rights that he/she otherwise would have in relation to this matter.

B.

If a Party fails to perform an obligation within the allocated time limit, then the failing party shall pay damages to the other Party.

C.

In these cases, there is a " deemed " outcome if the stakeholder does not take action within the pre-set period of time – all enabling to secure continuity of contractual processes.

D.

A Party ' s failure to perform an obligation within the allocated time limit would mean that the Engineer ' s or Employer’s decision becomes automatically binding.

Buy Now
Questions 22

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer ' s financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer ' s obligations under the Contract.

Buy Now
Questions 23

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 24

(Under FIDIC Red and Yellow Books (both editions) the Engineer must have received technical education. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 25

Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.

Options:

A.

Provisions of the General Conditions are deleted and replaced in the Particular Conditions solely by the words " not used " .

B.

All deletions of a General Conditions are replaced with new Particular Conditions that cover the same scope.

C.

Clarifications to the meaning of tender documents together with answers to tenderers ' inquiries made during the tender period by the Employer should be e-mailed in a Excel table in both PDF and XLS file format.

D.

The clarifications to the Contract given during the tender period are never to be attached to the Contract, as such clarifications are reflected by amending the Particular Conditions.

Buy Now
Questions 26

(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)

Options:

A.

Contractor

B.

Engineer

C.

Employer

Buy Now
Questions 27

(Golden Principle 2 states that " The Particular Conditions must be drafted clearly and unambiguously. " Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)

Options:

A.

Clarifications to the meaning of tender documents together with answers to tenderers’ inquiries made during the tender period by the Employer can be inconsistent. If Sub-Clause 1.5 does not provide for the right order, this Sub-Clause can be amended explicitly or implicitly, and this can be done through any of the documents mentioned in Sub-Clause 1.5.

B.

When clarifications are given during the tender period, which might impact several general conditions, it is not necessary to amend all these conditions through the Particular Conditions or to consider which exact general conditions require amendment, as such clarifications are deemed to be self-explanatory.

C.

Modifications made to the Conditions of Contract during tender negotiations that were only documented in emails between the Parties can be part of the Contract as long as those emails are subsequently included in the List of Contract documents. In such a case, it is not necessary to incorporate those modifications in, for instance, the Particular Conditions.

D.

In the Particular Conditions, all changes to the General Conditions must be clearly identified by reference to specific Sub-Clause numbers. Additionally, the Particular Conditions Sub-Clauses must clearly indicate the relationship between the newly introduced text and the corresponding General Conditions Sub-Clauses’ original text, e.g., addition, omission, replacement, or amendment.

Buy Now
Questions 28

Which one of the following claim events does NOT allow profit?

Options:

A.

Under the Construction Contract, interference by the Employer with Tests on Completion.

B.

Under the Construction Contract, the Engineer ' s delay in supplying drawings or issuing instructions.

C.

Under the Construction Contract, the failure of the Employer to give right of access to the site.

D.

Under the Construction Contract, the relevant authority had unnecessarily delayed the approval.

E.

Under the Plant and Design-Build Contract, errors in the Employer ' s requirements.

Buy Now
Questions 29

The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 30

Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?

Options:

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer ' s Requirements very well to see if the Works can be built on that location according to the Employer ' s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer ' s Requirements very thoroughly after the contract closes and see if the Employer ' s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999. In both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer ' s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after contract close to report on any errors, mistakes or conflicts in the Employer ' s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; Contractor has the opportunity to report on any errors, mistakes or conflicts in the Employer ' s Requirements and for Employer to change it; for after contract cl

Buy Now
Questions 31

Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?

Options:

A.

Yellow Book

B.

Red Book

C.

Silver Book

D.

Yellow or Silver Book

Buy Now
Questions 32

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 33

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

Options:

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Buy Now
Questions 34

(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Contractor shall obtain the Engineer’s and the Employer’s prior consent to all Subcontractors.

B.

If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the Engineer.

C.

The Contractor shall not be responsible for the acts or defaults of any Subcontractor.

D.

The Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract.

Buy Now
Questions 35

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

" In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction. "

What GP(s) is/are breached?

Options:

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3

Buy Now
Questions 36

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:

A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.

B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.

C.

Yes, because otherwise the Contractor doesn ' t have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.

D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor ' s Documents in the Employer ' s Requirements, as stated in Sub-Clause 5.2.

Buy Now
Questions 37

(Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

An attempt to reach an amicable settlement is a mandatory requirement before an Engineer ' s ruling can be referred to a DAAB.

B.

A decision by a DAAB is not final and binding on the Parties until it is confirmed by an arbitration award.

C.

The FIDIC Red Book ' s General Conditions specify a standing DAAB.

D.

A DAAB member nominated by one of the Parties must be agreed by the other Party.

E.

If the Employer or the Contractor fails to notify its dissatisfaction with an Engineer ' s ruling within the specified time, the DAAB ' s decision is final and binding.

Buy Now
Questions 38

(Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)? Choose all correct answers.)

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that a Variation shall be executed on a daywork basis.

Buy Now
Questions 39

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

Options:

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor ' s failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer ' s response to the Contractor ' s submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer ' s final decision on the quantum.

D.

It is the Employer ' s Representative who must first respond to the claim by the Contractor.

E.

The Engineer ' s response to a claim by the Contractor is final and binding upon the Employer.

Buy Now
Questions 40

(Under FIDIC Red Book (edition 1999) a notice may be delivered to which two addresses?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The address stated in the Contract Data.

B.

The address provided for by the recipient of the notice.

C.

The address of the Site.

D.

The address of the Contractor ' s Representative.

Buy Now
Questions 41

(Which two FIDIC Books (edition 2017) should especially be considered for use if the Employer needs the Contractor to take responsibility for the design and execution of the project. The construction will involve substantial work underground or work in other areas which tenderers cannot inspect.

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Yellow Book

B.

Red Book

C.

Silver Book by amending Sub-Clause 4.12 in the Particular Conditions

D.

Silver Book without amending Sub-Clause 4.12 in the Particular Conditions

Buy Now
Questions 42

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.

B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.

C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.

D.

Receipt of a statement and supporting documents.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 5, 2026
Questions: 140
CCM pdf

CCM PDF

$25.5  $84.99
CCM Engine

CCM Testing Engine

$30  $99.99
CCM PDF + Engine

CCM PDF + Testing Engine

$40.5  $134.99