PMP Project Management Professional (2025 Version) Questions and Answers

Questions 4

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectives

are verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannot

be any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in the

agreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Questions 5

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Buy Now
Questions 6

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Buy Now
Questions 7

In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.

What should the project manager do to manage this conflict?

Options:

A.

Schedule a meeting with the team member and their manager to discuss the issue.

B.

Talk to the project sponsor about the team member's attitude.

C.

Schedule a one-on-one meeting with the team member to talk about it and get their

cooperation.

D.

Find another person to replace this team member.

Buy Now
Questions 8

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

Options:

A.

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Buy Now
Questions 9

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Buy Now
Questions 10

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

Options:

A.

Send out a questionnaire to all users regarding the most useful features.

B.

Embed a feedback form into the system for users to respond.

C.

Interview a sampling of users to obtain the usage data.

D.

Build the functionality in the software to collect the operational usage data.

Buy Now
Questions 11

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Follow the organization's process and deliverables for predictive projects, even if

they compromise the agility and performance of the project.

B.

Use the risk register to document all of the compliance vulnerabilities generated by

the project so that all decisions are well documented and approved by stakeholders.

C.

Meet with the project management office (PMO)/compliance entity to work on

process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Buy Now
Questions 12

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

Options:

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

Buy Now
Questions 13

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

Options:

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

Buy Now
Questions 14

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.

Analyzed the sponsor's communication requirements.

B.

Confirmed that the portal is providing adequate information.

C.

Verified that the project team is following the communications management plan.

D.

Ensured the sponsor had the necessary skills to use the portal.

Buy Now
Questions 15

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Buy Now
Questions 16

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

Options:

A.

Start sending status updates to this stakeholder based on the request.

B.

Ask the stakeholder's manager if the stakeholder can be added to the list.

C.

Review the stakeholder engagement and communications management plans.

D.

Escalate the stakeholder’s request to the project sponsor.

Buy Now
Questions 17

A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?

Options:

A.

Provide clear direction on the work to be done and its alignment to the major objectives of the organization, using technology to communicate.

B.

Establish a clear hierarchical environment and allow them to navigate through the project faster using social networks.

C.

Foster proactive decision making and develop a hierarchy to approve decisions based on different levels of complexity.

D.

Create an environment that encourages leadership, translates ambitions into growth opportunities, and rewards overtime workers.

Buy Now
Questions 18

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.

What should the project manager do?

Options:

A.

Add the feature to the supplier's requirement list so they can deliver it.

B.

Ask the supplier to accommodate the additional scope under the current agreement.

C.

Ensure the project team understands the agreement and contract in place with the supplier.

D.

Monitor the work the business analyst is performing to avoid scope creep.

Buy Now
Questions 19

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

Options:

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Buy Now
Questions 20

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Buy Now
Questions 21

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Buy Now
Questions 22

A labor union contract negotiation is delaying the completion of a project to build

a new manufacturing plant. Because the labor contract was due for renewal this year, the

project manager documented the negotiation process as a risk to the project. The project

was about to start the first phase of equipment installation at the plant when the negotiation began.

How should the project manager address the situation?

Options:

A.

Meet with the project team to determine options for risk mitigation.

B.

Log the issue and follow the planned actions in the risk response plan.

C.

Acquire contract resources and submit a change request for the cost impact.

D.

Escalate the issue to the steering committee to ask for mitigation support.

Buy Now
Questions 23

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Buy Now
Questions 24

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then share

it with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agile

approach in the upcoming project.

C.

Make a request to human resources for new team members who have agile

experience.

D.

Ask the project sponsor to change the approach back to predictive as that is the

team’s strength.

Buy Now
Questions 25

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

Options:

A.

Ask the agile team to review the updated sprint velocity with the customer.

B.

Ask the product owner to review the prioritized backlog with the customer.

C.

Ask the agile team to review and update the quality management plan with the

customer.

D.

Review the impediments log with the customer.

E.

Send a detailed project management plan to the customer.

Buy Now
Questions 26

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Buy Now
Questions 27

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Buy Now
Questions 28

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

Options:

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Buy Now
Questions 29

Drag the technical practices on the left to the scenario on the right.

Options:

Buy Now
Questions 30

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Buy Now
Questions 31

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

Options:

A.

Review the communication needs of key stakeholders.

B.

Confirm that the project information is understood and feedback is received.

C.

Determine communication methods, frequency, and level of detail.

D.

Provide all project information to the stakeholder.

Buy Now
Questions 32

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

Options:

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

Buy Now
Questions 33

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Buy Now
Questions 34

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

Options:

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Buy Now
Questions 35

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

Options:

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Buy Now
Questions 36

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project's implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Buy Now
Questions 37

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Buy Now
Questions 38

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Questions 39

A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?

Options:

A.

Express trust in the team's ability to fulfill the necessary deliverables.

B.

Assert judgment over the team.

C.

Use a plan-driven approach in order to demonstrate control over the project.

D.

Increase the amount of subject matter experts (SMEs) to get better results.

Buy Now
Questions 40

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

Options:

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Buy Now
Questions 41

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

Options:

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Buy Now
Questions 42

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Buy Now
Questions 43

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Buy Now
Questions 44

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Buy Now
Questions 45

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Options:

A.

Update the restriction log with the new team capacity.

B.

Explain the new project requirements to the team.

C.

Update the project budget with the released team members.

D.

Explain the new team velocity to the customer.

Buy Now
Questions 46

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Buy Now
Questions 47

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Buy Now
Questions 48

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

Options:

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Buy Now
Questions 49

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Buy Now
Questions 50

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

Options:

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Buy Now
Questions 51

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

B.

Performed risk management analysis during daily scrums

C.

Reviewed the organizational process assets (OPAs) and lessons learned from similar projects

D.

Performed backlog grooming to ensure that acceptance criteria were being met

Buy Now
Questions 52

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

Options:

A.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.

B.

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.

C.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).

D.

Inform the scrum master so that the change can be discussed directly with the stakeholder.

Buy Now
Questions 53

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Buy Now
Questions 54

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Buy Now
Questions 55

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Buy Now
Questions 56

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Buy Now
Questions 57

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Buy Now
Questions 58

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Buy Now
Questions 59

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Buy Now
Questions 60

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

Buy Now
Questions 61

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Buy Now
Questions 62

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

Options:

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

Buy Now
Questions 63

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Buy Now
Questions 64

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

Buy Now
Questions 65

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams through

mid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets

(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determined

the future state.

D.

Hired a third-party agile delivery team to do the implementation.

Buy Now
Questions 66

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Options:

Buy Now
Questions 67

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Buy Now
Questions 68

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

Options:

A.

Ask the project sponsor to replace the contractor since they do not have agile experience

B.

Issue a formal notice to the contractor to obtain an agile certification

C.

Consult the project team to understand the extent of the training needs for the contractor

D.

Instruct the contractor to receive agile training since the project has already started

Buy Now
Questions 69

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

Options:

A.

Invest in developing the team's emotional intelligence.

B.

Ask the unmotivated team member to take a short leave.

C.

Reduce the number of daily and retrospective meetings.

D.

Send the unmotivated team member to another team.

Buy Now
Questions 70

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Options:

Buy Now
Questions 71

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

Buy Now
Questions 72

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Buy Now
Questions 73

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

Buy Now
Questions 74

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Buy Now
Questions 75

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

Options:

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Buy Now
Questions 76

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change

Buy Now
Questions 77

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Buy Now
Questions 78

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

Options:

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Buy Now
Questions 79

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Buy Now
Questions 80

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Buy Now
Questions 81

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

Options:

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Buy Now
Questions 82

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Buy Now
Questions 83

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Buy Now
Questions 84

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Buy Now
Questions 85

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?

Options:

A.

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.

B.

Review and update the success criteria to ensure that the channel is not decommissioned.

C.

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.

D.

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.

Buy Now
Questions 86

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

Options:

A.

Establish daily standups to review project progress and track the completion of deliverables

B.

Allow the team members to catch up at their own pace

C.

Alert the business stakeholders immediately of the schedule delay.

D.

Discuss the risk of project delay and work priorities with the respective functional managers

E.

Work with the team to identify options to accelerate project delivery.

Buy Now
Questions 87

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Buy Now
Questions 88

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Buy Now
Questions 89

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Buy Now
Questions 90

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Buy Now
Questions 91

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Buy Now
Questions 92

A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager

schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?

Options:

A.

Accommodator

B.

Mediator

C.

Arbitrator

D.

Conciliator

Buy Now
Questions 93

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Buy Now
Questions 94

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

Options:

A.

Escalate the issue to the project sponsor and seek assistance.

B.

Engage the project stakeholder and ensure all requirements are captured.

C.

Review the stakeholder engagement plan and communication strategy.

D.

Review the product requirements and update the stakeholder register.

Buy Now
Questions 95

A project team consisting of various professionals of different nationalities is struggling to achieve their project deliverables. What should the

project manager do?

Options:

A.

Provide the team with support to solve their own problems.

B.

Inform the project sponsor and train the entire team.

C.

Ask the human resources (HR) department to conduct performance training.

D.

Ask the functional department manager to replace the team members.

Buy Now
Questions 96

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Buy Now
Questions 97

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Buy Now
Questions 98

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Buy Now
Questions 99

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Buy Now
Questions 100

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?

Options:

A.

Send communications for clarification so there is a full understanding about the situation.

B.

Demonstrate the performance indexes and recommend corrective actions to the stakeholders

C.

Schedule a kick-off session to explain the problems of the project and gain approval and support

D.

Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders

Buy Now
Questions 101

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

Options:

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

Buy Now
Questions 102

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

Options:

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Buy Now
Questions 103

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Buy Now
Questions 104

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Buy Now
Questions 105

Drag the organizational characteristics on the left to the correct scenario on the right

Options:

Buy Now
Questions 106

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

Options:

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Buy Now
Questions 107

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

Options:

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Buy Now
Questions 108

The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery

What should the project manager do?

Options:

A.

Pay overtime to key resource to get the work done outside of working hours

B.

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects

C.

Speak with the client to see if the project delivery deadline can be delayed due to resource availability

D.

Talk to the program manager and about prioritizing this project over other projects so the key resources are available

Buy Now
Questions 109

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Buy Now
Questions 110

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Buy Now
Questions 111

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Buy Now
Questions 112

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Buy Now
Questions 113

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?

Options:

A.

A release burndown chart

B.

Analysis of the business requirements document

C.

Story points for the remaining user stories

D.

Surrogate measurements

Buy Now
Questions 114

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

Options:

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Buy Now
Questions 115

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

Buy Now
Questions 116

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

Options:

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actions

accordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Buy Now
Questions 117

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Buy Now
Questions 118

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

Options:

A.

Share the customer feedback with the project team

B.

Follow the meeting agenda and make a list of the next deliverables

C.

Document this feedback in the meeting minutes.

D.

Start planning how to improve the dates of next deliverables

Buy Now
Questions 119

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Buy Now
Questions 120

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Buy Now
Questions 121

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experience

to build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Buy Now
Questions 122

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

Options:

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Buy Now
Questions 123

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.

Have the project team work on other activities

B.

Implement plans to remove the obstacles

C.

Escalate to the project steering committee

D.

Prioritize the obstacles for resolution

Buy Now
Questions 124

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Buy Now
Questions 125

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a prioritized backlog and define iteration review sessions with stakeholders

B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.

Schedule a daily meeting to review team performance and impediments

D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Buy Now
Questions 126

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Buy Now
Questions 127

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

Options:

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Buy Now
Questions 128

A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.

What should the project manager do?

Options:

A.

Promote the higher performing team member to a higher position

B.

Request the high-performing team member to mentor the other team members

C.

Remind the high-performing team member to focus on shared rewards rather than individual rewards

D.

Reward the high-performing team member privately to avoid team disruption

Buy Now
Questions 129

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?

Options:

A.

Escalate the issue to the project sponsor and add it to the risk register

B.

Refuse to work on the project because management is not following standard project management practices

C.

Meet with management to explain the potential problems with running a project without a project scope statement

D.

Start the project with inputs from the project charter to save time

Buy Now
Questions 130

A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ask for expedited delivery of the component to mitigate the risk of schedule delays

B.

Ensure that relevant stakeholders and expectations are identified and assess the component delay

C.

Perform a detailed analysis of the release content for each component of the solution.

D.

Propose a new design of the solution to replace the external component with an internal one

Buy Now
Questions 131

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

Options:

A.

Tell the junior team member that the information is available in lessons learned

B.

Offer guidance and follow up with some developmental activity for the junior team member

C.

Inform the junior team member that risk mitigation is not part of their work

D.

Refer the junior team member to the senior team member who develops the risk mitigation strategy

Buy Now
Questions 132

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

Options:

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

Buy Now
Questions 133

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

Options:

A.

Set up a meeting with key stakeholders to clarify requirements

B.

Escalate to the project steering committee and request additional time

C.

Travel to the development team's office to push the schedule

D.

Create prototypes with the development team to confirm requirements

Buy Now
Questions 134

A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog

What should the project manager do?

Options:

A.

Push the team to deliver more so that the modules are developed and rolled out according to management's request

B.

Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

C.

Have the team work toward the tighter deadline so that integration will be easier.

D.

Speak to the team and slow the current pace to ensure the team is in alignment with the release date

Buy Now
Questions 135

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.

Implement the planned risk response to handle the issue.

B.

Review possible alternative documentation methods with team

C.

Update the risk register with the risk and proposed impact.

D.

Ask the team to fix the system to resolve the issue

Buy Now
Questions 136

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

Options:

A.

Define team ground rules

B.

Perform a retrospective session

C.

Implement daily team meetings.

D.

Request a manager performance review

E.

Conduct an annual review.

Buy Now
Questions 137

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Options:

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Buy Now
Questions 138

In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?

Options:

A.

Let the developers focus on the refactoring work and discuss it in the retrospective

B.

Restate to the developers the importance of focusing and meeting the sprint goal.

C.

Praise the developers for their proactivity and focus on quality.

D.

Escalate the issue to the developers’ functional managers

Buy Now
Questions 139

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

Buy Now
Questions 140

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

Options:

A.

Revisiting the project management plan to ensure deliverables are on time

B.

Increasing the frequency of project update meetings to keep stakeholders informed

C.

Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders

D.

Reviewing the business case and identifying gaps within scope

Buy Now
Questions 141

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

Options:

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Buy Now
Questions 142

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

Options:

A.

Request direction from the project sponsor

B.

Write an email to the client requesting clarification

C.

Seek support from the development manager.

D.

Work with the product owner to clarify the requirement

Buy Now
Questions 143

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Options:

Buy Now
Questions 144

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Options:

Buy Now
Questions 145

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Buy Now
Questions 146

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

Options:

A.

Schedule a steering committee meeting and obtain their approval on the request

B.

Support the decisions of the team and transfer the decision making responsibility to them.

C.

Inform the team that although this is a hybrid environment, the project manager

must still be responsible for making decisions

D.

Consult the product owner about letting the resources make decisions

Buy Now
Questions 147

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Options:

Buy Now
Questions 148

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

Options:

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

Buy Now
Questions 149

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

Options:

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Buy Now
Questions 150

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

Buy Now
Questions 151

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

Options:

A.

Invite technical stakeholders for backlog prioritization.

B.

Work on the features already prioritized by the product owner.

C.

Ask the sponsor for more resources to continue at the same pace.

D.

Add the technical debt tasks to the sprint backlog.

Buy Now
Questions 152

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

Options:

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Buy Now
Questions 153

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Buy Now
Questions 154

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

Options:

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Buy Now
Questions 155

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

Options:

A.

Force the team members to work from one location.

B.

Develop protocols for resolving conflicts between team members

C.

Obtain special expertise to advise the team members

D.

Set up face-to-face meetings with project team members

Buy Now
Questions 156

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Buy Now
Questions 157

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Buy Now
Questions 158

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

Options:

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.

B.

Stop crashing the schedule

C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators

D.

Use a resource-levelling technique

Buy Now
Questions 159

The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?

Options:

A.

Arrange a meeting with the managers and try to reach an agreement.

B.

Communicate with the project sponsor regarding the need to resolve the conflict between the managers.

C.

Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan

D.

Meet with both teams and their managers and try to figure out the root cause of the conflict

Buy Now
Questions 160

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

Options:

A.

Include stakeholders during daily standup meetings to monitor progress.

B.

Validate acceptance criteria with stakeholders prior to backlog refinement

C.

Avoid including stakeholders in iteration reviews.

D.

Create a requirements traceability matrix and distribute it accordingly

Buy Now
Questions 161

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Buy Now
Questions 162

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery

Buy Now
Questions 163

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk of

being noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurity

requirements.

Buy Now
Questions 164

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’

Options:

A.

Weekly colocated meetings with the relevant stakeholders

B.

Biweekly conference calls with the relevant stakeholders

C.

Weekly one-on-one meetings with each of the relevant stakeholders

D.

Biweekly written status reports from the relevant stakeholders

Buy Now
Questions 165

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

Options:

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Buy Now
Questions 166

During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to

be involved in the regular project communications and reporting cycles.

What should the project manager do?

Options:

A.

Ask the project team members to include the manager in all of their communications regarding this project.

B.

Inform the manager that only stakeholders identified in the communications management plan should be involved.

C.

Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

D.

Suggest the manager contact the steering committee and project management office (PMO) to be included.

Buy Now
Questions 167

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?

Options:

A.

Request a replacement resource

B.

Perform a cost-benefit analysis

C.

Implement risk responses

D.

Perform Integrated Change Control

Buy Now
Questions 168

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.

Start developing a business case.

B.

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.

Engage stakeholders and allocate resources

D.

Gather requirements from stakeholders

Buy Now
Questions 169

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

Options:

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

Buy Now
Questions 170

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

Options:

Buy Now
Questions 171

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

Options:

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

Buy Now
Questions 172

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

Options:

A.

Modify the project schedule to accommodate the delays in the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

Buy Now
Questions 173

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Options:

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope

Buy Now
Questions 174

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Buy Now
Questions 175

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance'?

Options:

A.

The project will be completed exactly as planned

B.

The project will be easier to complete than planned

C.

The project will be difficult to complete as planned.

D.

The project will not be completed as planned

Buy Now
Questions 176

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

Options:

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Buy Now
Questions 177

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Options:

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

Buy Now
Questions 178

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.

Referred to the communications management plan

B.

Validated the issue log

C.

Validated the project artifacts

D.

Performed expert judgment

Buy Now
Questions 179

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Buy Now
Questions 180

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions

B.

Inform management that commitments will not be met.

C.

Involve management to help resolve the conflicts

D.

Coach the team both as a whole and individually

Buy Now
Questions 181

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member's functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Buy Now
Questions 182

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

Options:

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Buy Now
Questions 183

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.

Team A as they have calculated fewer story points than team B.

B.

Team B as they have calculated more story points than team A

C.

The team that completes the most stories selected from the sprint backlog

D.

The team with the least amount of defects in their deliverables

Buy Now
Questions 184

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Buy Now
Questions 185

A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?

Options:

A.

Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.

B.

Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.

C.

Create the requirements management plan to outline how project requirements will be collected analyzed and documented and then assign requirements to team members

D.

Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members

Buy Now
Questions 186

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

Options:

A.

A team member talking about a user story that is not on the Scrum board

B.

A team member talking about a user story that is on the Scrum board

C.

A technology that blocks agile capabilities

D.

A lack of team empowerment and an inability to self-organize

E.

A review of the backlog at daily standup meetings

Buy Now
Questions 187

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

Options:

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is needed

in resolving the impediments

Buy Now
Questions 188

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Buy Now
Questions 189

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Buy Now
Questions 190

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

Options:

A.

Ask the human resources director to appoint a senior team leader

B.

Inform the project sponsor about the possible delay

C.

Directly manage the project team to avoid project delays

D.

Provide mentoring to the newly appointed team leader

Buy Now
Questions 191

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?

Options:

A.

Train the team on the new regulations as requested by management

B.

Get commitment from the team to include all of the required regulations

C.

Ask the project sponsor to add more time to the project.

D.

Share with participants the need to focus only on product functionality

Buy Now
Questions 192

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.

Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

Options:

Buy Now
Questions 193

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

Options:

A.

Schedule a meeting with the project team to reinforce the ground rules.

B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action

C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

D.

Ask the functional manager to replace team members not following the ground rules

Buy Now
Questions 194

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

Options:

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

Buy Now
Questions 195

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Buy Now
Questions 196

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

Options:

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Buy Now
Questions 197

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.

Analyze both projects to determine the most effective use of common resources

B.

Use resource optimization to justify requesting more resources for the critical project

C.

Provide schedule optimization training to the project teams to improve their skills.

D.

Apply fast-tracking techniques to compress the schedule of the critical project

Buy Now
Questions 198

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

Options:

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Buy Now
Questions 199

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Options:

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Buy Now
Questions 200

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

Options:

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Buy Now
Questions 201

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Buy Now
Questions 202

A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project

What should the project manager have the project team update to ensure proper communications to stakeholders?

Options:

A.

Project management plan

B.

Stakeholder engagement plan

C.

Stakeholder register

D.

Communications management plan

Buy Now
Questions 203

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Options:

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Buy Now
Questions 204

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Buy Now
Questions 205

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Buy Now
Questions 206

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?

Options:

A.

Increase resources on the technical design to enable a decision to proceed as this is a

quick return project.

B.

Increase the time spent on project development to improve the level of confidence to

validate the financial evaluation.

C.

Conduct a stakeholder survey with the plant operators to establish the probability of

this project reducing the cost of utilities.

D.

Stop any further project development and commence with the implementation as there

is no need to seek further approval.

Buy Now
Questions 207

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

Options:

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the quality

management plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Buy Now
Questions 208

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

Options:

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Buy Now
Questions 209

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company's historical organizational project artifacts

B.

Company's project responsibility assignment matrix (RAM)

C.

Company's resource management plan

D.

Company's resource calendars

Buy Now
Questions 210

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

Options:

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Buy Now
Questions 211

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Buy Now
Questions 212

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

Options:

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Buy Now
Questions 213

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Buy Now
Questions 214

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Buy Now
Questions 215

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

Options:

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

Buy Now
Questions 216

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

Options:

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

Buy Now
Questions 217

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Options:

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Buy Now
Questions 218

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

Buy Now
Questions 219

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Buy Now
Questions 220

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Buy Now
Questions 221

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

Options:

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

Buy Now
Questions 222

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.

Update the issue log and review the lessons learned register for options

B.

Implement conflict resolution to accommodate the team's needs

C.

Implement decision-making techniques to advance the stones

D.

Empower the team to self-organize and make their own decisions

Buy Now
Questions 223

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Buy Now
Questions 224

A project manager is leading a project that is in the execution phase. During a team

meeting, the project manager realizes that there are two team members who lack the

technical skills required for some of the upcoming tasks.

What should the servant leader project manager do next?

Options:

A.

Recommend to the team members to upskill themselves on the requirements for the

project.

B.

Discuss with the human resource (HR) manager about the possibility of changing team

members.

C.

Inform the sponsor about a possible delay due to the lack of skills in the team.

D.

Explore a training program that is within the project budget for the team members.

Buy Now
Questions 225

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

Options:

A.

An agreed-upon work method and tools that should fit the business need and project constraints

B.

A detailed mitigation plan on the risks for each work method and the tools used

C.

A consensus that everything will run as anticipated once the tools and work methods are identified

D.

A technology roadmap for creating similar deliverables in the future with the same tools

Buy Now
Questions 226

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Buy Now
Questions 227

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Buy Now
Questions 228

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

Options:

A.

Reprimand the team members who did not fill out the status reports.

B.

Justify the team members' behavior to the project sponsor.

C.

Quickly put together a report that will satisfy the project sponsor.

D.

Discuss the issue with the team members at fault.

Buy Now
Questions 229

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions when

needed.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders

ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all

unavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders to

make decisions.

Buy Now
Questions 230

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

Options:

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Buy Now
Questions 231

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

Options:

A.

A. Hire resources to obtain knowledge about the provider's specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Buy Now
Questions 232

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.

Submit a change request to include the manual.

B.

Add the needed manual and update the risk log.

C.

Review the stakeholder engagement plan.

D.

Review the terms and conditions of the contract.

Buy Now
Questions 233

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts

(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

Buy Now
Questions 234

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Buy Now
Questions 235

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

Options:

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Buy Now
Questions 236

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

Options:

A.

Ensure participation from all team members

B.

Ask the client to attend all daily calls.

C.

Ensure cross-departmental teams are colocated

D.

Request additional project resources

Buy Now
Questions 237

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.

Escalate the issue to the team member's functional manager and request a response

as soon as possible.

B.

Meet with the team member to understand what the issues are and to provide support.

C.

Leverage other team members who are contributing and making the project a success.

D.

Have the team member transferred to another project and add other resources to the

project.

Buy Now
Questions 238

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

Options:

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Buy Now
Questions 239

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

Options:

A.

Schedule crashing

B.

Fast tracking

C.

Earned schedule

D.

Earned value

Buy Now
Questions 240

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

Options:

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Buy Now
Questions 241

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Buy Now
Questions 242

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

Options:

Buy Now
Questions 243

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

Buy Now
Questions 244

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

Buy Now
Questions 245

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.

Assign this member to facilitate the next meeting to ensure project team collaboration.

B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.

C.

Review and update the project ground rules to make meeting attendance mandatory.

D.

Understand the reason for the team member's absence and encourage them to attend future meetings.

Buy Now
Questions 246

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Buy Now
Questions 247

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

Options:

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Buy Now
Questions 248

In a hybrid project, 100 new base stations are being added to a 4G mobile network

every month. At the end of the first month, the team is behind the target and the operator is

losing money. The stakeholders are requesting information on when the base stations can go

live and begin to bill.

What should the project manager do to take the schedule back and accelerate the return on

investment (ROI) of the project?

Options:

A.

Change the project approach to predictive.

B.

Increase reporting to the business.

C.

Clarify the agile and predictive modules.

D.

Reconsider necessary schedule reserves.

Buy Now
Questions 249

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.

Evaluate the possibility of managing this project using a predictive approach.

B.

Submit a change request for a new team that has agile experience.

C.

Mentor the team to explain agile principles and create a shared understanding.

D.

Hire a functional manager who is familiar with agile methodologies.

Buy Now
Questions 250

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Buy Now
Questions 251

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

Options:

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Buy Now
Questions 252

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

Options:

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

Buy Now
Questions 253

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

Options:

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Buy Now
Questions 254

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.

Inform executive management that the customer is made aware of the status during

the sprint demo.

B.

Prepare a weekly status report and share it with executive management every week.

C.

Inform executive management about agile principles and processes that are followed

in the project.

D.

Ask the team to prepare and share the status report with executive management every

week.

Buy Now
Questions 255

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Options:

Buy Now
Questions 256

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.

Update the stakeholder register.

B.

Refer to the resource management plan.

C.

Consult the project sponsor.

D.

Modify the statement of work (SOV).

Buy Now
Questions 257

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

Options:

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Buy Now
Questions 258

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

Options:

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Buy Now
Questions 259

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Buy Now
Questions 260

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Buy Now
Questions 261

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Options:

Buy Now
Questions 262

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.

Ensure that the whole team is appropriately recognized and organize a project farewell

party to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and save

them in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices so

the documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult to

undertake because the current project is not yet complete.

Buy Now
Questions 263

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Buy Now
Questions 264

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impact

negotiation.

Buy Now
Questions 265

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

Buy Now
Questions 266

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Buy Now
Questions 267

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Buy Now
Questions 268

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

Options:

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

Buy Now
Questions 269

A project manager has been assigned with initiating a large project to deliver

complex equipment. Part of the project will be the result of a long research process, but once

this is completed, the other part of the project must be incrementally delivered to the

customer.

Which approach should the project manager choose for this project?

Options:

A.

Agile

B.

Waterfall

C.

Predictive

D.

Hybrid

Buy Now
Questions 270

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.

Provide mentoring for the key team members on agile practices and support the team

with training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rules

stated in the document.

C.

Replace the key team members with new resources who are already aware of the agile

mindset.

D.

Provide directions to the team members on how to accelerate the company's

transformation, bringing the project back on track.

Buy Now
Questions 271

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Options:

Buy Now
Questions 272

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

Options:

A.

Change the project scope and seek approval to exclude this town from the overall

project.

B.

Engage with the town's authorities to discuss the reason for the change in commitment

and agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Buy Now
Questions 273

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assess

progress.

B.

Set up a feedback session with the product owner once a week so they can assess

progress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner's functional manager to a feedback session to escalate the

issue.

Buy Now
Questions 274

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Buy Now
Questions 275

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Buy Now
Questions 276

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Buy Now
Questions 277

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new team

members.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Buy Now
Questions 278

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

Options:

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

Buy Now
Questions 279

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

Options:

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Buy Now
Questions 280

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

Buy Now
Questions 281

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

Options:

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Buy Now
Questions 282

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

Options:

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.

B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

Buy Now
Questions 283

A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

Options:

A.

Continue production processes and plan to discuss changes at the next annual target review meeting.

B.

Begin a marketing campaign to sell alternative packaging after the 12-month period ends.

C.

Inform management of the new law as an opportunity to expand market share and share the proposed products

D.

Organize a meeting with all stakeholders and review the stakeholder engagement plan

Buy Now
Questions 284

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

Options:

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.

Issue a change request to include the additional scope, and track the completion of the work items.

C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.

Arrange to pass the cost to the operational area since the customer will benefit.

Buy Now
Questions 285

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

Options:

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Buy Now
Questions 286

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog and

begin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learned

and complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for the

product backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Buy Now
Questions 287

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

Options:

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Buy Now
Questions 288

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.

C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.

Buy Now
Questions 289

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Buy Now
Questions 290

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

Options:

A.

US$650,000

B.

US$452,500

C.

US$547,500

D.

US$582,500

Buy Now
Questions 291

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

Options:

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Buy Now
Questions 292

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

Options:

A.

Postpone the selection of the technology used until more information is gathered

B.

Suggest their own approach to solve the issue and ask the team to follow it

C.

Call for an open dialogue which the team will arrive at through consensus

D.

Allow the team to decide since the teams should be autonomous

Buy Now
Questions 293

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

Options:

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Buy Now
Questions 294

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

Options:

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

Buy Now
Questions 295

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.

Meet with the team member and search for the root cause of their behavior.

Buy Now
Questions 296

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Buy Now
Questions 297

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project

status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for

incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Buy Now
Questions 298

The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?

Options:

A.

Ensure there are opportunities for the product owner to present project reviews to the stakeholders.

B.

Suggest that the product owner attend a training session about assertive communication.

C.

Suggest that the product owner shadow colleagues who are good presenters.

D.

Recommend a specialized article about delivering effective presentations to the product owner.

Buy Now
Questions 299

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.

B.

Discuss the issue with the functional manager to understand the reason for the

complaint.

C.

Support the team member and provide documentation to the functional manager

proving their performance.

D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.

Buy Now
Questions 300

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.

Promote a productive environment where everybody can work without interruptions

from the rest of the team members.

B.

Create a reward system recognizing group contributions to get people motivated and

improve performance.

C.

Facilitate sprint planning sessions with a focus on defining the minimum viable product

(MVP).

D.

Design a set of metrics including velocity, which is a good measure of value delivered.

Buy Now
Questions 301

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

Options:

A.

Implement daily standups where the team can share their impediments, risks, and

issues.

B.

Review the communications management plan and implement changes.

C.

Schedule weekly risk review meetings with the team to review project risks and

concerns.

D.

Distribute a copy of the communications management plan to the scrum master.

Buy Now
Questions 302

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.

Negotiate the payments with the supplier and remind them of their long-term association

B.

Penalize the supplier according to the contract's service level agreement (SLA)

C.

Hire another information security supplier and incentivize them for speedy delivery

D.

inform the relevant stakeholders of this challenge and seek their support

Buy Now
Questions 303

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

Buy Now
Questions 304

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

Options:

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.

Remind the team frequently that the project must be delivered on time and within budget

C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Buy Now
Questions 305

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.

Review the communications management plan with the team members.

B.

Remind the team members to follow the team charter.

C.

Motivate the team members to speak freely in the meeting.

D.

Arrange a team-building activity to involve all team members.

Buy Now
Questions 306

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

Options:

A.

Escalate the team member's disruptive behavior to their functional manager.

B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.

C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.

D.

Request team members document their decisions independently and share with each other.

Buy Now
Questions 307

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Buy Now
Questions 308

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Buy Now
Questions 309

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Buy Now
Questions 310

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Buy Now
Questions 311

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Buy Now
Questions 312

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Buy Now
Questions 313

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.

What should the project manager do?

Options:

A.

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead's functional manager.

Buy Now
Questions 314

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

Options:

A.

File a change request to make the customer billable for all extra costs incurred for the project.

B.

Ask the accounting department to forward all project expenses to the project manager's email.

C.

Monitor the budget for the project continually and anticipate any issues if possible.

D.

Ask the project resources to finish their assignments in less time than originally planned.

Buy Now
Questions 315

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

Options:

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external

stakeholders.

C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the

government.

Buy Now
Questions 316

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Options:

Buy Now
Questions 317

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Buy Now
Questions 318

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.

Buy Now
Questions 319

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

Buy Now
Questions 320

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

Options:

A.

Traditional delivery, to ensure high quality and that the product meets market demands

B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product

C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration

D.

Incremental delivery, to ensure that mobile capability is released fast to the users

Buy Now
Questions 321

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Buy Now
Questions 322

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Buy Now
Questions 323

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

Options:

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Buy Now
Questions 324

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

Options:

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor's app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Buy Now
Questions 325

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

Options:

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.

Buy Now
Questions 326

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

Options:

A.

Increase the contingency reserves to cover unknown-unknowns.

B.

Implement short cycles for inspection and provide feedback.

C.

Increase the management reserves to convert the known-unknowns.

D.

Create a new risk entry to identify the stakeholder as a detractor.

Buy Now
Questions 327

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

Options:

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

Buy Now
Questions 328

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Options:

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

Buy Now
Questions 329

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

Options:

A.

Included lessons learned from past projects

B.

Used bottom-up estimating

C.

Utilized three-point estimates

D.

Validated the schedule performance index (SPI) to evaluate deviation

Buy Now
Questions 330

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

Options:

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities

B.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

C.

Review the critical path and update the project schedule with the newly identified tasks.

D.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

Buy Now
Questions 331

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Buy Now
Questions 332

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Buy Now
Questions 333

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Buy Now
Questions 334

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Buy Now
Questions 335

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Buy Now
Questions 336

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

Options:

A.

Ask management to replace the new sponsor with the previous sponsor.

B.

Request the previous sponsor to discuss changes with the project team.

C.

Explore ways to share the project vision and outcome with the new sponsor.

D.

Find ways to bypass the new sponsor and reach management for support.

Buy Now
Questions 337

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

Options:

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

Buy Now
Questions 338

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Buy Now
Questions 339

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Buy Now
Questions 340

A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.

What should the project manager do next to address this stakeholder’s concerns?

Options:

A.

Review the benefits realization plan with the stakeholder.

B.

Provide the stakeholder with regular updates on project progress.

C.

Add the stakeholder to the stakeholder engagement plan.

D.

Review the prior analysis results with the stakeholder.

Buy Now
Questions 341

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

Options:

A.

Monitor all stakeholders.

B.

Keep all stakeholders informed.

C.

Analyze the stakeholders.

D.

Engage the stakeholders.

Buy Now
Questions 342

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Buy Now
Questions 343

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

Options:

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

Buy Now
Questions 344

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor's lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

Buy Now
Questions 345

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.

Design an updated status report.

B.

Request a meeting with the stakeholder.

C.

Escalate this to the project sponsor.

D.

Forward the project status reports.

Buy Now
Questions 346

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

Options:

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

Buy Now
Questions 347

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Buy Now
Questions 348

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Buy Now
Questions 349

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

Options:

A.

On schedule

B.

Ahead of schedule

C.

Stopped

D.

Behind schedule

Buy Now
Questions 350

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

Options:

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

Buy Now
Questions 351

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Buy Now
Questions 352

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Buy Now
Questions 353

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Buy Now
Questions 354

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

Buy Now
Questions 355

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

Options:

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Buy Now
Questions 356

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.

B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.

Buy Now
Questions 357

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.

Ask the product owner if some low-priority stories could be cut from the sprint.

B.

Continue with the sprint as the progress shows buffers for potential interruptions.

C.

Ask the project team to select any additional stories as they have additional capacity than planned.

D.

Continue with the sprint work as planned and keep monitoring.

Buy Now
Questions 358

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Buy Now
Questions 359

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Options:

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Buy Now
Questions 360

A project manager is working on a software development project. The project manager and the project team identified the project risks. As the

project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

Options:

A.

Risk monitored

B.

Risk occurred

C.

Risk managed

D.

Risk identified

Buy Now
Questions 361

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

Options:

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Buy Now
Questions 362

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Buy Now
Questions 363

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

Buy Now
Questions 364

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

Options:

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Maintain the same task allocation structure to avoid any disruption in the project team.

C.

Move the developer to another team and look for a replacement developer.

D.

Request that all quality assurance tasks be allocated to the new resource.

Buy Now
Questions 365

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

Options:

A.

Set up a meeting with the team to discuss and determine the project's challenges.

B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.

C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.

D.

Meet with the data suppliers to explain the critical timing requirements of the project.

Buy Now
Questions 366

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

Options:

Buy Now
Questions 367

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Ignore the obstacle and present the partial solution to the customer

C.

Focus on generating business value despite the obstacle

D.

Make changes to reprioritize the backlog because of the obstacle.

Buy Now
Questions 368

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer's complaints and critical issues in the issue log.

Buy Now
Questions 369

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Buy Now
Questions 370

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

Options:

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Buy Now
Questions 371

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

Options:

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

Buy Now
Questions 372

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

Options:

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Buy Now
Questions 373

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Communicate with the industry's regulatory authority to grant the company an exception

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Comply with the regulatory requirements and work to compress the project schedule.

D.

Hire a third party who is an expert on the industry's regulations to work out the details.

Buy Now
Questions 374

Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

Options:

A.

Ask the contractor to solve this problem because this is a contractual obligation.

B.

Terminate the contract and initiate a new one with a local contractor.

C.

Implement key performance indicators (KPIs) and convince the contractor to engage the team.

D.

Reassess continually to remove blockers for the team.

Buy Now
Questions 375

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

Options:

A.

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

Buy Now
Questions 376

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

Options:

A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.

Share weekly status reports with detailed information about the project and team performance.

C.

Submit performance reports and task assignments to keep the stakeholder informed.

D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.

Provide training to the team on emotional intelligence and status reporting techniques.

Buy Now
Questions 377

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

Options:

A.

Invite the sales manager to the next sprint meeting to clarify requirements.

B.

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.

Request a meeting with the product owner to help clarify the user story.

Buy Now
Questions 378

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

Options:

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Buy Now
Questions 379

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Buy Now
Questions 380

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

Options:

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

Buy Now
Questions 381

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.

B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.

C.

Set up an intranet site and allow stakeholders to access the relevant project information.

D.

Divide up the organization among the project team to provide direct project updates.

Buy Now
Questions 382

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

Options:

A.

Tell the client about the chance for the potential delay.

B.

Work with the project team to evaluate the potential delay.

C.

Do not disclose the likelihood of a delay as it is yet to happen.

D.

Ask the project sponsor to inform the client in the next update.

Buy Now
Questions 383

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

Buy Now
Questions 384

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Buy Now
Questions 385

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

Options:

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.

B.

Make arrangements with the resource's functional manager to relocate the team member to another existing project.

C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in the

contract.

D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.

Buy Now
Questions 386

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

Buy Now
Questions 387

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the

company’s competitive advantage. What should the project manager do?

Options:

A.

Reject all requested changes and bypass the company's change control process.

B.

Encourage the project team to add premium features to impress the client.

C.

Start the process to include the new features of the product on the next iteration.

D.

Allow all requested changes and bypass the company's change control process.

Buy Now
Questions 388

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

Options:

A.

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.

Remove the project team member immediately and assign the pending activities to other team members.

C.

Tell the customer that they do not have the authority to remove project team members.

D.

Ask the project team member to call the customer to apologize for their behavior.

Buy Now
Questions 389

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

Options:

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Buy Now
Questions 390

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

Options:

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Buy Now
Questions 391

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

Options:

A.

Select members for their skill or potential.

B.

Establish the project scope and set clear team objectives.

C.

Set performance standards and direction.

D.

Hold early kick-off meetings and regular weekly meetings.

Buy Now
Questions 392

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

Options:

A.

Communicated a new delivery date to the customer along with the news about the delay

B.

Disclosed to senior management in confidence, then communicated the delay to the customer

C.

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

Buy Now
Questions 393

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Buy Now
Questions 394

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

Options:

A.

Prioritize which backlog activities should be kept.

B.

Work on the backlog activities with fewer story points.

C.

Ask for more resources to clear the backlog activities.

D.

Assign an owner for each backlog activity and track progress.

Buy Now
Questions 395

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Buy Now
Questions 396

A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the

project?

Options:

A.

Confer with team members.

B.

Review with security experts.

C.

Schedule regular project audits.

D.

Discuss with the customer.

Buy Now
Questions 397

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

Options:

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Buy Now
Questions 398

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Buy Now
Questions 399

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

Options:

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Buy Now
Questions 400

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Buy Now
Questions 401

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Buy Now
Questions 402

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Buy Now
Questions 403

A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.

What should the project manager do?

Options:

A.

Place the new team member on a performance improvement program.

B.

Ask another team member to take some of the new team member's work.

C.

Assign easier activities to the new team member.

D.

Allocate time within the iterations to mentor the new team member.

Buy Now
Questions 404

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Buy Now
Questions 405

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previous

ways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

Buy Now
Questions 406

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?

Options:

A.

Feedback from the project sponsor

B.

Agreed-upon key performance indicators (KPIs)

C.

Input from project stakeholders

D.

Competencies of team members

Buy Now
Questions 407

A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.

Which action should the project manager take?

Options:

A.

Apply the new list of approval procedures.

B.

Escalate the issue to the project sponsor.

C.

Ask the project team if the scope can be changed.

D.

Inform the customer that the project will be late.

Buy Now
Questions 408

An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.

What should the project manager do first?

Options:

A.

Document the direction and control framework into the project charter.

B.

Develop an engagement plan to achieve consensus.

C.

Identify and interview all of the relevant stakeholders.

D.

Get direction and control framework requirements from stakeholders.

Buy Now
Questions 409

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

Options:

A.

Work with the procurement team to find alternative options.

B.

Contact the vendor that supplied similar equipment for a previous project.

C.

Use the existing equipment and replace it later with the new equipment

D.

Ask the project sponsor to expedite the vendor selection process.

Buy Now
Questions 410

A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to

enhance the budget estimations for the project?

Options:

A.

Discuss the budget with the team during the daily standups to ensure the budget is under control.

B.

Review budget-related lessons learned from similar projects.

C.

Invite the client to the kick-off meeting and create the project budget during the meeting,

D.

Implement an agile approach to avoid using a fixed budget,

Buy Now
Questions 411

A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the

system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the

year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?

Options:

A.

Reassure the sponsor by explaining the probability of this risk materializing is extremely low.

B.

Carry out tests to verify that the system does not fail again due to the high occurrence of events.

C.

Review the list of risks to verify that this issue was considered and execute the detailed action plan.

D.

Inform the sponsor about the issue and make a request for sufficient funds to be made available.

Buy Now
Questions 412

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

Options:

A.

Assessed feasibility and impacts

B.

Developed benchmarking

C.

Analyzed stakeholders

D.

Detailed the project charter

Buy Now
Questions 413

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?

Options:

A.

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.

B.

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.

C.

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.

D.

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.

Buy Now
Questions 414

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the

scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,

among other critical blockers.

What should the project manager do?

Options:

A.

Request an additional resource to assist in solving all of the impediments listed by the team.

B.

Determine and agree when a situation becomes an impediment to be solved by the scrum master.

C.

Request the team review and prioritize the open impediments to resolve all of them as soon as possible.

D.

Push back, explaining that a self-organized team should address all of the problems to get the work done.

Buy Now
Questions 415

An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.

What should the project manager do first?

Options:

A.

Acknowledge the stakeholder's concerns and work to correct the deliverable.

B.

Compare the stakeholder's assertion to the metrics in the quality report.

C.

Ask the project sponsor for additional funding for improved quality outcomes.

D.

Update the risk register with information on the noncompliant deliverable.

Buy Now
Questions 416

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

Options:

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

Buy Now
Questions 417

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?

Options:

A.

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.

B.

Discuss the issue with the team so the product manager can understand the trade-offs.

C.

Suggest the team and product manager go with the faster approach, reducing the scope.

D.

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.

Buy Now
Questions 418

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Buy Now
Questions 419

Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.

What should the project manager do to help ensure a successful outcome for the project?

Options:

A.

Collaborate with stakeholders to complete an analysis of priorities with ranked objectives.

B.

Withhold from revealing the priorities and objectives until midway through negotiations.

C.

Begin the negotiation process with predetermined objectives to guide the discussions.

D.

Adjust priorities and objectives based on real-time developments during the negotiation process.

Buy Now
Questions 420

A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that

there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.

What should the project manager do?

Options:

A.

Refer to the configuration management knowledge base for similar projects delivered in the past.

B.

Arrange for a workshop with the customer to understand the business values expected from the outcomes.

C.

Include a representative from the customer to work collaboratively with the team.

D.

Acknowledge that the current team needs improvement and hire more qualified team members.

Buy Now
Questions 421

In a review session held halfway through the project's development, several important stakeholders voice extreme dissatisfaction with the solution's current development versus what they had agreed were the goals and outputs of the project. One of the more prominent individuals threatens to close the project immediately. With no dissatisfaction having been voiced at prior sessions, the project manager is surprised.

How should the project manager respond during the session?

Options:

A.

Engage with the individuals about their dissatisfactions and determine what they view as possible resolutions.

B.

Agree with the individual that they have every right to close the project and remind them of the resources already consumed.

C.

Reprise past responses, especially positive ones, that the dissenters presented in previous sessions to defend the team's work.

D.

Emphasize that this is the first occurrence of voiced dissatisfaction and then proceed to reconcile their concerns.

Buy Now
Questions 422

A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was

appointed to attend the first meeting with the auditors scheduled for the following week.

What should the project manager do to prepare for the audit?

Options:

A.

Reserve story points for the next iteration if needed.

B.

Review the project information.

C.

Ask the development team to provide compliance information.

D.

Ask for a waiver during the audit.

Buy Now
Questions 423

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.

What should the project manager do to manage such a situation for upcoming phases?

Options:

A.

Revise the project schedule to accommodate fixing discovered issues.

B.

Ensure customer validation occurs more frequently during the life cycle of the project.

C.

Review the customer validation team's test plan early in the life cycle.

D.

Ask the project team to increase unit testing of the deliverables.

Buy Now
Questions 424

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

Options:

A.

Perform stakeholder engagement.

B.

Perform integrated change control.

C.

Update the quality management plan.

D.

Update the risk management plan.

Buy Now
Questions 425

A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.

What should the project manager do after identifying the stakeholders?

Options:

A.

Prioritize stakeholders from the client's organization and the local community.

B.

Prioritize stakeholders from the project manager's own organization.

C.

Prioritize the stakeholders that are more interested in the success of the project.

D.

Prioritize the stakeholders that may have more impact on the development of the project.

Buy Now
Questions 426

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.

Ensure the client representative is involved in the estimation.

B.

Review the completion costs of similar projects.

C.

Ensure that a 20% contingency is included in the estimation.

D.

Review the lessons learned from similar projects.

Buy Now
Questions 427

A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will

take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6

months.

What should the project manager do to align stakeholders’ needs and expectations?

Options:

A.

Work with the stakeholders to create a prioritized backlog and release a roadmap.

B.

Modify the requirements to those that can be completed in 6 months.

C.

Implement fast-tracking and crashing activities to complete the project in 6 months.

D.

Include all stakeholders in daily scrum meetings to keep them informed.

Buy Now
Questions 428

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

Options:

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.

B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.

C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.

D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.

Buy Now
Questions 429

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a

specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted

the import of this machine model.

What should the project manager have done to prevent this from happening?

Options:

A.

Ensured that the SMEs correctly defined the project scope and the machine model.

B.

Ensured the project sponsor provided enough funding to purchase the latest version of the machine.

C.

Ensured that regulatory compliance was considered in the quality management plan.

D.

Ensured that the technical team researched and selected the latest model of the machine.

Buy Now
Questions 430

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

Options:

A.

Assess and prioritize the impact of the new law on the project plan.

B.

Update the project plan because the law is an obligation for the project.

C.

Minimize the scope to catch the cost and schedule baseline.

D.

Meet the sponsor to ask for additional time and budget increase.

Buy Now
Questions 431

A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?

Options:

A.

Retrospective meetings

B.

Daily meetings

C.

Kanban board

D.

Gantt chart

Buy Now
Questions 432

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

Options:

A.

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

B.

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.

C.

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.

D.

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.

Buy Now
Questions 433

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

Options:

A.

Establish a project schedule

B.

Assign a team leader

C.

Recognize the team's contributions

D.

Establish a team charter

Buy Now
Questions 434

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

Options:

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Acquired more than one resource skilled in each component.

D.

Facilitated cross-functional knowledge transfer during the project.

Buy Now
Questions 435

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Options:

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Buy Now
Questions 436

During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?

Options:

A.

Assign the work based on the skill sets of team members.

B.

Request feedback from stakeholders about the quality delivery.

C.

Assign the work in consultation with the functional manager.

D.

Discuss this with the team and review the quality process.

Buy Now
Questions 437

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.

Involve all of the stakeholders in the escalation by setting up a conference call.

B.

Escalate to the other party's management and inform the steering committee.

C.

Reach out to peer managers for similar escalation situations and follow past experiences.

D.

Review the established project escalation process and take the appropriate action.

Buy Now
Questions 438

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

Options:

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

Buy Now
Questions 439

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

Options:

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.

Delay developing the indirect tax module until the tax regulation comes into effect.

C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

Buy Now
Questions 440

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

Options:

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Buy Now
Questions 441

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Buy Now
Questions 442

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

Options:

A.

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.

Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.

D.

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Buy Now
Questions 443

During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.

What should the project manager do in this situation?

Options:

A.

Accept the request and commit to some benefit improvement opportunities for the project.

B.

Investigate the request and express willingness to find ways to obtain higher project benefits.

C.

Review the proposal and suggest optional benefit improvement opportunities for the project.

D.

Explain the planning and budgeting process and demonstrate that the project proposal maximizes benefits.

Buy Now
Questions 444

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Buy Now
Questions 445

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.

What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.

B.

Check with human resources (HR) regarding the availability of staff.

C.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

D.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

Buy Now
Questions 446

The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).

What should the project manager do?

Options:

A.

Inform the stakeholders that the project goals are in the business case and change requests must be submitted.

B.

Secure approval from the most influential stakeholders on the project goals and the needed functionality.

C.

Host requirements gathering meetings where all of the stakeholders can identify their project goals until agreement is reached.

D.

Develop a list of project goals, secure sponsor approval, and then socialize them with the direct and indirect stakeholders.

Buy Now
Questions 447

Drag the communication event on the left to the main subject discussed during the event on the right.

Options:

Buy Now
Questions 448

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.

Provide the team with the enterprise environmental factors (EEFs).

B.

Run a benchmark with similar sites to compare compliance constraints.

C.

Look into lessons learned documentation for similar projects.

D.

Hire a specialized engineer to support the design team.

Buy Now
Questions 449

While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What

should the project manager do to ensure a smooth delivery of the product?

Options:

A.

Involve the client in risk identification.

B.

Agree with the client on acceptance criteria.

C.

Involve the client in a performance gap analysis.

D.

Agree with the client on a new project charter.

Buy Now
Questions 450

A project manager is working on a project to develop a new watch at a matrix organization.

Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)

Options:

A.

Schedule performance index (SPI) for the portfolio

B.

Earned value in terms of resources

C.

Expected return on investment (ROI) for portfolio projects

D.

Earned value in terms of schedule

E.

Earned value in terms of cost

Buy Now
Questions 451

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel

confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product

increment with the product owner now.

What should the project manager do to mitigate this risk?

Options:

A.

Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.

B.

Schedule an additional interim demo with the product owner.

C.

Address the issue as part of the retrospective.

D.

Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.

Buy Now
Questions 452

A project manager is leading a project in a heavily regulated industry. Match the considerations on the left with the correct compliance plan categories on the right.

Options:

Buy Now
Questions 453

A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.

Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)

Options:

Buy Now
Questions 454

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

Options:

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Buy Now
Questions 455

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?

Options:

A.

Ask the team to adapt based on their current resources.

B.

Plan a meeting with the stakeholders to get more resources.

C.

Replan the upcoming deliverables based on the available tools.

D.

Ask the project sponsor to provide the needed resources.

Buy Now
Questions 456

Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Set up a team building event to bring synergy back to the project team.

B.

Adjust the project manager's management style to better fit senior team members.

C.

Ask for advice on how to be a better mentor to these team members.

D.

Meet daily with each senior team member to monitor project status.

Buy Now
Questions 457

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.

However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives

as planned, but also wants to accommodate new information and changes as the project progresses.

Which project management approach should the project manager select for this project?

Options:

A.

Hybrid

B.

Incremental

C.

Agile

D.

Phased

Buy Now
Questions 458

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

Options:

A.

Escalate the issue of the additional requirements to the executive leadership team.

B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).

C.

Implement all the requirements the customer has requested.

D.

Adjust the scope baseline and schedule baseline accordingly.

Buy Now
Questions 459

A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?

Options:

A.

Update the risk management plan and send it to the project team.

B.

Update the schedule baseline to the new project time line.

C.

Escalate the issue to senior leadership for resolution.

D.

Work with relevant stakeholders to determine possible solutions.

Buy Now
Questions 460

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).

These changes would improve the project outcome.

What should the project manager do next?

Options:

A.

Conduct an audit on the procurement process and inform the vendor about the audit's observations.

B.

Assess the situation as an opportunity for improvement and perform a risk analysis.

C.

Consult the list of selected vendors for the bid and evaluate a possible change of vendor.

D.

Revise the procurement control process to avoid undesired changes that might affect the schedule.

Buy Now
Questions 461

The key stakeholders of a project would like to be actively involved in the review of product increments.

What should the project manager do?

Options:

A.

Analyze their interest and influence to manage expectations.

B.

Update the communications management plan for key stakeholders.

C.

Identify the needs and expectations of key stakeholders.

D.

Encourage their participation in release and sprint reviews.

Buy Now
Questions 462

A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution

team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.

What should the project manager do next to deliver a reliable solution?

Options:

A.

Meet with the resources and agree that the more experienced resource's approach has proven to be effective in the past.

B.

Meet with each resource's functional manager and arrive at a common approach that is appropriate for the project's constraints.

C.

Meet with the entire project team and decide on a further course of action based on team consensus.

D.

Meet with the resources together and find common ground on viewpoints to compromise on an approach.

Buy Now
Questions 463

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Buy Now
Questions 464

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

Options:

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

Buy Now
Questions 465

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project

manager use to manage these risks using an agile approach?

Options:

A.

Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.

B.

Implement a scrum risk retrospective to analyze the risks at the end of the project.

C.

Assign an agile risk manager to better understand and track the project risks.

D.

Evaluate the risks constantly and reprioritize work as the project progresses.

Buy Now
Questions 466

A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.

Which are three fundamental actions the project manager should take? (Choose 3)

Options:

A.

Decide on the frequency of communications.

B.

Define key performance indicators (KPIs) to measure and report.

C.

Determine the appropriate methods of communication.

D.

Identify the level of detail needed by different stakeholders.

E.

Obtain executive approval on the communications management plan.

Buy Now
Questions 467

A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?

Options:

A.

Tell the supplier that they have an obligation to supply the raw material.

B.

Search for a new supplier that can deliver the same materials on time.

C.

Seek advice from the legal department and implement penalties.

D.

Assess the possible impact of the raw material shortage on the project.

Buy Now
Questions 468

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Buy Now
Questions 469

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Increase the team capacity to finish the project on time.

B.

Register an issue and escalate it to the project sponsor.

C.

Invite the stakeholders to discuss a new prioritization.

D.

Estimate the impact and consult with the product owner.

Buy Now
Questions 470

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second

iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

Options:

A.

Ask the product owner to add the missing feature in the backlog.

B.

Invite stakeholders to discuss the impact of adding the regulatory feature.

C.

Estimate the related cost and ask for a project extension.

D.

Increase the capacity of the team to include the missed feature.

Buy Now
Questions 471

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two

projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.

What kind of leadership style should the project manager utilize for the current project?

Options:

A.

Transformational

B.

Interactional

C.

Laissez-faire

D.

Charismatic

Buy Now
Questions 472

A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

Options:

A.

Organize the team members into several kick-off sessions based on technology type.

B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.

C.

Ask the human resources (HR) department to arrange interview meetings to select the team.

D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.

Buy Now
Questions 473

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

Options:

A.

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.

Prepare to perform the duties of the cost controller for the duration of the project.

C.

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

Buy Now
Questions 474

A compliance manager announces a new policy issued by the government that may impact project development.

How should the project manager respond?

Options:

A.

Continue with project execution as per the previously approved project plan.

B.

Maximize delivery by including this policy in the process.

C.

Address any blockers to the project due to this policy and resolve them.

D.

Analyze the circumstances that brought about this new policy.

Buy Now
Questions 475

An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.

How can the project manager ensure that the appropriate acceptance criteria are applied to the features?

Options:

A.

Define the acceptance criteria and specific functional test cases only after analyzing the user feedback from testing the early feature release.

B.

Integrate the acceptance criteria review into the definition of ready (DoR) for each feature and associated tests into the feature's definition of done (DoD).

C.

Use the broadest set of acceptance criteria to ensure that all features have a common quality baseline and associated functional test cases.

D.

Integrate the specific tests into the definition of ready (DoR) for each feature and the acceptance criteria into the feature's definition of done (DoD).

Buy Now
Questions 476

A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

Options:

A.

Impact value

B.

Expected monetary value (EMV)

C.

Net present value (NPV)

D.

Earned value (EV)

Buy Now
Questions 477

Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.

What should the project manager do?

Options:

A.

Speak individually with the team members who do not participate in conversations.

B.

Manage time efficiently using the agenda and ask each participant to contribute.

C.

Speak individually with the team member who always disrupts the conversations.

D.

Start the meeting with a review of the ground rules, meeting objectives, and the agenda.

Buy Now
Questions 478

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

Options:

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

Buy Now
Questions 479

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

Options:

A.

Discuss this issue with the affected team members and support them during the transition.

B.

Start looking for replacements as soon as possible to help prevent any schedule slippage.

C.

Engage with the project sponsor to ensure that this change does not affect the project execution.

D.

Determine the impact to the project and implement mitigations per the project management plan.

Buy Now
Questions 480

Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.

What should the project manager do?

Options:

A.

Assemble the entire project team to produce new flowcharts from current versions.

B.

Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.

C.

Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.

D.

Work with a consultant and the project sponsor to produce new flowcharts.

Buy Now
Questions 481

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

Options:

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Buy Now
Questions 482

A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the

deployment.

What should the project manager have done to prevent the delay?

Options:

A.

Obtained all critical information ahead of time

B.

Involved upper management in the process

C.

Involved the customer in the deployment process

D.

Used the sample data already in place

Buy Now
Questions 483

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

Options:

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Buy Now
Questions 484

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

Options:

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

Buy Now
Questions 485

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

Options:

A.

Establish a probability and impact matrix and plan response criteria.

B.

Disregard the situation since it is not hindering the project deliverables.

C.

Develop a joint policy among the various organizations.

D.

Escalate the issue to the project sponsor and seek their guidance.

Buy Now
Questions 486

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

Options:

A.

Mitigate the risks that are applicable to the current and following iterations.

B.

Focus on the project deliverables rather than the documented risks.

C.

Agree that any issue can be handled when it becomes a problem.

D.

Acknowledge that the risks will be handled in the corresponding iteration.

Buy Now
Questions 487

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

Options:

A.

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.

B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.

Ensure that the project backlog has the features and stories prioritized correctly.

D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Buy Now
Questions 488

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Buy Now
Questions 489

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

Buy Now
Questions 490

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

Buy Now
Questions 491

A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.

What should the project manager do?

Options:

A.

Remove the development team's rejected feature from the backlog.

B.

Reassure all team members that the development team will fix the issue.

C.

Initiate an improvement plan for the development team to follow.

D.

Evaluate the context for the conflict with the development team.

Buy Now
Questions 492

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

Options:

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

Buy Now
Questions 493

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

Options:

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

Buy Now
Questions 494

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate most authorities and control the authority by withholding important information.

B.

Delegate certain authorities and control the authority by withholding important information.

C.

Delegate certain authorities and share information to allow fair decision-making.

D.

Delegate most authorities and share information to allow fair decision-making.

Buy Now
Questions 495

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Buy Now
Questions 496

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

Options:

A.

Product roadmap

B.

User stories

C.

Business requirements document

D.

Product backlog

Buy Now
Questions 497

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?

Options:

A.

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.

B.

The scrum master should ensure the appropriate escalation to resolve the issues.

C.

The product owner owns the open issues until they are resolved.

D.

Individual team members need to submit service desk tickets to resolve the issues.

Buy Now
Questions 498

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

Options:

A.

Use templates from an existing project.

B.

Ask the project management office (PMO) for guidance.

C.

Surveying peers to understand what templates they have used.

D.

Lead the project team in finding the best templates.

Buy Now
Questions 499

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no

longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,

and there is no capacity for any developer to take on additional work.

What should the project manager do next to fulfill this resource need?

Options:

A.

Determine resource allocation options based on project priority.

B.

Apply changes to the existing resource allocations and inform the development manager.

C.

Meet with the sponsor to determine how to rebaseline the schedule.

D.

Inform the sponsor of the situation and request an extension of the target completion date.

Buy Now
Questions 500

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is

a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service

team is overwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose two)

Options:

A.

Contact the customers in batches and inform them that the issues are being worked on currently.

B.

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.

C.

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.

D.

Ask senior management to replace the customer service manager with a more qualified one.

E.

Request that the customer service team prioritizes work on queries that are received this week.

Buy Now
Questions 501

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Buy Now
Questions 502

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Options:

Buy Now
Questions 503

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

Options:

A.

Include the local union representative in the high-power, high-impact stakeholder group

B.

Focus on the sideward stakeholders only and let the organization manage the community.

C.

Build channels to extend communication efforts to the local community

D.

Use the city administration to address communication with the community

Buy Now
Questions 504

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

Options:

A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.

Update the schedule and project risk register according to the regulatory requirement.

C.

Consult the project management plan for guidance on addressing the regulatory requirement.

D.

Assess the impact of implementing the potential regulatory requirement on the project.

Buy Now
Questions 505

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

Options:

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Buy Now
Questions 506

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.

Share project documentation in a repository with exclusive access.

B.

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.

Send periodic emails to senior management with the latest project updates.

D.

Keep project artifacts up-to-date and accessible to all stakeholders.

Buy Now
Questions 507

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Buy Now
Questions 508

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

Options:

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Buy Now
Questions 509

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Buy Now
Questions 510

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Buy Now
Questions 511

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Buy Now
Questions 512

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Buy Now
Questions 513

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

Options:

A.

Work more closely with the agile team to eliminate the need for progress reports

B.

Record this in the issue log and find a resource to produce the reports

C.

Produce the progress reports on their own

D.

Engage a new resource to produce the progress reports

Buy Now
Questions 514

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Buy Now
Questions 515

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

Options:

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Buy Now
Questions 516

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Buy Now
Questions 517

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

Options:

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Buy Now
Questions 518

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

Buy Now
Questions 519

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Buy Now
Questions 520

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Options:

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Buy Now
Questions 521

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Buy Now
Questions 522

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Buy Now
Questions 523

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Buy Now
Questions 524

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

Options:

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Buy Now
Questions 525

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Buy Now
Questions 526

As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?

Options:

A.

Include this topic in the next iteration retrospective

B.

Review this topic with the product owner before the next iteration planning

C.

Discuss this topic with the team in the next daily meeting

D.

Ask the product owner to review this topic in the next iteration planning

Buy Now
Questions 527

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Buy Now
Questions 528

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Buy Now
Questions 529

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Buy Now
Questions 530

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Buy Now
Questions 531

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

Options:

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Buy Now
Questions 532

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Buy Now
Questions 533

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

Options:

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Buy Now
Questions 534

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Buy Now
Questions 535

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?

Options:

A.

Schedule training courses to enhance team performance

B.

Add new team members to help the project finalization

C.

Initiate rewards and incentives according to assessment results

D.

Schedule working lunch meetings until the project is complete

Buy Now
Questions 536

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact to

the project value.

Buy Now
Questions 537

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Buy Now
Questions 538

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Buy Now
Questions 539

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

Options:

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Buy Now
Questions 540

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Buy Now
Questions 541

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

Options:

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

Buy Now
Questions 542

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Buy Now
Questions 543

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

Options:

A.

Autocratic decision making

B.

Expert judgment

C.

Context diagram

D.

Change control tools

Buy Now
Questions 544

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Buy Now
Questions 545

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Buy Now
Questions 546

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Options:

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Buy Now
Questions 547

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Buy Now
Questions 548

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

Options:

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Buy Now
Questions 549

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Buy Now
Questions 550

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Buy Now
Questions 551

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Buy Now
Questions 552

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

Options:

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

Buy Now
Questions 553

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Buy Now
Questions 554

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Buy Now
Questions 555

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Buy Now
Questions 556

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Buy Now
Questions 557

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every

iteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential

information.

Buy Now
Questions 558

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Buy Now
Questions 559

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Buy Now
Questions 560

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Buy Now
Questions 561

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Buy Now
Questions 562

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Buy Now
Questions 563

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Buy Now
Questions 564

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

Options:

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Buy Now
Questions 565

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

Options:

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Buy Now
Questions 566

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute to

projects.

B.

Assign employees to agile projects so they can quickly adjust to the new approach.

C.

Train all employees in agile approaches.

D.

Shift the way the company views, reviews, and assesses employees.

Buy Now
Questions 567

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Buy Now
Questions 568

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Aug 17, 2025
Questions: 1988