A project manager has been asked to participate in the procurement process for a
software application that allows customers to buy online e-learning courses. The project
manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement
How should the project manager respond to the suggestion?
A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.
How should the project manager address this issue?
In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?
During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product
After collecting the new requirements, what should the project manager do?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.
How should the project manager approach this situation?
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.
What should the project manager have done to prevent this situation from occurring?
An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.
What should the project manager recommend?
A stakeholder is requesting that the project manager share project status updates
on a regular basis. This stakeholder is not included in the regular distribution list.
What should the project manager do?
A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?
A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.
What should the project manager do?
A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.
What should the project manager have done to avoid this issue?
A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?
A project manager is meeting with the project sponsor regarding a new project.
The project manager tells the sponsor that, as part of the communications management
plan, a weekly email will be sent with the status of the project, so the sponsor can be
informed of the progress. The sponsor indicates that the email is not necessary because
they will ask for a status update whenever it is needed.
What should the project manager do next?
A labor union contract negotiation is delaying the completion of a project to build
a new manufacturing plant. Because the labor contract was due for renewal this year, the
project manager documented the negotiation process as a risk to the project. The project
was about to start the first phase of equipment installation at the plant when the negotiation began.
How should the project manager address the situation?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
In the past, the project manager and the project team performed well using
predictive methodology. However, the organization recently decided to adopt agile
approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations? (Choose
two)
The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?
During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.
The customer is asking the project manager for guidance.
What should the project manager do?
During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?
A project sponsor receives project information and updates in a timely manner, but
the sponsor is concerned because key information is missing in the reports. What should the
project manager do?
During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.
What should the project manager do first?
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.
How should the project manager proceed in order to complete the risk register?
During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.
What should the project manager do first?
A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.
At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.
How should the project manager ensure project success?
In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.
What should the project manager do to handle this situation?
A company has hired a vendor to deliver a scope of work and assigned a project
manager to oversee the project. The vendor advised that they completed the scope
successfully and is asking for approval.
What should the project manager do in response to this request?
A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?
One of the service providers on a complex project has been facing resource
availability problems over the last six months. However, the service provider has assured the
project manager that the deliverables will be on time.
How should the project manager address this situation?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
During the execution phase, the project manager discovered that the deliverables
are not meeting the quality specifications requested by the main stakeholder. This has
caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost
performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being
rejected during the next iteration?
Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.
What should the project manager have done to prevent this situation from happening?
A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.
What should the team member do?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
A project started 12 months ago and is currently on iteration 12 of 14. The team
has performed well and completed all deliverables on time. However, some team members
are starting to complain about the length of the project, creating a risk for lack of
performance at this critical stage.
What should the project manager do as a servant leader to mitigate this risk?
According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not
delivered, the company could receive a fine from the government. What should the project manager do?
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.
What should the project manager do next?
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?
A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?
An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance
team is requesting a project budget for the new product.
What should the team do to address this request?
A large organization decided to adopt an agile methodology based on the trends
seen in the industry. The organization invested a large amount of money in adopting it, but
after a few months, the implementation failed.
What should the project manager have done differently to avoid the implementation failure?
A project team is conducting a retrospective. The team wants to identify what had
a positive impact on the velocity and keep doing it.
Click on the area that the team should focus on to identify good practices.
A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?
A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.
A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.
How should the project manager handle this issue?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors
What should the project manager do?
A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.
Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.
What should the project manager have done?
A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.
How should the project manager communicate the organizational culture and project goal to these stakeholders?
An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.
What should the project manager do to help move the project forward?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?
During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?
A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?
A project manager is working on a major construction project. Part of the
agreed-upon plan was to use a cloud-based system with a server that runs on high-speed
internet service since most of the team members work virtually. The company needs to
reduce operating costs as much as possible and management insists that the project will
now use a system running on a conventional dial-up service.
What should the project manager do next?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.
What should the project manager do?
A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project
Which two actions can the project manager take to bring the team back on track? (Choose two)
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?
During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?
A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.
Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.
The company asked the project manager to explain the value gained by using an agile process.
How should the project manager respond?
In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.
After getting more information about the new manager, what is the project manager's next step?
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager
schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?
A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested
in the product design.
How should the project manager deal with this situation?
A project team consisting of various professionals of different nationalities is struggling to achieve their project deliverables. What should the
project manager do?
A project manager is using a hybrid approach for project delivery. The
development team was sized, but is not yet fully resourced. The project manager is working
on defining the project schedule.
What should the project manager do to address the issue of developer availability?
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:
Approved Work Package Cost Estimates: US$9,500
Contingency reserves: $500 %
Management reserves: 10% of contingency reserves
Percent complete of the project: 50%
Planned percent of the project: 40%
Actual costs of the project: US$4,500
What is accurate about the project status?
A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?
A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.
What should the project manager do to build consensus regarding the requirements?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
Drag the organizational characteristics on the left to the correct scenario on the right
During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?
A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?
The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery
What should the project manager do?
While developing a new product, a key stakeholder expresses concern about
insufficient information on product feature requirements. The product team disagrees and
mentions that detailed requirements have been provided.
What should the project manager do to handle this situation?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals
What two options will help the team initially address this obstacle? (Choose two)
Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable
What should the project manager do next?
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings
How should the project manager handle this?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?
A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team
What should the project manager do?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?
During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.
What should the new project manager do to address the process improvements?
A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.
What should the project manager do?
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement
What should the project manager do next?
A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog
What should the project manager do?
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project
What should the project manager do first?
The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible
What three actions should the project manager take to address this situation? (Choose three)
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.
What does the project manager need to do first?
During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task
What should the project manager do to obtain the information required by the developer?
During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client
Match the scenario on the left with the action on the right.
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects
What should the project manager do?
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks
Drag each risk type on the left to its correct example on the right
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?
During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.
What should the project manager do?
During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.
What should the project manager pay special attention to in order to achieve this goal?
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?
An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply
Which two actions should the project manager take? (Choose two)
During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project
What should the project manager do?
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected
What should the project manager do going forward?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches
What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget
What should the project manager do next?
A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?
A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted
a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After
3 days of work, the project manager completed two actions and spent US$80,000.
What should the project manager do next?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change
What should the project manager have done to avoid this situation?
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.
What should the project manager do?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using
What should the project manager have done to avoid this issue?
Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel
How should the project manager handle this situation?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?
Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)
A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?
A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.
What should the project lead do in this situation?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project
What should the project manager do?
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck
An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.
What should the project manager do first to ensure team adherence to the ground rules?
A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?
A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change
What should the project manager do?
A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped
What should the project manager do?
The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible
What should the project manager use to identify the risks?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
An agile project team is looking to develop quality standards for a project How should the project manager coach the team?
The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members
What should the project manager do?
A project to implement a new process is still in development. When implemented,
the company will benefit by a reduction in utility costs. The project financial evaluation
indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product
being developed has discrepancies with the one requested by the customer.
What should the project manager do?
At the end of a project, one of the suppliers is facing financial difficulties and is
pushing the project manager to obtain financial, legal, and administrative approval in order to
communicate formal project closure and ensure the transfer of liability. What should the
project manager do next?
A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype
What should the project manager do to accelerate this solution?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the
customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during
project execution?
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?
A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team
What should the project manager do first to solve the situation?
A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward
What should the project manager do first at this pomp
A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies
When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?
A project team is executing a project to replace an existing system with a new one.
A new project manager has been hired and observes that the team consist of professionals
who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet
What should the project team have done to avoid this issue?
During project execution, an important stakeholder threatens to withdraw support
for the project, citing a lack of transparency and accountability in the way the project is being
executed. What should the project manager do to handle this situation?
A project manager is leading an automation project. The project team is colocated
and includes people from both the technical and business units. The project manager
discovers that personal differences and work styles are affecting the project negatively.
How should the project manager address this?
A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted
What should the project manager do?
A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.
What should the project manager do?
A project sponsor has requested a trend analysis of all risks that the project has
monitored over the past 12 months. What should the agile project manager do?
A project manager is leading a project that is in the execution phase. During a team
meeting, the project manager realizes that there are two team members who lack the
technical skills required for some of the upcoming tasks.
What should the servant leader project manager do next?
A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
A team is developing an experimental program to be used by the public. What should
the project manager do to ensure the desired benefits are achieved?
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
A project manager finds out that the required project status reports have not been
filled out by most team members. These status reports are urgently needed to compile a
comprehensive status report for the project sponsor.
What should the project manager do to address this situation?
A project manager is leading an integration project for a retail company. The project
demands a lot of time from the stakeholders to make important business decisions. The
project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this
project?
A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?
A project manager has experience working with a specific provider that has been
requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
A project team delivered a critical deliverable to the customer. The customer
complained that the maintenance manual was not included.
What should the project manager do next?
A project leader is assigned to a new project and is asked to assemble an effective
five-member agile team. If the project leader has no restrictions, which team should they
choose?
A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project
How should the agile leader ensure successful delivery?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?
A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own
What should the project manager do?
A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations
One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?
us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project
How should the project manager report this cost?
A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
In a hybrid project, 100 new base stations are being added to a 4G mobile network
every month. At the end of the first month, the team is behind the target and the operator is
losing money. The stakeholders are requesting information on when the base stations can go
live and begin to bill.
What should the project manager do to take the schedule back and accelerate the return on
investment (ROI) of the project?
A project manager is leading the first agile project for the organization. During the
kick-off meeting, the project manager notices that the team does not have the same
understanding about agile approaches. The project manager is concerned about the impact of that confusion.
What should the project manager do to address this situation?
An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.
What should the project manager do?
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''
A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.
What should the project manager do next?
A complex, high-value agile project includes sprint demonstrations with the customer
every four weeks. Executive management is concerned about the project's progress and
wants more frequent updates on the project status.
What should the project manager do?
A retail company identifies that it is losing sales because customers are not promptly
informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.
Considering the objective to deploy customer value, which project life cycle approach should be chosen?
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?
A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?
In a software project using an agile approach, there have recently been work
overruns. After assessing the situation, the project manager concluded that the overruns are
occurring because of insufficiently refined product backlog items.
What should the project manager do to correct this issue?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
A project is on its sixth iteration out of seven. Select the two points where the team is
performing better than expected. (Choose two.)
As a project is reaching completion, the project sponsor tells the project manager to
immediately close the project and to move on to another project. Which critical task should the
project manager complete before closing the project?
A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff
What should the project manager do first?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.
What should the project manager do?
A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.
What should the project manager do?
A project manager is working with an agile team to enhance a product. Due to a
tight deadline, the team is trying to crash the schedule by engaging multiple resources to work
on the project simultaneously. However, the technical environment is configured to allow only
one resource to work on a feature at a time. The team plans to upgrade the technical
environment but is unable to agree on a way forward.
What should the project manager do first?
A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback
What should the project manager do to resolve the issue?
A project manager has been assigned with initiating a large project to deliver
complex equipment. Part of the project will be the result of a long research process, but once
this is completed, the other part of the project must be incrementally delivered to the
customer.
Which approach should the project manager choose for this project?
An organization started the process of a digital transformation and is trying to change
its culture from a predictive to a more agile approach. The project manager leading the
change management process identified some knowledge gaps of key team members, which
could prevent the transformation from happening as planned.
What should the project manager do?
A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
A newly appointed product owner is working with a project team that is using agile
for the first time. The product owner is constantly disrupting various team members throughout
the day to discuss progress. This has resulted in the team feeling micromanaged and
frustrated because of the constant disruptions.
How should the project manager proceed?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some
reserves needed
What should the project manager do to successfully complete the next phase?
A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.
What should the project manager do next?
A project manager is assigned to a new project and is allocated with virtual team
members. Later, two more members from a recently acquired company join as additional
resources to the project team.
In order to ensure that there are no potential misunderstandings, what should the project
manager do?
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract
What should the project manager do?
The sponsor approaches the project manager with new features they want added to
the project. The project is 95% complete, but the sponsor insists that continued support for the
project relies on the addition of the new features.
What should the project manager do?
A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
A project team consists of members based in country A and subject matter experts
(SMEs) based in country B with a 12-hour time difference. What can the project manager do
to improve interactions between the team members in both countries?
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.
What should the project manager do next?
During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.
What should the project manager do to address the issue?
A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.
Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)
During the project planning phase, a project manager called a meeting to discuss the
product backlog with multiple stakeholders who represent the end users in various capacities.
Only one executive manager attended the meeting.
What should the project manager do?
An agile team was hired to work on a public service project. The team received a
list of vague ideas about the business and now needs to understand, develop, and prioritize a
list of functionalities.
Who will be responsible for this task?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities
What should the team do differently during planning for the next iteration"?
Vendor A submitted a bid for US$500,000. There is a 65% probability that the
vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come
in ahead of schedule for a savings of US$50,000.
What should the project manager determine as the value of the vendor's bid?
A project requires testing of the final product to be done at another department's
testing facility, which is known for having low availability. This situation could potentially
impact the project schedule.
What should the project manager do next?
Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.
What should the project manager do to resolve this issue and help the team move on to the next iteration?
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?
A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification
What should the project manager do?
A project manager is assigned midway through a project. The team members are in
different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?
A project manager receives a serious complaint from a functional manager about a
team member. What should the project manager do?
During the setup of an agile project, the product owner expressed clear interest in
having features released during product development over having the product completed in
one year. What should the project manager do?
A new project manager is managing a hybrid project. The project manager wants to be
a servant leader to support the team by removing impediments but is not receiving feedback
from the team about the issues and risks they are facing.
What should the project manager do?
A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.
What should the project manager do to address this issue?
A project manager is working on a highly complex project. During the execution of
the project, the local government changed certain environmental regulations, which could
potentially delay the project.
What immediate action should the project manager take?
A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days
What should the project manager do first to maintain the project team's performance level?
A project manager has been assigned to a new project. There is one team member
who never says anything during meetings. After meetings, however, the team member sends
detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.
What should the project manager do?
A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the
team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?
A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the
project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’
experience as an agile practitioner working as a scrum master.
What should the project manager do at the start of the project?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to
ensure the community members are up to date on project progress?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market
while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.
What should the project manager do to avoid a reoccurrence of this scenario?
A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.
What should the project manager do?
A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.
What should the project manager do to manage this situation?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
One of the team members is always late to the daily standup meeting. What should the project manager do?
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information
should the project manager provide so that senior management can get a broader view of the project?
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.
What should the project manager do?
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team
to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.
What should the project manager do?
A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.
How should the project manager resolve this conflict?
A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.
What should the project manager do to address this problem?
A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has
identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.
What should the project manager do first?
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members
on the team who have more experience with similar tasks.
What should the project manager do?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.
How should the project manager proceed?
After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.
What should the project manager do first?
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work
How should the project manager approach the situation?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.
What should the project manager do?
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to
ensure the project is delivered successfully?
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?
A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of
risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk
mitigation plan.
What should the project manager do?
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?
An experienced project team member always points out the issues of other team members during meetings. The other team members feel that
the experienced team member is deflecting their own issues in meetings.
What should the project manager do?
A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.
What should the project manager's first action be?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.
What should the project manager do?
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.
What should the project manager, who is responsible for this project, do to mitigate this risk?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much
experience in development.
What should the project manager do?
A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle
What should the project manager do next?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.
What should the project manager do?
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.
Which technique will best serve this purpose?
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.
What should the project manager do?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.
What should the project manager do?
A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly
requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes
of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?
During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to
reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project
manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide
upon the most effective way to communicate progress.
What should the project manager do?
A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical
complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?
An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they
are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?
A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager
discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The
remote team member feels they are not being adequately rewarded and recognized for their job.
What should the project manager do?
A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a
critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining
that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.
What should the project manager have done differently?
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the
project?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.
What should the project manager do next?
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low.
What should the project manager do?
A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.
Which statement is true?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.
What should the project manager do next?
An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile
practices, which are relevant to the project.
What should the project manager do in order to gain buy-in from the different stakeholders?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?
A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?
An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.
What should the project manager do first?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to
enhance the budget estimations for the project?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.
What should the project manager have done to avoid this setback?
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,
among other critical blockers.
What should the project manager do?
An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.
What should the project manager do first?
A project manager is looking for ways to keep the budget on track throughout the project life cycle.
What should the project manager do to ensure that happens?
During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.
What should the project manager do?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.
What should the project manager do to help ensure a successful outcome for the project?
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that
there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.
What should the project manager do?
In a review session held halfway through the project's development, several important stakeholders voice extreme dissatisfaction with the solution's current development versus what they had agreed were the goals and outputs of the project. One of the more prominent individuals threatens to close the project immediately. With no dissatisfaction having been voiced at prior sessions, the project manager is surprised.
How should the project manager respond during the session?
A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was
appointed to attend the first meeting with the auditors scheduled for the following week.
What should the project manager do to prepare for the audit?
A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.
What should the project manager do to manage such a situation for upcoming phases?
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?
A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?
A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.
What should the project manager do?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.
What should the project manager do to integrate the diverse stakeholder groups?
In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a
specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted
the import of this machine model.
What should the project manager have done to prevent this from happening?
Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.
What should the project manager have done to prevent this?
A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.
What should the project manager do first?
A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.
What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?
A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?
A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is
identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact
on the project outcomes.
What should the project manager do next?
A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.
What should the project manager do next?
A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will
vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team
makes a decision that the project lead strongly disagrees with.
How should the project lead proceed?
The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,
which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.
What should the project manager do first to address this situation?
During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.
What should the project manager do in this situation?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.
What should the project manager do first?
The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).
What should the project manager do?
Drag the communication event on the left to the main subject discussed during the event on the right.
During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.
What should the project manager do?
While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What
should the project manager do to ensure a smooth delivery of the product?
A project manager is working on a project to develop a new watch at a matrix organization.
Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)
An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel
confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product
increment with the product owner now.
What should the project manager do to mitigate this risk?
A project manager is leading a project in a heavily regulated industry. Match the considerations on the left with the correct compliance plan categories on the right.
A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.
Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)
A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.
What should the project manager do to address this risk?
A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?
Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.
However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives
as planned, but also wants to accommodate new information and changes as the project progresses.
Which project management approach should the project manager select for this project?
A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.
What should the project manager do next?
A project schedule risk has turned into an issue. The project manager foresees delays in project execution.
What should the project manager do to resolve the issue?
After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).
These changes would improve the project outcome.
What should the project manager do next?
The key stakeholders of a project would like to be actively involved in the review of product increments.
What should the project manager do?
A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution
team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.
What should the project manager do next to deliver a reliable solution?
An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.
What should the project manager do?
Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project
manager use to manage these risks using an agile approach?
A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.
Which are three fundamental actions the project manager should take? (Choose 3)
A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried
to contact the consultant but has been told that the consultant does not have the time to discuss the project.
What should the project manager do to move the project forward?
A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?
A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second
iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two
projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.
What kind of leadership style should the project manager utilize for the current project?
A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.
How should the project manager build a cohesive, high-performing team?
A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.
What should the project lead do to obtain the needed resources?
A compliance manager announces a new policy issued by the government that may impact project development.
How should the project manager respond?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?
Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.
What should the project manager do?
While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.
What should the scrum master do?
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.
What should the project manager do next?
Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?
A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the
appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?
A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the
deployment.
What should the project manager have done to prevent the delay?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.
What should the project manager do next?
A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.
What should the project manager do first to evaluate the cultural differences within the organizations?
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.
What should the project lead do?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?
A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on
the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?
In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.
What should the project manager do?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.
What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?
A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.
What should the project manager use to explain the project scope?
To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.
How should these issues be resolved?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no
longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,
and there is no capacity for any developer to take on additional work.
What should the project manager do next to fulfill this resource need?
A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is
a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service
team is overwhelmed with these unresolved queries.
Which two actions should the project manager take to correct this problem? (Choose two)
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation''
A project manager was notified about a new regulatory requirement that could impact the project schedule.
What should the project manager do first?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution
phase and will affect a few key workers’ licenses, which will become noncompliant.
What should the project manager do?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the
project. How should the project manager resolve this?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.
How should the project manager resolve this conflict?
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.
What should the project manager do?
A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.
What should the project manager do to support the team?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.
What should the project manager do given the urgency?
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time
What should the project manager do next?
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.
What should the project manager do?
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity
issues joining team calls during the day.
What should the project manager do?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager
believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the
technology.
What should the project manager do?
In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?
Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.
What should the project manager do?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline
What should the project manager do next?
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?