A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?
A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?
A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress
(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.
What should the project manager do first?
A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
A project team has transitioned to full-time remote working. The project manager
started noticing that some team members have not been completing their assigned tasks by
the planned dates despite reminders during weekly team meetings. This has the potential for
delaying the project delivery.
How should the project manager resolve this situation?
A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.
What should the project manager do?
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.
What should the project manager do first?
A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.
What should the project manager do to select the most effective project framework?
A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.
How should the project manager recognize high performance?
A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?
A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.
What should the project manager do first?
An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.
What should the project manager do to help the project team?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.
Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.
How should the project manager handle this situation?
In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.
What should the project lead do?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A project manager is leading a project team that consists of five team members. One of the team members, a senior technical staff member, always criticizes the ideas of other members during team meetings. However, this senior technical member is not performing well on their own daily tasks. Other team members are frustrated and have become silent in meetings.
What should the project manager do?
A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV)
to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will
vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team
makes a decision that the project lead strongly disagrees with.
How should the project lead proceed?
During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements
Which technique should the project manager use to resolve this issue?
A project team has been together for a long time and has been led by three different
project managers. Lately, the performance of one of the team members has been declining
and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and
sustained?
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)
A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members
available who are qualified to complete the work.
What should the project manager do?
A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was
appointed to attend the first meeting with the auditors scheduled for the following week.
What should the project manager do to prepare for the audit?
During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.
What should the project manager do next?
A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.
What should the project manager do to address this situation?
A project manager is leading a major water pipeline project and realizes midway into
the project that the project completion date is not achievable. Local farmers who rely on the
water for irrigation may be affected due to the delay. The project manager is afraid of their
displeasure and reaction, which will affect the project.
How should the project manager plan the communication to the stakeholders?
A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated
by other team members.
Which three actions should the project manager take? (Choose three)
A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.
What should the project manager recommend?
A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequate
authorization to make the decision themselves but is not quite sure.
What should the project manager do next?
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Update the issue log and refer to the resource management plan to address the situation.
Ask the team for extra work to fulfill the project commitment.
Reduce the scope of the project and inform stakeholders.
A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.
What should the project manager do next?
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.
During the iteration retrospective, the team realizes that the complexity of the work was underestimated.
What should the project manager do?
A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.
What should the project manager have done to prevent this?
A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a
successful project completion?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?
A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an
approval from the design department will be needed.
What should the project manager do?
Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.
What should the project manager do?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,
among other critical blockers.
What should the project manager do?
A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.
What should the project manager do?
In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.
Which action should the project manager avoid?
A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?
A project manager works with a multifunctional team. During a review meeting, two team members disagree on the development approach.
What should the project manager do?
Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.
What should the project manager do first?
A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.
What can the project manager do to gain the support of the stakeholder?
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
A project with multiple teams recently transitioned from a predictive approach to agile
as requested by the product owner. Midway through implementation, a team member noticed
there was no technical capability to support the current business requirement; therefore, the
project will need to be reworked and the issue needs to be communicated to all stakeholders.
What should the agile project lead have done to avoid this situation?
During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts
What should the project manager do?
A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.
What should the project manager do?
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.
What should the internal project manager do first?
A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.
What should the project manager do?
A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the
customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during
project execution?
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion.
What should the project manager do?
A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations?
(Choose two)
A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and
efficiency of the risk management process.
What should the project manager use to accomplish this?
A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.
What should the project manager do?
A junior team member escalates an issue to the project manager about another
member's interpersonal skills causing the team to be less effective.
What should the project manager do first?
The team architect resigned from the company. The new architect points out a
design flaw during a planning meeting that may potentially impact the final quality.
What should the project manager do first?
A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.
What should the project manager do first?
A project manager is working on a project to develop a new watch at a matrix organization.
Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?
A project manager has been assigned to a new project. There is one team member
who never says anything during meetings. After meetings, however, the team member sends
detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.
What should the project manager do next?
A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
A key project stakeholder does not attend any of the project meetings and is
providing false information that the project team is not delivering on time. What should the
project manager do to address this situation?
A project manager is appointed to manage an infrastructure project that spans
across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.
What should the project manager do to ensure good collaboration between the remote project team members?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
In a software project using an agile approach, there have recently been work
overruns. After assessing the situation, the project manager concluded that the overruns are
occurring because of insufficiently refined product backlog items.
What should the project manager do to correct this issue?
A project manager has been assigned to a project that is in progress. The project
manager is looking for information regarding why the project is being completed.
What should the project manager do first?
A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to
enhance the budget estimations for the project?
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.
What should the project manager do?
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?
A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.
What should the project manager do to lead the project?
A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?
When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the
importance of this document to the project manager?
A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two)
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.
What should the project manager do next?
Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team
interactions must be considered.
How should the project teams interact in their meetings?
A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.
How should the project manager continually evaluate the effectiveness of the virtual team's engagement?
An agile project is in its ninth of 10 iterations. The team is delivering the work as expected. In the planning session, the team identifies a dependency with another project in the organization.
What should the scrum master do in order to accomplish the iteration goal?
Due to contractual issues, a key team member cannot travel to the project location for a design review meeting.
What should the project manager do?
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?
A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.
Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)
A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.
What should the project manager do next?
A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is
a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service
team is overwhelmed with these unresolved queries.
Which two actions should the project manager take to correct this problem? (Choose two)
A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After
discussing these concerns with the team, it is determined that the project does not have the full support of senior management.
What should the new project manager do next?
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause
analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time
What should the project manager have done to avoid this delay?
A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has
been working on this project for 6 months, and the morale of the team is low due to the schedule.
What can the project manager do to motivate the team?
A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support
What approach should the project manager take?
Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly
requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes
of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?
An agile project manager is evaluating the method that will be used to display the
value of the work performed to date. Which method will they select to display to the project stakeholder?
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.
What should the project manager do next?
The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team
Which two actions should the project manager take? (Choose two)
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
A project manager who works for a company involved in several industries is asked
to lead a software development project for a government agency. The company attempted to
execute similar projects for other industries before but was unsuccessful.
What should the project manager do to ensure project success?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?
A project manager is developing a project baseline schedule and has started to
assign team members to the project activities according to their function. What should the
project manager do in this phase?
A project team is executing a project to replace an existing system with a new one.
A new project manager has been hired and observes that the team consist of professionals
who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
During the planning for a long project, the project manager recognized that several
members of the team are new to their roles. How should the project manager incorporate this
into planning?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
A developer who has almost completed a required product feature for a prototype
leaves the company in the middle of an iteration. What should the project manager do?
A complex, high-value agile project includes sprint demonstrations with the customer
every four weeks. Executive management is concerned about the project's progress and
wants more frequent updates on the project status.
What should the project manager do?
An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.
What should the agile leader do?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
In the middle of an iteration, the product owner tells the agile team that the
government has updated legal requirements. This will result in some changes in the product
definition.
How should the project manager handle this situation?
A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?
A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.
What should the project lead use for backlog refinement considering the sprints are 2 weeks long?
An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?
A project team delivered a critical deliverable to the customer. The customer
complained that the maintenance manual was not included.
What should the project manager do next?
A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
A project manager is leading the first agile project for the organization. During the
kick-off meeting, the project manager notices that the team does not have the same
understanding about agile approaches. The project manager is concerned about the impact of that confusion.
What should the project manager do to address this situation?
A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.
What should the project manager do?
A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team
What should the project manager do first to ensure the project is compliant?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?
A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?
A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation
What should the project manager do next?
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.
What should the project manager do next?
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?
A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities
What should the team do differently during planning for the next iteration"?
A project manager has recently joined a small company. The company's chief
operating officer (COO) asked the team to skip some steps in the process in order to work
more quickly. The project manager wants to ensure that these steps are not skipped in the
future.
What should the project manager do?
A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?
A project manager has noticed that a critical team member is consistently arguing
with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.
What should the project manager do next?
An organization is adopting an agile mindset. On the first agile project, the project
manager faced an issue because the team was unable to make decisions on time.
What should the project manager do to address the problem?
A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time
What kind of conflict resolution did the project manager apply in this situation?
A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
A project manager has experience working with a specific provider that has been
requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.
Why are the project managers having issues motivating the agile staff?
A project stakeholder has expressed concern that the established success criteria for
the project are not being met. What should the project manager do next?
A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?
A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.
What should the project lead do first?
A project manager submits several requests to purchase required hardware and
knows from previous experience that this kind of procurement usually results in disputes
between the company and its suppliers. How can the project manager mitigate this risk in the
request for proposal (RFP) with suppliers?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some
reserves needed
What should the project manager do to successfully complete the next phase?
A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget
What should the project manager update first?
A team member is openly criticized by others during a standup meeting for failing to
complete yesterday's tasks. What should the agile coach do first to address the situation?
A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?
A new project manager is managing a hybrid project. The project manager wants to be
a servant leader to support the team by removing impediments but is not receiving feedback
from the team about the issues and risks they are facing.
What should the project manager do?
A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided
details to the customer 2 weeks ago and set up a weekly conference call to effectively
communicate with them, but the customer has not been participating in the calls.
How should the project manager handle this situation?
A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client's security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client's team. The
project manager does not want to have such an external dependency.
What should the project manager do first?
A project manager has been assigned with initiating a large project to deliver
complex equipment. Part of the project will be the result of a long research process, but once
this is completed, the other part of the project must be incrementally delivered to the
customer.
Which approach should the project manager choose for this project?
During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.
What should the project manager do first?
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.
What should the project manager do?
A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?
A customer asks the project manager about opportunities to create business value.
What should the project manager do first in order to provide the customer with an appropriate
response?
In the planning phase, a project manager receives identified risks from the sponsors
and subject matter experts (SMEs) and wants to develop a risk response strategy for them.
What should the project manager do first?
A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person
What should the project manager do first?
During the project planning phase, a project manager called a meeting to discuss the
product backlog with multiple stakeholders who represent the end users in various capacities.
Only one executive manager attended the meeting.
What should the project manager do?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
A project manager is working on a large project in another country and realizes that
only a few people from the project team are working on all of the releases. What should the
project manager do to prevent this in the future?
A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.
What should the project manager have done to avoid this negative feedback'?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.
What should the project manager do to address this concern?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
An issue reoccurs six months after a project's go-live date despite being resolved
during the project life cycle. What should the project manager have done in the previous
phase to avoid this issue?
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?
A project manager is working on a project with multiple workstreams. One of the
workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen
again?
A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.
What should the project manager do?
A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype
What should the project manager do to accelerate this solution?
A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?
A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff
What should the project manager do first?
A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own
What should the project manager do?
An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information
should the project manager provide so that senior management can get a broader view of the project?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain
feedback from on project deliverables. What should the project manager do?
A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the
team member's emotional situation has affected the rest of the team's performance.
How should the project manager handle this situation?
A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical
complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?
A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.
Now that the project is back on track, what should the project manager do next?
A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion
What should the project manager do next?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist
from the team was average.
What should the project manager do to help the new compliance specialist improve?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.
What should the project manager do?
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a
result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.
What should the project manager do first?
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.
Who should the project manager contact to help the team accelerate the delivery?
A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as
something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall
progress.
What should the project manager do next?
A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager
discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The
remote team member feels they are not being adequately rewarded and recognized for their job.
What should the project manager do?
The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.
What should the project leader do?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.
Which statement is true?
A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of
the team. What should the project manager do?
A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the
team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?
A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change
requests issued due to the nature of the project.
What should the project manager do?
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.
What should the project manager do?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a
previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery
What should the project lead do?
A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.
What should the project manager do first?
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component
managed by an external vendor. How should the project manager address the team member's concern?
In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.
What should the project manager do?
A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has
identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.
What should the project manager do first?
A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big
of an expenditure for the company to undertake.
What should the project manager do in the future when working on new product projects?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.
What should the agile project manager do to engage the stakeholder in the project?
Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to
ensure the project is delivered successfully?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment
What should the project manager do?
A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?
A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.
What should the project manager do in this situation as a servant leader?
A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned
cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?
During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask
the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.
How should the project manager address this situation?
During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail
the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.
What should the project manager do next?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do
next?
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage interdependencies?
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.
The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.
How should the project manager handle communication?
A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.
What should the project manager do?
A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the Scrum Master and the Product Owner related to a feature requested by an important customer.
How should the project manager resolve this conflict?
A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.
What should the project manager do?
A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?
An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?
A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.
What should the project manager do?
A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.
What should the project manager propose?
A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?
A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter
What should the project manager do?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.
What should the project manager do first?
A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager
schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the
project?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?
A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment
What should the project manager do?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution
What should the project manager do?
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated requirements?
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead
handle this situation?
A project steering committee meeting was arranged to approve a milestone of a project within two weeks. The project manager is informed that a new project executive will take over the project.
What should the project manager do first?
Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.
What should the project manager do?
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager
What should the project manager do first in this situation'?
A company has transitioned and is now delivering projects using a hybrid approach
instead of a predictive approach. The distributed project team's knowledge of agile is varied.
The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.
What does the project lead need to do to prevent a risky situation in the next iterations?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.
What should the project manager do next?
A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.
Which risk management strategy has been adopted in this scenario?
A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on
the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing
Which three corrective actions should the project manager perform? (Choose three)
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the
project. How should the project manager resolve this?
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity
issues joining team calls during the day.
What should the project manager do?
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager
do to monitor compliance?
During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation
What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.
What should the project manager do given the urgency?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
A project manager is assigned to a strategic communication project that involves
subject matter experts (SMEs), interns, and new recruits. The project manager discovers
that the project is not gaining much traction due to knowledge gaps from the interns. The
budget for training is exhausted and the project needs to be delivered without delay.
Which two actions should the project manager take? (Choose two)
A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.
What should the project lead do?
A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?
A project manager was notified about a new regulatory requirement that could impact the project schedule.
What should the project manager do first?
One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings
How should the project manager handle this'?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
During the final iteration of the execution phase, the project has a cost performance
index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.
How should the project manager avoid a budget shortfall?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.
What should the project manager do?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.
What should the project manager do next?
During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.
What should the project manager do?
In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.
What should the project manager do next?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying
resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.
What should the project manager do first?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery
How should the project manager avoid this situation in the future?
A project manager was recently assigned to work on a hybrid project. After being a part of the project team for a couple of months, the project manager realizes that parts of this project depend on other organizational projects. These dependencies have not been identified.
What should the project manager do first?
Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.
What should the project manager do next?
A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.
What should the project leader do next?
A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?
A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.
How should the project manager respond?
A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).
Which two steps should the project lead take to define the MVP? (Choose 2)
A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.
What action should the project manager take?
A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.
Which two actions should the project manager take first? (Choose 2)
Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.
How should the project manager approach the situation?
A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.
What type of contract and project approach should the project manager consider?
A project manager is leading the development and delivery of a strategic product that must be delivered on time. The project is facing technical issues that could significantly impact the budget and ability to deliver some of the product features.
What should the project manager do first to resolve the issue?
The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).
What should the project manager do?
During the setup of an agile project, the product owner expressed clear interest in
having features released during product development over having the product completed in
one year. What should the project manager do?
A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.
What should the project manager do first?
The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.
What should the project manager have done first to avoid this situation?
During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?
A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?
A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?
A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.
Who should the project manager ask to update the process?
A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.
What should the project manager do first to resolve this issue?
A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.
What should the project manager do?
During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.
What should the project manager ask the team to do next?
A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.
What should the project manager do to address this concern?
A project manager is quantifying risk for their project. The project manager needs an expert opinion in this process, but experts are spread over different geographic locations and time zones.
What should the project manager do?
A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.
Which project management approach should the project manager advise using?
A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.
What should the project manager do first?
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?
A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.
What should the project manager do?
In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.
What should the project manager do?
During a risk review meeting early in a project, the project team flags the possibility that a key team member might be away during the implementation of a key work package. Unfortunately, this team member is currently the only resource with the knowledge to perform this work, although it is possible someone else could do it with training.
What should the project manager do?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?
During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
What should the project manager do first to get the team energized and performing efficiently?
A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.
What should the project manager do?
The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.
Which three actions should the project manager take? (Choose three)
A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.
What should the project manager do?
A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.
What should the project manager do first?
A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
Which first two actions should the project manager perform? (Choose 2)
A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.
What should the project manager do first to ensure each stakeholder has the information they need?
The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.
What three actions should the project manager do? (Choose 3)
A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.
What should the project lead do?
A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.
What action should the project manager take?
A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.
What should the project lead do?
While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.
What should the scrum master do?
A project team used agile approaches to create a minimum viable product (MVP). Currently, the team is discussing the possible next steps.
What should be the next step?
A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.
Which landscape describes the project environment?
An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.
What should the project manager take into account first when building the schedule for this new project?
A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?
A key stakeholder of a project wants to include additional work before completion.
What should the project manager do?
A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.
What should the project manager suggest?
A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.
What should the project lead do?
A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?
A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.
What should the project manager do?
A project manager is new to an organization that typically follows a hybrid approach but is shifting to incorporate more agile. A dedicated project team has been provisionally assigned. The new project manager needs to review the internal environment in order to build a high-performing team.
To build a high-performing team, which three factors should the project manager evaluate? (Choose 3)
A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.
What should the project manager do next?
The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.
What should the project manager do in this situation?
During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
What should the project manager do first?
During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.
What should the project manager do first?
A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.
How should the project manager proceed in order to complete the risk register?
During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?
A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.
What should the project manager do to help ensure a successful outcome for the project?
A company has hired a vendor to deliver a scope of work and assigned a project
manager to oversee the project. The vendor advised that they completed the scope
successfully and is asking for approval.
What should the project manager do in response to this request?
During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.
What should the project manager do first?
An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A product owner has an idea for a new product but is struggling to define the
features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?
A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?
A project manager is working on a large project with a very difficult client. During
the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.
How should the project manager approach this?
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
A project manager is meeting with the project sponsor regarding a new project.
The project manager tells the sponsor that, as part of the communications management
plan, a weekly email will be sent with the status of the project, so the sponsor can be
informed of the progress. The sponsor indicates that the email is not necessary because
they will ask for a status update whenever it is needed.
What should the project manager do next?
During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.
What should the project manager do?
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,
What should the project manager do?
A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.
What should the project manager do to manage this conflict?
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.
What should the project manager do?
A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
Match the project situation on the left to the meeting on the right where the situation could occur.
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?
A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.
How should the project manager address these objectives?
A project manager is using a hybrid approach for project delivery. The
development team was sized, but is not yet fully resourced. The project manager is working
on defining the project schedule.
What should the project manager do to address the issue of developer availability?
A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.
What should the project manager have done to avoid this situation?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.
What else does the project manager need to do before determining the budget baseline?
As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.
What should the project manager do?
A project manager has been asked to participate in the procurement process for a
software application that allows customers to buy online e-learning courses. The project
manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.
The customer is asking the project manager for guidance.
What should the project manager do?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.
What should the project manager do?
At the end of the last iteration, the customer rejects the deliverables since they did
not meet the customer's expectations. What should the project manager have been done
to prevent this situation?
According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
A project manager is assigned to oversee the deployment of a new product that
will be used by the entire organization. A key success factor for the project is the timely
and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?
A labor union contract negotiation is delaying the completion of a project to build
a new manufacturing plant. Because the labor contract was due for renewal this year, the
project manager documented the negotiation process as a risk to the project. The project
was about to start the first phase of equipment installation at the plant when the negotiation began.
How should the project manager address the situation?
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.
Who is responsible for analyzing the new requirement and making the final decision?
At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.
How should the project manager proceed?
A senior management team member contacts an agile project lead and mentions
that certain features the senior manager thought would be in the current release were not
included. What should the agile project lead do?
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year
Which project approach suits the scenario?
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team
requests a change in the sprint goals and sprint backlog items.
What should the project manager do?
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.
Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.
What should the project manager have done?
A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.
What should the project manager do?
The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?
A project needs to purchase a specific piece of equipment, as stated in the
project documents and approved by the project sponsor. The procurement division is
questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?
An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.
What should the project manager of the ongoing project do?
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.
What should the project manager do to handle this situation?
An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?
A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project
How should the project manager proceed?
During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?
The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
On a transformational project, the project manager is confronted with resistance
from the stakeholders. To overcome this and gain acceptance of the change, what should
the project manager do first?
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.
What should the project manager do first?
A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix
What should the project manager do to improve the stakeholder relationship?
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.
Which statement is true''
A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.
What should the project manager do to address the growing resistance?
local company is developing a new product and. for the first time, using a remote
team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's
outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
A project started 12 months ago and is currently on iteration 12 of 14. The team
has performed well and completed all deliverables on time. However, some team members
are starting to complain about the length of the project, creating a risk for lack of
performance at this critical stage.
What should the project manager do as a servant leader to mitigate this risk?
An organization in a regulated industry has decided to switch from a predictive to
an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,
and the project manager is still accountable for the project outcomes. During the fourth sprint
demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
A product owner has provided the team with a prioritized backlog for the initial
launch of a new product. After analysis, the team concludes that some work is missing to
support the initial launch and provides this information to the product owner. The product
owner acknowledges the missing work and adds it to the bottom of the backlog. The team is
not happy with the prioritization that the missing work received.
What should the project manager do in this situation?
A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders
What should the project manager do first?
A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget
Which two actions should the project manager take initially to resolve this problem? (Choose two)
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams
What should the project manager do?
A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork
What should the project manager do to improve morale?
A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget
What should the project manager do next?
A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.
Drag each stakeholder scenario on the left to the correct engagement level on the right.
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?
A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities
How should the stakeholder be engaged in the project?
An agile project team is looking to develop quality standards for a project How should the project manager coach the team?
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
Drag the communication event on the left to the mam subject discussed during the event on the right.
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project
After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right
Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?
A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected
What should the project manager do going forward?
For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available
Why is an attendance list important?
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project
What should the project manager do first?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate
What interpersonal skill did the project manager use?
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change
What should the scrum master do?
The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible
What should the project manager use to identify the risks?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations
What should the project manager do?
The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action
What two actions should the project manager take'? (Choose two)
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using
What should the project manager have done to avoid this issue?
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team's request"?
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.
What should the project manager do?
After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?
A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped
What should the project manager do?
The project schedule is falling behind and the project manager observes that the project team seems to be spending the majority of their time writing documentation instead of performing project tasks What should the project manager do to help ensure that the team focuses on project tasks?
One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended
What should the project manager do next?
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?
Which two actions should a project manager consider while launching a new virtual team? (Choose two)
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again
What should the project lead do next?
After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features
What should the project manager do to avoid this in the future?
A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.
What should the project manager do first to prevent the project from going further off track?
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.
What should the project manager do first?
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.
What two actions can the project manager take to be more cost effective? (Choose two)
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?
A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible
What approach should be used in this situation?
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements
How should the project manager address this situation?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing
What should the project manager review?
An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.
What should the project manager do first to ensure team adherence to the ground rules?
During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects
What should the project manager do?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.
What should the project manager do next?
A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time
How should the project manager address this situation?
During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?
A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?
During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email
What should the project manager do?