How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?
A project charter has been completed and is ready for approval. The project's goal and approach have been clearly determined and a list of generalized specialists has been set.
How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?
An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.
What should the agile practitioner do in this situation?
An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?
Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.
What should the scrum master do to handle this situation?
A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.
What should the team lead do to improve decision quality and reduce the time required to make decisions?
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.
How should this situation have been prevented?
When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?
A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.
What should the Scrum Master do to accomplish this?
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace.
What analysis should the team use to understand the issues?
An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this?
During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.
What should the agile practitioner have done to avoid the situation?
An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.
What should the agile practitioner do?
Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?
A team retrospective was going well until the team lead introduced the "define the next experiment" topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team's efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.
A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
An agile team is working on the first sprint, and has already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?
A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.
How should the scrum master help the team to resolve the issue?
During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)
During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.
What should the agile practitioner do?
Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.
How should the project manager explain why this is not the forum to ask these questions?
A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.
How should the team address this issue?
The product owner is very concerned about work not being completed and tested before a hard release date.
What can the agile team do to mitigate this risk?
A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.
What should the product owner have the customer review and approve?
A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?
An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?
During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.
What is an effective way to handle conflicting opinions in team meetings in an agile environment?
During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.
What is an effective way to handle conflicting opinions in team meetings in an agile environment?
In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.
How should the project manager approach this project?
A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?
The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?
During its first sprint, a new Scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories.
What should the team do?
A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.
What should the Agile Project Manager advise?
A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the first meeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.
What should the project manager do next?
An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.
What should the team do next?
One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.
How should the product owner respond?
A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.
Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?
An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?
During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation.
What should the agile practitioner do?
Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value.
What should the project manager do?
An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.
What should the agile team lead do at the end of this iteration?
A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.
Which action did the project manager most likely take when choosing the approach?
A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?
An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.
Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?
During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk.
What should the team do next?
What should the project manager do to share this project's knowledge and learning with wider organizational business groups?
A product owner needs to elaborate on a product roadmap. How can the product owner collaborate with stakeholders to identify the features that offer maximum value?
A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?
After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.
If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?
A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.
To address this issue and bring the project back on track, what action should the team take?
A project's Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.
What technique did the team use?
The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.
What should an agile practitioner do?
During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.
What can the team do to better manage this situation?
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?
On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?
Due to its complexity, a new team member struggles with developing a concise user story.
What advice should the agile practitioner give to assist with developing the story?
Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.
What should the product owner do to help the team?
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.
What should the Scrum Master do?
A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?
A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.
What should the project manager do to make sure team members are following up on risks?
A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.
How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
A project team is working with an enterprise agile center of excellence (CoE) to transition to a Scaled Agile Framework (SAFe). Many of the team members are not familiar with the new methodology and are worried that it will lead to more work and scrutiny.
What should the agile team lead do to help ensure a smooth transition?
A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.
What should the project lead do to help the team?
Why should an agile coach model agile principles and behaviors, become self-aware, and be present?
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?
During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.
What is the agile project manager trying to show?
In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.
What are some of the practices a project manager can bring to an adaptive environment?
A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.
What should the scrum master do?
During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.
How should the agile practitioner handle the recommendation?
Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?
Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.
What should the Scrum Master do in this situation?
DRAG DROP
All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?
An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.
How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?
Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.
What should the project manager do?
During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.
What should the agile project leader have done to avoid this situation?
A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.
Which two actions should the product owner take? (Choose two.)
A technical problem arises that will likely impact the stories planned for delivery in the current sprint.
What should the Scrum Master do?
As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met.
How should the project management plan be adjusted?
An agile team is preparing a release plan for a project. What information will the team need to complete this plan?
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
How many sprints will be needed to complete the entire backlog?
The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.
How can the team improve their collaboration?
A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?
The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?
Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.
What should the Scrum Master do next?
A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?
During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.
How should the scrum master respond?
After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.
What should the agile practitioner do?
Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.
What should the agile practitioner do?
What should the agile practitioner have done to ensure stakeholder satisfaction?
A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.
What is the estimated time remaining for the project?
What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?
A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.
Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?
During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.
What should the scrum master do now?
An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.
What should the scrum master do first?
A Product Owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog.
What should the Product Owner do next?
New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.
How should the stakeholders ensure their objectives are met by product delivery?
An agile team is optimizing the workflow by investing in initiatives to identify and reduce unnecessary handovers and delays. What should the team do in this situation?
A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.
What should the team lead do next?
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?
An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.
What should the team member do?
During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?
A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.
What strategy should be used to deliver it successfully?
A team is preparing to demonstrate new product capabilities to a leadership team. The demonstration will show working software and a listing of the projected value of the capabilities.
What should the team do to ensure the demonstration is successful?
The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.
What should the team do next?
A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.
What should the servant leader do?