Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Questions 4

What should the team have done to improve retrospective outcomes?

Options:

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log and then reviewed their progress at the end of every iteration

Buy Now
Questions 5

During a project ' s last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

Options:

A.

Inform the product owner ' s manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Buy Now
Questions 6

During team meetings, the team often struggles with making decisions about their technical approach.

What should be done to improve the quality and timeliness of decisions?

Options:

A.

Work with the team to improve collaboration by fostering group decision-making and conflict resolution techniques.

B.

Promote team discussion but give the Product Owner the ultimate decision-making authority.

C.

Assign individual team members as decision owners for each key decision to avoid conflict.

D.

Identify team members that demonstrate servant leadership qualities to facilitate discussion and make decisions.

Buy Now
Questions 7

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative ' s current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Options:

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

Buy Now
Questions 8

What practice is the agile facilitator implementing?

Options:

A.

Building openness and transparency on the project ' s health and status

B.

Facilitating conflict resolution among executive team members

C.

Using active stakeholder involvement to build features in an incremental and iterative approach

D.

Seeking continuous feedback from executive team members

Buy Now
Questions 9

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

Options:

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

Buy Now
Questions 10

A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.

How should the project manager proceed?

Options:

A.

Consult with the product owner to prioritize the new work at a higher level.

B.

Consult with the project sponsor and project team to resolve the issue.

C.

Consult with the project team to rework the existing estimates.

D.

Consult with the product owner and project team.

Buy Now
Questions 11

What should the agile practitioner have done to ensure stakeholder satisfaction?

Options:

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Buy Now
Questions 12

While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the Scrum team do?

Options:

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members

Buy Now
Questions 13

What should the agile coach do?

Options:

A.

Start the hiring process for a new, equally skilled database administrator as a replacement.

B.

Move this database administrator to another team so that team members learn database-related tasks.

C.

Add another database administrator to balance the workload and aid with knowledge retention.

D.

Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.

Buy Now
Questions 14

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

Options:

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.

B.

Ask the product owner to review their items with the product owner ' s teammates before adding user stories to the backlog.

C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.

D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.

Buy Now
Questions 15

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder ' s supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Buy Now
Questions 16

An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours, which affects team performance.

What should the agile coach do to mitigate this issue?

Options:

A.

Speak with the functional managers and come to an agreement that will resolve the issue

B.

Explain to functional managers that too much control will inversely impact team morale

C.

Meet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue

D.

Inform the team there will be penalties to anyone who visits that business during working hours

Buy Now
Questions 17

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?

Options:

A.

Terminate the project to cut losses

B.

Review possible options and make an informed decision to cut losses based on delivered business value

C.

Bring in experts to increase the probability of success

D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release

Buy Now
Questions 18

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.

What strategy should be employed to re-organize the teams?

Options:

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies

C.

After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role

D.

Features should be prioritized and then teams should be organized around those priorities

Buy Now
Questions 19

An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team ' s ability to produce results. The team insists on implementing these tasks since they will increase efficiency.

What should the agile coach do?

Options:

A.

Characterize chores as low priority since they do not add obvious value to the product

B.

Delegate chore-related tasks to another team.

C.

Escalate the issue to the shareholders/steering committee.

D.

Get the product owner and team to meet to prioritize the work.

Buy Now
Questions 20

What do the principles of Extreme Programming (XP) include?

Options:

A.

Communication, respect, and courage

B.

Communication, process flow, and authoritarian structure

C.

Value people over processes, communication, respect disagreement, and strive for consensus

D.

Rapid feedback, assume simplicity, incremental change, embrace change, and quality work

Buy Now
Questions 21

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Buy Now
Questions 22

A Scrum team has worked hard to reach their sprint goal, but impediments have prevented them from succeeding. The team needed help from a specialist on another team, but the specialist was on a 2-week vacation.

What should the scrum master do?

Options:

A.

At the sprint retrospective, the scrum master and development team should discuss why the team did not know the specialist was unavailable during the sprint. The scrum master should then set clear rules so situations like these can be avoided in the future.

B.

It can be very distressing for a Scrum team not to reach its sprint goals. The scrum master should hold an evaluation meeting to discuss who in the team was responsible for discovering the specialist was not available, then make an improvement task for the next sprint.

C.

The scrum master, as a servant leader, should always try to remain positive about the team ' s work. Even when team members’ make mistakes, there should be trust that everyone is doing their best. Engaged team members work more efficiently, and a sustainable pace is important for project success.

D.

At the sprint retrospective, the Scrum team should reflect on how the past sprint has worked out. The scrum master should facilitate an open discussion to discover the root causes for the missed sprint goals and find a way to avoid similar situations in future sprints.

Buy Now
Questions 23

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Buy Now
Questions 24

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the Scrum Master do?

Options:

A.

Report the issue to the product owner and request help.

B.

Let the new release manager participate in the daily standup.

C.

Invite the new release manager to the sprint demo and ask for help.

D.

Send a status report to the release manager highlighting the issue.

Buy Now
Questions 25

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Buy Now
Questions 26

What should the Scrum Master do?

Options:

A.

Ask the product owner how upper management ' s comments can be redirected.

B.

Direct the developer team to ignore the phone calls and emails.

C.

Ask the product owner to enter the requests into the product backlog as high priority.

D.

Personally respond to upper management ' s phone calls and emails.

Buy Now
Questions 27

A member of a project ' s development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training

B.

Ask the outside specialists if database administration is required from the team

C.

Send one member to training only after asking the team if there is an issue with the current workflow

D.

Wait until all members of the team can attend training

Buy Now
Questions 28

Options:

A.

Document the problem, escalate to the project manager, and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Buy Now
Questions 29

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

Options:

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Buy Now
Questions 30

One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.

How should the product owner respond?

Options:

A.

Stakeholders have the opportunity to add features to the sprint.

B.

Team members determine if there are any impediments preventing them from meeting the sprint goal.

C.

The product owner explains which product backlog items have been done and which have not.

D.

Team members identify ways to improve and make plans to implement these improvements.

Buy Now
Questions 31

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.

How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project

B.

Write backlog items that include QA as part of the description

C.

Ask for the current QA documents and incorporate them into the technical debt backlog

D.

Ask the product owner to write tests and QA controls into the acceptance criteria

Buy Now
Questions 32

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration ' s remaining scope?

Options:

A.

Convince the team to stop planning and keep the size small

B.

Identify the technically minimal and achievable tasks

C.

Refer to the remaining prioritized backlog items

D.

Select some of the smallest items from the backlog

Buy Now
Questions 33

Options:

A.

Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.

B.

Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.

C.

Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.

D.

Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.

Buy Now
Questions 34

A global subscription-based service is pursuing enterprise agility across digital product development teams. Product teams release updates frequently, but customer usage data and support trends are reviewed only at the end of each quarter. As a result, several low-adoption features continue to receive investment while customer churn gradually increases. Leadership wants the product teams to respond more quickly to changing customer behavior.

What should the agile practitioner recommend?

Options:

A.

Schedule monthly executive reviews to assess customer usage and feedback to support investment decisions.

B.

Integrate customer usage analytics into feature prioritization processes to adjust investment decisions.

C.

Delegate feature prioritization decisions to regional business managers based on customer usage analytics.

D.

Increase the number of features delivered each quarter to drive customer usage and improve overall satisfaction.

Buy Now
Questions 35

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Buy Now
Questions 36

What should the Scrum Master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story ' s technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story ' s priority and wait until more technical details are available.

Buy Now
Questions 37

A scrum master wants to encourage better collaboration within a collocated team and is coming up with a visualization method for the project. How could the scrum master promote transparency?

Options:

A.

Consolidate the team ' s updates in presentation slides and email them to the team regularly.

B.

Radiate key information such as the team ' s work, progress, and velocity at the team ' s common area.

C.

Share team progress individually with each top performer every week.

D.

Attach sticky notes for each assignment to the wall in the team ' s area.

Buy Now
Questions 38

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

Options:

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Buy Now
Questions 39

Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with that work

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Buy Now
Questions 40

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

Options:

A.

Request direction from the technical manager

B.

Encourage the Product Owner to reallocate the features to another sprint

C.

Determine who is best qualified to address the challenges

D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources

Buy Now
Questions 41

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

Options:

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Buy Now
Questions 42

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during meetings. What should the project lead do to encourage the team members to express themselves?

Options:

A.

Emphasize rules that need to be respected during meetings.

B.

Allow team members to talk when they feel comfortable without any pressure.

C.

Organize separate meetings with each individual team member.

D.

Create a safe environment for discussions during meetings.

Buy Now
Questions 43

One of the overseas stakeholders on an agile project has not been actively involved in the project ' s development. What would be the first step to reengage the stakeholder?

Options:

A.

Increase the frequency of emails and/or try to call the stakeholder.

B.

Remind the stakeholder of their obligation to engage in the project.

C.

Talk to the stakeholder ' s superior so they can offer coaching and guidance on project involvement.

D.

Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

Buy Now
Questions 44

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?

Options:

A.

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.

B.

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.

C.

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.

D.

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.

Buy Now
Questions 45

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Buy Now
Questions 46

A scrum master is part of a team that has just agreed on the project scope and deliverables for a global, multilingual manufacturing company that has many staff members moving between locations. The team consists of 20 people and the budget is US$5 million. The kickoff meeting is scheduled for the following month.

What should the scrum master do as a first step?

Options:

A.

Organize a sprint planning meeting and include stakeholders.

B.

Invite the product owner to create a stakeholder map.

C.

Identify the key stakeholders at the earliest opportunity.

D.

Invite the key stakeholders to the kickoff meeting.

Buy Now
Questions 47

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.

Influence the customer

B.

Mention the idea at the next retrospective

C.

Show the customer how much time and money would be saved

D.

Present the idea at the next ceremony attended by stakeholders to obtain their input

Buy Now
Questions 48

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories ' tasks.

D.

Help establish the next sprint ' s goal.

Buy Now
Questions 49

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master ' s estimation

B.

Identify a set of user stories based on the team ' s velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Buy Now
Questions 50

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Questions 51

What should the product owner do?

Options:

A.

Determine the required tasks for implementing the high-level features

B.

Identify the detailed design for the high-level features

C.

Prioritize the product backlog for the upcoming release

D.

Estimate the user stories in the iteration backlog

Buy Now
Questions 52

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

Options:

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Buy Now
Questions 53

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team ' s historical velocity to calculate a range of features that can be delivered

Buy Now
Questions 54

What should the Scrum Master do first?

Options:

A.

Work with the customers to build the product backlog and identify their initial requirements.

B.

Meet with the stakeholders and enterprise architects to understand the project ' s vision.

C.

Plan and execute a sprint 0 to establish the project ' s foundational needs.

D.

Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.

Buy Now
Questions 55

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Buy Now
Questions 56

What should the agile practitioner do?

Options:

A.

Commend the team on trying the idea, then encourage discussion regarding alternatives

B.

Ask a manager to direct the team on fixing the process

C.

Encourage the team to continue executing the idea to see if it improves

D.

Privately speak with the team member to convey that their idea worsened the outcome

Buy Now
Questions 57

A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.

To address this issue and bring the project back on track, what action should the team take?

Options:

A.

Perform value stream analysis to eliminate the processes with wastage.

B.

Reevaluate the minimum viable product (MVP) deliverables to remove high-risk stories and meet timelines.

C.

Adjust the story points included in each sprint to represent the actual velocity.

D.

Include high-risk stories in earlier sprints to deliver incremental velocity.

Buy Now
Questions 58

Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?

Options:

A.

Organize onsite backlog-refinement workshops to ensure common understanding.

B.

Set up weekly meetings where all team members will participate.

C.

Call an onsite meeting where ground rules will be discussed and agreed upon.

D.

Ask the product owner to prepare an onsite team-building activity.

Buy Now
Questions 59

What should the agile practitioner do next?

Options:

A.

Identify a team member to do a proof of concept using this framework.

B.

Email the team directing them to immediately begin using this new framework.

C.

Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.

D.

Discuss this option at the next retrospective.

Buy Now
Questions 60

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Buy Now
Questions 61

A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?

Options:

A.

The purpose of the daily coordination meeting is for the scrum master to be able to follow up on the sprint plan. The team should explain what may be impeding them from reaching the sprint goal.

B.

According to the Scrum guide, the daily coordination meeting is part of the Scrum framework. The purposes of this meeting are to enable the scrum master to verify the team is on track and to escalate impediments.

C.

The daily coordination meeting is an effective way for the development team to follow up on progress toward the sprint goal and discuss anything that may hinder their work. It is a way to actively manage risks and dependencies.

D.

The daily coordination meeting is held to verify that people are working on the right things. The whole Scrum team should be able to answer these questions: What did I do yesterday, what will I do today, and what can stop me from making progress?

Buy Now
Questions 62

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Buy Now
Questions 63

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?

Options:

A.

Project velocity should be stable overtime.

B.

Moving velocity from 27 to 35 is a decrease in productivity.

C.

A burndown chart compares planned versus actual, not velocity.

D.

Velocity is iterative and will only be used for sprint numbers.

Buy Now
Questions 64

What should the agile team lead do?

Options:

A.

Create a new team to deliver the dependencies, and bring team B under performance management.

B.

Conduct a vision-sharing session with the teams to communicate the project ' s overall goals.

C.

Swap team members from both teams so that deliveries are better supported.

D.

Discuss negotiating the delivery timelines with team A.

Buy Now
Questions 65

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

Options:

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

Buy Now
Questions 66

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Buy Now
Questions 67

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Buy Now
Questions 68

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Buy Now
Questions 69

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.

What should the Scrum Master do?

Options:

A.

Explain to the SME the importance of being a team player, that the tasks are assigned by the Scrum Master, and work should not be refused.

B.

Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist.

C.

Leverage a separate testing team altogether to assist with all testing to ensure consistent results.

D.

Explain to the team the importance of reducing team size by reducing specializations and bottlenecks and that every team member plays an equal part.

Buy Now
Questions 70

In companies where decision-making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?

Options:

A.

A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value.

B.

Agile is focused only on digital transformation project management, whereas a predictive approach focuses on traditional " brick and mortar " projects.

C.

The agile formal change management system is better able to deal with unknown variables.

D.

Agile is relatively new; therefore, it is inherently more aligned with data-analytic-based efforts.

Buy Now
Questions 71

An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members ' personalities and motivators?

Options:

A.

Use the DISC framework with each team member.

B.

Use MoSCoW ratings to keep people engaged.

C.

Hire a SAFe coach to provide encouragement.

D.

Employ BDUF to help with providing structure to meetings.

Buy Now
Questions 72

A stakeholder complains about the amount of changes that are being introduced to a project. What should the product owner do?

Options:

A.

Escalate the complaint to the scrum master

B.

Suggest implementing a more rigorous change governance

C.

Coach the stakeholder on agile principles

D.

Agree to limit scope changes going forward to control costs

Buy Now
Questions 73

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

Options:

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.

B.

Estimate in story points and pull in new work per the team ' s capacity

C.

Add limits to all columns and only pull work in when the queue is not full.

D.

Create a cumulative flow diagram and start looking for bottlenecks.

Buy Now
Questions 74

Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?

Options:

A.

Understand the physical and virtual communication needs of the team and plan agile events based on the majority of the team members ' needs.

B.

Escalate with senior management and ensure that everyone on the project team is physically colocated for all planned agile events.

C.

Invest in technology-collaboration tools to enable effective communication and ensure a common understanding of the scope, issues, and solutions.

D.

Recognize the different communication styles of the stakeholders and take a vote on the best approach that will work for the team.

Buy Now
Questions 75

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

How many sprints will be needed to complete the entire backlog?

Options:

A.

15

B.

16

C.

17

D.

18

Buy Now
Questions 76

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and Product Owner decide and reprioritize based on value

C.

Recommend canceling the current iteration and plan the change request into the next iteration

D.

Recommend that the Product Owner add this change request as a user story to the backlog for the current iteration

Buy Now
Questions 77

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

Options:

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Buy Now
Questions 78

A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.

How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?

Options:

A.

The team needs to see the product owner ' s body language and facial expressions to understand what they really want.

B.

An in-person meeting helps ensure the product owner will consider their feedback carefully and not ask for any unneeded rework.

C.

It typically takes more time and resources to set up and test a virtual communications tool than to meet in person.

D.

The team will be able to better address the product owner ' s needs if they can have a conversation and ask questions.

Buy Now
Questions 79

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: " I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles. "

What is the agile lead attempting to highlight?

Options:

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Buy Now
Questions 80

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

Options:

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

Buy Now
Questions 81

A newly formed Scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?

Options:

A.

Kaizen

B.

Specific, measurable, assignable, realistic, and time-based (SMART) goals

C.

Key performance indicators (KPIs)

D.

Muda

Buy Now
Questions 82

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.

What should the team do?

Options:

A.

Conduct frequent demos and obtain feedback from users throughout the development of the next release

B.

Inform senior management that since the product was successfully released, the project is considered delivered and should be closed

C.

Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity

D.

Implement a better definition of done to ensure that continuous integration processes are managed effectively

Buy Now
Questions 83

What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Buy Now
Questions 84

A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.

How should the product owner address this situation?

Options:

A.

Improve the product testing and quality assurance skills among the team

B.

Facilitate more product planning sessions with the software team.

C.

Consider moving to a more predictive product development approach.

D.

Develop a prototype of the product to obtain feedback from users.

Buy Now
Questions 85

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

Options:

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.

B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.

C.

Delegate the decision for the best feature implementation to the most senior team member.

D.

Decide on the technical implementation that best fits the purpose of the technical design.

Buy Now
Questions 86

What should the agile practitioner do?

Options:

A.

Work with the agile team and product owner to agree on the definition of done

B.

Ask the project sponsor to determine whether the product is completed

C.

Plan another review after the product has been tested

D.

Add testing to the backlog, and have the product owner reprioritize

Buy Now
Questions 87

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team ' s agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Buy Now
Questions 88

During planning sessions, an agile practitioner notices that some team members do not share common ideas.

What should the agile practitioner do?

Options:

A.

Ask the team if they would like to adopt alternative techniques

B.

Create a team norms document to set participation guidelines

C.

Ask the Scrum Master to resolve the issue at the stand-up meeting

D.

Capture feedback during lessons learned at the end of the iteration

Buy Now
Questions 89

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Options:

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project ' s status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team ' s decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project ' s status.

Buy Now
Questions 90

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

Options:

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Buy Now
Questions 91

Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?

Options:

A.

Note the changes to the restructure and roles that affect team activities

B.

Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements.

C.

Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project

D.

Obtain a copy of the redefined key roles to update the stakeholder analysis

Buy Now
Questions 92

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Buy Now
Questions 93

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Buy Now
Questions 94

A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges.

How should the team plan improvements to their product?

Options:

A.

Follow the project schedule created at the start of the project.

B.

Hold regular retrospectives and have team members commit to specific actions.

C.

Allow team members to choose improvement items and trust their judgment.

D.

Encourage team members to write code that is tightly coupled together.

Buy Now
Questions 95

What should the agile practitioner do?

Options:

A.

Complete the test cases before creating the story in the backlog

B.

Define the detailed business requirements so that the team can continue with development

C.

Define the user stories with just enough detail so the team can collaborate continuously

D.

Ensure the acceptance criteria includes testing scenarios, so the team can do thorough testing

Buy Now
Questions 96

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Buy Now
Questions 97

What agile tools can help the team address these issues?

Options:

A.

Information radiators and wireframes

B.

Information radiators and story maps

C.

Process flows and personas

D.

Personas and extreme characters

Buy Now
Questions 98

What should the Scrum Master do?

Options:

A.

Engage the team to determine the sprint velocity based on previous agile projects.

B.

Average the sprint velocity based on input from team members

C.

Share the sprint velocity obtained from the sponsor with the team

D.

Run multiple sprints before determining the sprint velocity with the team

Buy Now
Questions 99

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?

Options:

A.

New tools that deliver iterative and incremental work

B.

A more predictable delivery schedule and better quality

C.

Higher levels of activity-based planning and user histories

D.

Increased focus on the value and benefits delivered

Buy Now
Questions 100

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

Options:

A.

Included the stakeholders in the project planning meeting

B.

Organized an earlier demo to solicit business feedback

C.

Ensured all business leaders signed off on requirements

D.

Engaged key stakeholders periodically to collect requirements

Buy Now
Questions 101

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?

Options:

A.

Estimate and define the work items.

B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.

C.

Add features to the product backlog.

D.

Determine if the demand is or is not feasible.

Buy Now
Questions 102

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

Options:

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Buy Now
Questions 103

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

Options:

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project ' s success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Buy Now
Questions 104

A new agile team member notices that the team ' s current process involves excessive documentation. What should the new team member do?

Options:

A.

Teach the team the appropriate agile principle, obtain consensus, and drive adoption.

B.

Allow another team member to prepare those documents that do not appear to bring value.

C.

Notify the project manager about other documentation techniques, and identify which documents bring value and which do not.

D.

Follow the existing process to avoid conflicts.

Buy Now
Questions 105

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

Options:

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Buy Now
Questions 106

How can this issue be resolved?

Options:

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features to include only the vitally important one.

D.

Extend the iteration to complete the feature.

Buy Now
Questions 107

Unable to meet a sprint ' s committed velocity, an agile team approaches the agile coach to define the next sprint ' s velocity. What should the agile coach advise?

Options:

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

Buy Now
Questions 108

The coach on a new agile team notices that one team member is influencing most of the team ' s decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team ' s velocity drops.

Buy Now
Questions 109

While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.

Why is the project sponsor making this suggestion?

Options:

A.

The information gathered will help the team improve the allocation of resources in developing the most important features.

B.

The project sponsor believes that the agile team is not adding in the most important features during this sprint.

C.

The users can help the team understand if the feature adds value, avoiding the risk of building the wrong product.

D.

The users will start using the software sooner, and the team can start working on the next iteration.

Buy Now
Questions 110

An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.

What should the agile project manager do to promote trust and collaboration?

Options:

A.

Talk with the human resources (HR) department to select team members with similar backgrounds to eliminate conflict

B.

Collocate for team building to promote collaboration to build trust and improve communication.

C.

Promote a project charter with the project vision and purpose to help align the team.

D.

Promote a team charter with a set of norms rules and agreements to facilitate the work

Buy Now
Questions 111

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

Options:

A.

Requested approval from the project sponsor

B.

Undertaken a review of all requirements

C.

Conducted an end-of-phase demonstration

D.

Performed a retrospective to validate project deliverables

Buy Now
Questions 112

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

Options:

A.

Allow stakeholders to discuss without the scrum master ' s intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Buy Now
Questions 113

An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

Options:

A.

Cover up the Kanban board every time the project team is not actively updating it.

B.

Demonstrate how the Kanban board is necessary for assigning proper ownership for the work that has been done.

C.

Explain that the Kanban board enables the team to complete the work and increases transparency on work that is not done.

D.

Remove the Kanban board immediately and place it in a location where it is not visible.

Buy Now
Questions 114

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

Buy Now
Questions 115

In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.

How should the project manager approach this project?

Options:

A.

Define all requirements so value can be added by delivering a high-level plan at the initiation phase.

B.

Suggest the Product Owner prioritize the work items by feature to maximize value.

C.

Ask the customer to define the requirements of all stakeholders and select the most valuable features.

D.

Ensure the client has a clear idea about the features and end product before the project starts.

Buy Now
Questions 116

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Buy Now
Questions 117

During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can, and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Buy Now
Questions 118

Options:

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened

Buy Now
Questions 119

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Buy Now
Questions 120

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

" Inspect and adapt " are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member ' s opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Buy Now
Questions 121

What should the agile team lead do?

Options:

A.

Create a central repository for information, and provide access to Team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide Team B with the information on an " as needed " basis

Buy Now
Questions 122

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.

What is the agile project leader doing?

Options:

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Buy Now
Questions 123

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

Options:

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Buy Now
Questions 124

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team ' s time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Buy Now
Questions 125

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.

Value stream mapping

B.

Long-term Lean planning

C.

Business process modeling

D.

Planning poker

Buy Now
Questions 126

An agile team wants to collectively determine a project ' s size. What will the team be doing if they use the planning poker technique to accomplish this?

Options:

A.

Estimating story points by comparing them to similar, past features

B.

Estimating stories by placing them in buckets

C.

Using the number of dots for votes to estimate story points

D.

Estimating the relative size of stories by using story points

Buy Now
Questions 127

How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Buy Now
Questions 128

In a Scrum team, who should be responsible for the budget and release plans?

Options:

A.

The Scrum Master assigns someone on the team to handle the budget, and the Product Owner is responsible for release plans

B.

The finance department is responsible for the budget, and the Product Owner is responsible for release plans

C.

The Scrum team as a whole, as they are self-organizing and share accountability

D.

The Product Owner is responsible for both the budget and the release plans

Buy Now
Questions 129

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Buy Now
Questions 130

An organization wants to increase value delivery in its agile projects.

What should the agile teams do?

Options:

A.

Perform analysis and development work, but no testing because that should be managed by another specialized team.

B.

Master available technology and tools to provide informative dashboards to the stakeholders.

C.

Work with product owners and turn product backlog items into potentially shippable product increments.

D.

Complete projects by their deadlines and share the budgets upfront with project sponsors.

Buy Now
Questions 131

During a project ' s last iteration, an agile team struggled with a feature ' s delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature ' s priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Buy Now
Questions 132

A company is planning to launch a new service to improve the customer checkout experience.

What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

Options:

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an Agile delivery approach and provide information to the stakeholders on Agile values and principles.

C.

Educate the team about Scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

Buy Now
Questions 133

A Scrum team is visualizing the blockers that arise when they work on their activities on the kanban board. The team decided to analyze why the blockers occur so they can take action to minimize their occurrence and reduce lead times.

Which practices should the team use?

Options:

A.

The most important principle in Scrum is reducing work in process (WIP). The lower the number of items, the lower the risk of items getting blocked. Based on the team’s capacity, they should set the lowest WIP limits possible.

B.

The team should look at all the blockers, determine the reason behind them, group them, and determine if there is a pattern. They should then determine what and how they can make relevant changes.

C.

The team should discuss the issue with their scrum master because it is their responsibility to remove impediments, such as blockers, in cooperation with other teams.

D.

Blockers are a result of bottlenecks. The team should ask for more resources to prevent bottlenecks from arising and reduce the risk of long lead times.

Buy Now
Questions 134

A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.

What should the Agile Project Manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member ' s role may vary as stated in the definition of done (DoD).

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the Product Manager defines the functionality from end to end.

Buy Now
Questions 135

A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.

Can the product owner reject changes to a product backlog?

Options:

A.

Yes, the product owner is part of a Scrum team and can reject any changes on the product backlog.

B.

Yes, because the product owner is the decision maker for product backlog changes.

C.

No. because this action will create disruption in the Scrum team.

D.

No. because only members of the Scrum team can reject or approve changes.

Buy Now
Questions 136

Options:

A.

Planning

B.

Daily Scrum

C.

Sprint Demo

D.

Retrospective

Buy Now
Questions 137

An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.

What should the scrum master do first?

Options:

A.

Build a product roadmapthat shows the features and releases.B Request an existing cross-functional team be dedicated to the project

B.

Obtain specific product requirements from a customer focus group.

C.

Develop a project budget based on the project charter.

Buy Now
Questions 138

What should the agile coach do to develop members into a high-performance team?

Options:

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Buy Now
Questions 139

Case Study

An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team ' s support has committed to the scope and deadline.

Check in with the project in three stages to answer the associated questions.

How do two additional features and more story points added by the product owner impact the team ' s progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)

Options:

A.

The scope of the items in the backlog has been increased to reflect an increase in velocity.

B.

The backlog has been increased and the velocity of the project may no longer be on track.

C.

The team has committed to additional work added to the backlog and will increase velocity.

D.

The team did not complete the backlog items at the same velocity due to external issues

Buy Now
Questions 140

During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the Scrum Master do?

Options:

A.

Encourage all team members to participate, and have them type their retrospective feedback into the agile lifecycle management tool.

B.

Ask more specific questions during the retrospectives.

C.

Use retrospective techniques, such as silent writing, clustering, and dot voting to field feedback prior to discussion by the team.

D.

Ask team members to email feedback that can be summarized in a spreadsheet for the team.

Buy Now
Questions 141

The product owner working on an agile software development project has brought all the Scrum team members together for the first sprint planning meeting. The team has read the user stories and has provided estimates to complete these user stories. The product owner plans to empower the team to get the work done.

What is this an example of?

Options:

A.

Emotional intelligence

B.

Two-way communication

C.

Bipartisan agreement

D.

Reciprocal communication

Buy Now
Questions 142

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project ' s total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Buy Now
Questions 143

During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.

What should the Scrum Master do?

Options:

A.

Discourage the team member from deviating from the plan and document the request during the retrospective

B.

Encourage the team member to research the issue and present the findings during the retrospective

C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases

D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important

Buy Now
Questions 144

A team member has made a mistake on a project.

How should the Scrum Master address the mistake?

Options:

A.

Encourage all team members to follow existing processes.

B.

Require team members to complete a peer review of work and deliverables.

C.

Facilitate a retrospective to identify areas of improvement.

D.

Reward those who have the lowest occurrences of mistakes.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 22, 2026
Questions: 481
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$30  $99.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99