During a project ' s last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.
What should the agile practitioner do?
During team meetings, the team often struggles with making decisions about their technical approach.
What should be done to improve the quality and timeliness of decisions?
The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative ' s current status.
Which summaries are correct and will be presented during the monthly project review? (Refer to
the email and exhibits to the Team Manager)
A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.
What should the agile project leader do?
A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.
How should the project manager proceed?
What should the agile practitioner have done to ensure stakeholder satisfaction?
While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the Scrum team do?
A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.
How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?
An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours, which affects team performance.
What should the agile coach do to mitigate this issue?
Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.
What should the product owner do?
A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.
What strategy should be employed to re-organize the teams?
An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team ' s ability to produce results. The team insists on implementing these tasks since they will increase efficiency.
What should the agile coach do?
During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.
What should the scrum master do now?
A Scrum team has worked hard to reach their sprint goal, but impediments have prevented them from succeeding. The team needed help from a specialist on another team, but the specialist was on a 2-week vacation.
What should the scrum master do?
In a project, the customer asks for a requirement that clearly deviates from the contract terms.
How should the contractor react?
An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.
What should the Scrum Master do?
The product owner is very concerned about work not being completed and tested before a hard release date.
What can the agile team do to mitigate this risk?
A member of a project ' s development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.
What should the agile team lead do?
Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.
Which of the following activities should be performed next?
One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.
How should the product owner respond?
When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.
How should the agile practitioner address this concern?
During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration ' s remaining scope?
A global subscription-based service is pursuing enterprise agility across digital product development teams. Product teams release updates frequently, but customer usage data and support trends are reviewed only at the end of each quarter. As a result, several low-adoption features continue to receive investment while customer churn gradually increases. Leadership wants the product teams to respond more quickly to changing customer behavior.
What should the agile practitioner recommend?
An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).
A scrum master wants to encourage better collaboration within a collocated team and is coming up with a visualization method for the project. How could the scrum master promote transparency?
A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.
What should the agile practitioner do?
Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.
How can the project team achieve this?
The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during meetings. What should the project lead do to encourage the team members to express themselves?
One of the overseas stakeholders on an agile project has not been actively involved in the project ' s development. What would be the first step to reengage the stakeholder?
In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.
How should the agile lead implement an effective and efficient solution?
An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.
Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)
A scrum master is part of a team that has just agreed on the project scope and deliverables for a global, multilingual manufacturing company that has many staff members moving between locations. The team consists of 20 people and the budget is US$5 million. The kickoff meeting is scheduled for the following month.
What should the scrum master do as a first step?
An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.
What should the team member do?
What is the first thing an agile development team should do when planning an iteration?
An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.
What should the agile team do?
An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.
Which approach should the agile lead take?
An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.
Which approach should the agile lead take?
The Scrum Master for a large project must provide an estimate of what can be delivered in six months.
What should the Scrum Master do?
Why should an agile coach model agile principles and behaviors, become self-aware, and be present?
A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.
To address this issue and bring the project back on track, what action should the team take?
Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?
An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?
A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?
An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)
During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.
How should the scrum master respond?
The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.
What should the agile practitioner do next?
The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.
How should the Agile Leader address this?
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.
What should the Scrum Master do?
In companies where decision-making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?
An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members ' personalities and motivators?
A stakeholder complains about the amount of changes that are being introduced to a project. What should the product owner do?
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.
What should the team do to improve its speed of delivery?
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.
What should the team do to improve its speed of delivery?
Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?
A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
How many sprints will be needed to complete the entire backlog?
The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?
A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.
Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?
A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.
How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?
An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: " I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles. "
What is the agile lead attempting to highlight?
A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.
Is this agile strategy appropriate?
A newly formed Scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?
Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.
What should the team do?
A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.
How should the product owner address this situation?
A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.
How should the scrum master help the team to resolve the issue?
A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?
During planning sessions, an agile practitioner notices that some team members do not share common ideas.
What should the agile practitioner do?
One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.
What should the agile practitioner do?
Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?
Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?
When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?
When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?
A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges.
How should the team plan improvements to their product?
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.
What value can the organization gain by moving to an iterative approach?
During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.
What should the agile practitioner have done to avoid the situation?
A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.
What is the role of the team?
A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.
Which action should the scrum master take?
During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.
What should the product owner do to help the team?
A new agile team member notices that the team ' s current process involves excessive documentation. What should the new team member do?
Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.
How should this situation be handled?
Unable to meet a sprint ' s committed velocity, an agile team approaches the agile coach to define the next sprint ' s velocity. What should the agile coach advise?
The coach on a new agile team notices that one team member is influencing most of the team ' s decisions. What should the coach do?
While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.
Why is the project sponsor making this suggestion?
An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.
What should the agile project manager do to promote trust and collaboration?
At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.
How should the scrum master proceed?
An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?
The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.
What should the coach do to help the team?
In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.
How should the project manager approach this project?
An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.
What should the team do next?
During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?
During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
What should the project leader do?
In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?
A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.
What is the agile project leader doing?
During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.
What should the scrum master do?
All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)
When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?
An agile team wants to collectively determine a project ' s size. What will the team be doing if they use the planning poker technique to accomplish this?
During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)
An organization wants to increase value delivery in its agile projects.
What should the agile teams do?
During a project ' s last iteration, an agile team struggled with a feature ' s delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.
What should the agile project leader have done to avoid this situation?
A company is planning to launch a new service to improve the customer checkout experience.
What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?
A Scrum team is visualizing the blockers that arise when they work on their activities on the kanban board. The team decided to analyze why the blockers occur so they can take action to minimize their occurrence and reduce lead times.
Which practices should the team use?
A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.
What should the Agile Project Manager advise?
A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.
Can the product owner reject changes to a product backlog?
An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.
What should the scrum master do first?
What should the agile coach do to develop members into a high-performance team?
Case Study
An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team ' s support has committed to the scope and deadline.
Check in with the project in three stages to answer the associated questions.
How do two additional features and more story points added by the product owner impact the team ' s progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)
During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the Scrum Master do?
The product owner working on an agile software development project has brought all the Scrum team members together for the first sprint planning meeting. The team has read the user stories and has provided estimates to complete these user stories. The product owner plans to empower the team to get the work done.
What is this an example of?
During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.
What is the agile project manager trying to show?
During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.
What should the Scrum Master do?
A team member has made a mistake on a project.
How should the Scrum Master address the mistake?