Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Questions 4

What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Buy Now
Questions 5

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

A project charter has been completed and is ready for approval. The project's goal and approach have been clearly determined and a list of generalized specialists has been set.

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

Options:

A.

Analyze the list of all project participants and stakeholders, clarifying stakeholder roles and responsibilities.

B.

Promote consensus-driven decision-making and a shared vision for team commitments and decisions.

C.

Determine roles and responsibilities among team members and promote hierarchy, responsibility, and ownership among team members.

D.

Have team members introduce one another and create a hierarchy that reflects responsibilities, roles, and decision-making.

Buy Now
Questions 6

How could the project leader have avoided this?

Options:

A.

Led by example by encouraging the team to engage in consensus-driven decision making

B.

Iterated the need for agile teams to make quick decisions, then followed up with that team member

C.

Empowered a team member to facilitate decision making then made a final decision on behalf of the team

D.

Refrained from participating in the team's decision-making process, except to document and communicate results

Buy Now
Questions 7

An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.

Ask the Scrum Master to help reduce the rate of change.

B.

Work with the Agile Coach to document the requirements in a collaborative way.

C.

Work with the stakeholder directly rather than go through different layers of people.

D.

Work with the development team to confirm the requirements.

Buy Now
Questions 8

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Buy Now
Questions 9

What should the team do?

Options:

A.

Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Buy Now
Questions 10

Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.

What should the scrum master do to handle this situation?

Options:

A.

Separate large user stories.

B.

Apply work-in-progress limits.

C.

Organize user stories into epics.

D.

Replace user stories into features.

Buy Now
Questions 11

What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Buy Now
Questions 12

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Buy Now
Questions 13

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Buy Now
Questions 14

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Buy Now
Questions 15

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Buy Now
Questions 16

A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the Scrum Master do to accomplish this?

Options:

A.

Ask the team members' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the Scrum Master.

Buy Now
Questions 17

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace.

What analysis should the team use to understand the issues?

Options:

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Buy Now
Questions 18

An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this?

Options:

A.

Estimating story points by comparing them to similar, past features

B.

Estimating stories by placing them in buckets

C.

Using the number of dots for votes to estimate story points

D.

Estimating the relative size of stories by using story points

Buy Now
Questions 19

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

Options:

A.

Included the stakeholders in the project planning meeting

B.

Organized an earlier demo to solicit business feedback

C.

Ensured all business leaders signed off on requirements

D.

Engaged key stakeholders periodically to collect requirements

Buy Now
Questions 20

An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.

What should the agile practitioner do?

Options:

A.

Create an issue on the backlog to investigate the root cause and assign a team resource to resolve the issue immediately.

B.

Request increased velocity from the development team to clear off some defects and stay on track with the current iteration's work.

C.

Ask the team to determine how to adapt to this increase in the next retrospective.

D.

Stop work on in-progress user stories to clear defects from the product owner and increase velocity on defect resolution.

Buy Now
Questions 21

What should the product owner have done differently?

Options:

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gain confidence from the stakeholders

D.

Presented a demo of all the stories including the work in progress stories

Buy Now
Questions 22

Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?

Options:

A.

The product owner may act as the stakeholders' proxy at the demo and that the stakeholders do not need to be directly involved with the team.

B.

The demo will show whether or not the team understands the level of effort required to complete the project.

C.

The stakeholders will learn whether or not the implementation has worked by getting immediate feedback so they can correct their assumptions for the next sprint.

D.

The stakeholders will be better positioned to evaluate whether or not the resources expended by the organization are worthwhile.

Buy Now
Questions 23

A team retrospective was going well until the team lead introduced the "define the next experiment" topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team's efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.

Options:

A.

Remind the group that all input is welcome but dissension is not productive and suggest the group move on to another task more agreeable to everyone.

B.

Restate both stances, ask for details of both approaches, and create a chart of similarities and differences.

C.

Construct an Ishikawa diagram for each approach, and use the 5 Whys technique to determine the effectiveness of each approach.

D.

Interject and request this experiment be postponed for 2 months, so the new team member has time to observe the current approach.

Buy Now
Questions 24

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

Buy Now
Questions 25

What should the agile practitioner do?

Options:

A.

Ask the product owner to inform all stakeholders about the project's progress.

B.

Send meeting notes to all stakeholders after each review meeting.

C.

Include the results of the review meetings in the information radiators.

D.

Convince the stakeholders of the benefits of attending the review meetings.

Buy Now
Questions 26

An agile team is working on the first sprint, and has already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

Options:

A.

Communicate the importance of the business need to the team and refine the product backlog.

B.

Ask the team to discuss the changes to the features with the customer.

C.

Meet with the agile team lead to prioritize the requirements.

D.

Discuss and prioritize the requirements with the team.

Buy Now
Questions 27

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

Options:

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.

B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.

C.

Delegate the decision for the best feature implementation to the most senior team member.

D.

Decide on the technical implementation that best fits the purpose of the technical design.

Buy Now
Questions 28

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Buy Now
Questions 29

During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

Options:

A.

Inform the product owner's manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Buy Now
Questions 30

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Buy Now
Questions 31

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

Options:

A.

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

Buy Now
Questions 32

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Buy Now
Questions 33

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Buy Now
Questions 34

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Buy Now
Questions 35

An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?

Options:

A.

Report this as a blocker and ask senior management to provide the right subject matter experts (SMEs) until all the outstanding issues can be dosed.

B.

Identify the key business stakeholders and invite them to day-long sessions until all the dependencies and outstanding issues can be closed.

C.

Identify the key dependencies that need to be resolved in order of priority level so the user stories can meet the definition of ready (DoR) criteria.

D.

Report this as a blocker and ensure the product owner is able to deprioritize the issues so the user stories can meet the definition of ready (DoR) criteria.

Buy Now
Questions 36

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Buy Now
Questions 37

Options:

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened

Buy Now
Questions 38

In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.

How should the project manager approach this project?

Options:

A.

Define all requirements so value can be added by delivering a high-level plan at the initiation phase.

B.

Suggest the Product Owner prioritize the work items by feature to maximize value.

C.

Ask the customer to define the requirements of all stakeholders and select the most valuable features.

D.

Ensure the client has a clear idea about the features and end product before the project starts.

Buy Now
Questions 39

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?

Options:

A.

To produce a fast return on investment

B.

To reduce risk as quickly as possible

C.

To gain competitive advantage as soon as possible

D.

To maintain visibility with project stakeholders

Buy Now
Questions 40

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Buy Now
Questions 41

How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Buy Now
Questions 42

During its first sprint, a new Scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories.

What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Buy Now
Questions 43

A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.

What should the Agile Project Manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member's role may vary as stated in the definition of done (DoD).

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the Product Manager defines the functionality from end to end.

Buy Now
Questions 44

A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the first meeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.

What should the project manager do next?

Options:

A.

Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.

B.

Identity and create personas that can help the team better understand the needs of the target user base.

C.

Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).

D.

'Engage the human resources (HR) team to identify the key users and interview all of them accordingly.

Buy Now
Questions 45

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Buy Now
Questions 46

One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.

How should the product owner respond?

Options:

A.

Stakeholders have the opportunity to add features to the sprint.

B.

Team members determine if there are any impediments preventing them from meeting the sprint goal.

C.

The product owner explains which product backlog items have been done and which have not.

D.

Team members identify ways to improve and make plans to implement these improvements.

Buy Now
Questions 47

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

Options:

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Buy Now
Questions 48

Options:

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Buy Now
Questions 49

What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Buy Now
Questions 50

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

Options:

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Buy Now
Questions 51

During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation.

What should the agile practitioner do?

Options:

A.

Organize a team-building activity to improve team morale

B.

Have team members work in pairs to learn from each other and develop new skills

C.

Ask team members to perform a value stream analysis of their activities

D.

Add more resources to the team to help with the tasks

Buy Now
Questions 52

Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value.

What should the project manager do?

Options:

A.

Keep the meetings because some find them valuable and assume that those not attending are working steadily and have no blockers.

B.

Change the meeting to the end of the day ensure it lasts only 15 minutes and require all team members to attend.

C.

Work with team members to create a wiki where they can record their current accomplishments.

D.

Reduce the occurrence of meetings because team members regularly communicate with the another and the customer

Buy Now
Questions 53

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Buy Now
Questions 54

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Buy Now
Questions 55

What should the Scrum Master do?

Options:

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Buy Now
Questions 56

A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?

Options:

A.

Obtain executive team buy-in by conducting a meeting to present the advantages of agile principles and processes.

B.

Issue a memo of understanding that agile principles should be implemented for all new projects.

C.

Introduce agile principles and processes, then make the change an experiment to obtain buy-in.

D.

Require all staff and management to attend agile training and adhere to its principles.

Buy Now
Questions 57

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Buy Now
Questions 58

A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.

What should the project lead do to accommodate this request?

Options:

A.

Review the burn up chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

B.

Review the burn down chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

C.

Ensure the team focus on completing the current items in the backlog and do not accept any request for changes.

D.

Work with the product owner to launch a minimum viable product (MVP) and focus on completing only this portion of work by the new deadline.

Buy Now
Questions 59

What should the project leader suggest?

Options:

A.

Develop and document a detailed architectural design; peer review with the development team and implement/test

B.

Develop the functional requirements of the solution first before any non-functional requirement, as they provide more customer value

C.

Discuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature

D.

Develop and test the implementation approach and demonstrate it at the next sprint review to collect feedback

Buy Now
Questions 60

During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk.

What should the team do next?

Options:

A.

Work overtime to meet the customer request and the iteration commitments.

B.

Ask another team that is less busy to handle the situation.

C.

Work with the product owner to assess the impact for reprioritization.

D.

Work on the customer request in the next iteration as a top priority.

Buy Now
Questions 61

What should the agile team do next?

Options:

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Buy Now
Questions 62

What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

Options:

A.

Invite people from across the organization to attend daily stand-ups

B.

Invite people from across the organization to attend retrospectives

C.

Invite people from across the organization to attend the release meeting and project retrospectives

D.

Regularly meet with people across the organization to share the project's lessons learned and best practices

Buy Now
Questions 63

What should the agile team lead do?

Options:

A.

Create a new team to deliver the dependencies, and bring team B under performance management.

B.

Conduct a vision-sharing session with the teams to communicate the project's overall goals.

C.

Swap team members from both teams so that deliveries are better supported.

D.

Discuss negotiating the delivery timelines with team A.

Buy Now
Questions 64

A product owner needs to elaborate on a product roadmap. How can the product owner collaborate with stakeholders to identify the features that offer maximum value?

Options:

A.

Identify the product users and their high-level key activities to get their perspective because the product is intended for them.

B.

Obtain the project sponsor's perspective to get an initial idea of the features they believe the product should have to guide the development team.

C.

Analyze the development team's capacity and skills because these will determine which features to include in the roadmap.

D.

Create a draft of the product roadmap that the development team can use as a guide for further guidance.

Buy Now
Questions 65

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Buy Now
Questions 66

What should the product owner do?

Options:

A.

Determine the required tasks for implementing the high-level features

B.

Identify the detailed design for the high-level features

C.

Prioritize the product backlog for the upcoming release

D.

Estimate the user stories in the iteration backlog

Buy Now
Questions 67

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Options:

A.

Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk.

B.

The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions.

C.

Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support.

D.

An owner should have been identified to obtain timely stakeholder feedback.

Buy Now
Questions 68

A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.

To address this issue and bring the project back on track, what action should the team take?

Options:

A.

Perform value stream analysis to eliminate the processes with wastage.

B.

Reevaluate the minimum viable product (MVP) deliverables to remove high-risk stories and meet timelines.

C.

Adjust the story points included in each sprint to represent the actual velocity.

D.

Include high-risk stories in earlier sprints to deliver incremental velocity.

Buy Now
Questions 69

A project's Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

Options:

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Buy Now
Questions 70

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.

What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Buy Now
Questions 71

Options:

A.

Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.

B.

Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.

C.

Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.

D.

Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.

Buy Now
Questions 72

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Buy Now
Questions 73

Why is stakeholder engagement important for project success?

Options:

A.

To participate in establishing a shared vision as a member of the team

B.

To provide the acceptance criteria for the delivered items

C.

To propose implementation methods to the development team

D.

To evaluate the performance of the development team

Buy Now
Questions 74

During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.

What can the team do to better manage this situation?

Options:

A.

Deliver the minimum marketable feature (MMF) to customers for feedback.

B.

Write acceptance criteria for each business requirement to conduct proper testing.

C.

Develop test cases based on user stories.

D.

Ask the customer to provide acceptance criteria before developing the user stories.

Buy Now
Questions 75

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Buy Now
Questions 76

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?

Options:

A.

Self-organize

B.

Assign tasks to each team member

C.

Meet with the customer

D.

Identify the Scrum Master

Buy Now
Questions 77

What should the project leader do?

Options:

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Buy Now
Questions 78

On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?

Options:

A.

A project charter should be established and reviewed throughout the project life cycle to ensure the accurate documentation of stakeholders' interests and expectations.

B.

A product backlog should be created to list the project requirements from all of the project stakeholders.

C.

An Agile Manifesto should be created to document the project stakeholders, their desired outcomes, and identified risks.

D.

A user story should be created for all key stakeholders to list their individual business objectives and needs.

Buy Now
Questions 79

Due to its complexity, a new team member struggles with developing a concise user story.

What advice should the agile practitioner give to assist with developing the story?

Options:

A.

Hand the story over to a more experienced team member

B.

Break the story up and focus on the most valuable parts

C.

Discuss the story at the next retrospective

D.

Pick another story from the product backlog

Buy Now
Questions 80

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Buy Now
Questions 81

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

Options:

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project's success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Buy Now
Questions 82

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the Scrum Master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.

B.

Ask the team to find a workaround so that they can continue with the current project management plan.

C.

Advise the team to continue working on the sprints as the release plan has been set.

D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.

Buy Now
Questions 83

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?

Options:

A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.

B.

Collect updates from each team member before the meeting and share them with all members.

C.

Ask the team member to update daily progress on the information radiators.

D.

Change the team velocity to show positive progress in shared information radiators.

Buy Now
Questions 84

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all spikes are executed

Buy Now
Questions 85

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

Options:

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Buy Now
Questions 86

A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.

How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?

Options:

A.

The team needs to see the product owner's body language and facial expressions to understand what they really want.

B.

An in-person meeting helps ensure the product owner will consider their feedback carefully and not ask for any unneeded rework.

C.

It typically takes more time and resources to set up and test a virtual communications tool than to meet in person.

D.

The team will be able to better address the product owner's needs if they can have a conversation and ask questions.

Buy Now
Questions 87

The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.

What is the estimated project conclusion?

Options:

A.

Twelve months

B.

Three months

C.

Six months

D.

Two months

Buy Now
Questions 88

A project team is working with an enterprise agile center of excellence (CoE) to transition to a Scaled Agile Framework (SAFe). Many of the team members are not familiar with the new methodology and are worried that it will lead to more work and scrutiny.

What should the agile team lead do to help ensure a smooth transition?

Options:

A.

Set up lunch-and-learn sessions with the team to provide overviews about the new way of working.

B.

Encourage knowledge sharing and transparency among the working team.

C.

Request the enterprise coach to help the team through the process

D.

Discuss with the team what will change and when and establish a process to address concerns.

Buy Now
Questions 89

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

Options:

A.

Coordinate a collaboration session so all the team members are involved in the solution process.

B.

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.

Hire external consultants to advise on solution options and train team members in any technical gaps.

Buy Now
Questions 90

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Buy Now
Questions 91

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

Options:

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Buy Now
Questions 92

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

Options:

A.

Review the burndown chart to identify ways to increase efficiency.

B.

Chair a weekly team retrospective focusing on identifying areas for continuous improvement.

C.

Ask a senior manager to initiate a root-cause analysis.

D.

Identify team key performance indicators (KPIs) and create positive incentives when targetsare achieved.

Buy Now
Questions 93

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Buy Now
Questions 94

In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.

What are some of the practices a project manager can bring to an adaptive environment?

Options:

A.

Building a collaborative decision-making environment with key stakeholders, teams, and sponsors.

B.

Ownership of detailed project planning, user histories, retrospectives, showcases and metrics board

C.

Ensuring agile values and principles are adopted by all teams involved in delivery of the project.

D.

Developing the project charter, writing the project plan, and following the achievement of all milestones.

Buy Now
Questions 95

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

Options:

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Buy Now
Questions 96

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.

How should the agile practitioner handle the recommendation?

Options:

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team's senior members decide whether to adopt the suggested practice.

Buy Now
Questions 97

What was the determining factor?

Options:

A.

Size and priority

B.

Minimum marketable features

C.

Release plan

D.

Sprint mapping

Buy Now
Questions 98

Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?

Options:

A.

Ask the agile practitioner to help write the user stories.

B.

Ask the agile team to facilitate a story-writing workshop.

C.

Ask subject matter experts (SMEs) to help write the user stories.

D.

Ask the agile practitioner to facilitate a story-writing workshop.

Buy Now
Questions 99

Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.

What should the Scrum Master do in this situation?

Options:

A.

Understand the root cause of this issue and recommend discussing their differences to find common ground.

B.

Hold a team meeting to discuss these issues and help direct the whole team on how to proceed further.

C.

Let the two team members resolve the conflict on their own.

D.

Ask their functional manager to intervene and resolve the issue.

Buy Now
Questions 100

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

Options:

Buy Now
Questions 101

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Buy Now
Questions 102

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.

What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom, and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog’s priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project’s progress

Buy Now
Questions 103

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

Options:

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Buy Now
Questions 104

Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.

What should the project manager do?

Options:

A.

Mention the risks during the daily standups and ensure all agreed-upon response actions are discussed by the team.

B.

Remind the team daily about the threats and request a response regarding which risks have been identified and resolved

C.

Arrange weekly meetings and invite the project sponsor to discuss the importance of the project with the team.

D.

Create a space on the board to prioritize the threats, along with an update on the actions that are in progress and what still needs to be done.

Buy Now
Questions 105

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Buy Now
Questions 106

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Buy Now
Questions 107

A technical problem arises that will likely impact the stories planned for delivery in the current sprint.

What should the Scrum Master do?

Options:

A.

Consider adding a story to the next sprint to seek resolution

B.

Immediately solve the problem on behalf of the team

C.

Ask the team to collaboratively work out a solution

D.

Engage a technical manager to assist with finding a solution

Buy Now
Questions 108

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met.

How should the project management plan be adjusted?

Options:

A.

Holistically at the project level

B.

At the end of each sprint

C.

At a sprint level after each demo

D.

Periodically, at both the release and project level

Buy Now
Questions 109

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

Options:

A.

Amount of work needed to complete a single user story

B.

Amount of work that can be accomplished by each team member

C.

Amount of work that can be accomplished in an iteration

D.

Amount of work that can be accomplished by the entire team

Buy Now
Questions 110

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

How many sprints will be needed to complete the entire backlog?

Options:

A.

15

B.

16

C.

17

D.

18

Buy Now
Questions 111

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

Options:

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.

Buy Now
Questions 112

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team's agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Buy Now
Questions 113

The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?

Options:

A.

By coaching the team to outperform previous velocity

B.

By coaching the team to adhere to expectations set by the scrum master

C.

By encouraging overestimation to increase velocity

D.

By advising the team to remain committed and focused on project goals

Buy Now
Questions 114

Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.

What should the Scrum Master do next?

Options:

A.

Alert the team that sprint goals might not be met and create an alternative plan

B.

Obtain team buy-in to perform modifications to the sprint backlog

C.

Have the sprint proceed as planned

D.

Ask the team to decide if the task should be reassigned

Buy Now
Questions 115

A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?

Options:

A.

Have the development team follow the product owner's direction

B.

Openly challenge the product owner in an effort to poke holes in their approach

C.

Facilitate a conversation about the user story between the development team and the product owner

D.

Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Buy Now
Questions 116

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?

Options:

A.

Project velocity should be stable overtime.

B.

Moving velocity from 27 to 35 is a decrease in productivity.

C.

A burndown chart compares planned versus actual, not velocity.

D.

Velocity is iterative and will only be used for sprint numbers.

Buy Now
Questions 117

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team's estimated velocity.

Buy Now
Questions 118

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all spikes are executed

Buy Now
Questions 119

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

Options:

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Buy Now
Questions 120

What should the agile practitioner have done to ensure stakeholder satisfaction?

Options:

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Buy Now
Questions 121

A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.

What is the estimated time remaining for the project?

Options:

A.

Eight months

B.

Two months

C.

Four months

D.

Six months

Buy Now
Questions 122

What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

Buy Now
Questions 123

What should the agile coach do?

Options:

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Buy Now
Questions 124

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

Options:

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Buy Now
Questions 125

A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.

Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?

Options:

A.

Empower each cross-functional team lead to manage their team's issues and impediments.

B.

Post the daily coordination meetings and discuss impediments raised by the teams.

C.

Ask the project management office (PMO) to work on the communications management plan for the cross-functional teams.

D.

Set up additional meetings to handle additional communications if necessary.

Buy Now
Questions 126

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Buy Now
Questions 127

Answer Options:

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Buy Now
Questions 128

An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.

What should the scrum master do first?

Options:

A.

Build a product roadmapthat shows the features and releases.B Request an existing cross-functional team be dedicated to the project

B.

Obtain specific product requirements from a customer focus group.

C.

Develop a project budget based on the project charter.

Buy Now
Questions 129

A Product Owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog.

What should the Product Owner do next?

Options:

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Buy Now
Questions 130

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.

How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Buy Now
Questions 131

Which option describes how risk should be managed in an agile project?

Options:

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stories they have been assigned.

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Buy Now
Questions 132

An agile team is optimizing the workflow by investing in initiatives to identify and reduce unnecessary handovers and delays. What should the team do in this situation?

Options:

A.

Create a value stream map.

B.

Draw a risk burndown chart.

C.

Use a kanban board.

D.

Make a cumulative flow diagram.

Buy Now
Questions 133

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?

Options:

A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.

B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.

C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.

D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.

Buy Now
Questions 134

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

Options:

A.

Calculated planned percent complete (PPC)

B.

Many small minimally marketable features (MMFs)

C.

Story points rather than cost estimates

D.

Calculated earned value (EV)

Buy Now
Questions 135

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

Options:

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.

B.

Define software functionality by relying on the developers' experience designing similar system

C.

Engage end users in user acceptance testing to ensure the product meets their expectations.

D.

Educate end users and other stakeholders to understand desired outcomes through user stories.

Buy Now
Questions 136

Options:

A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Buy Now
Questions 137

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.

Influence the customer

B.

Mention the idea at the next retrospective

C.

Show the customer how much time and money would be saved

D.

Present the idea at the next ceremony attended by stakeholders to obtain their input

Buy Now
Questions 138

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?

Options:

A.

Convince the team to stop planning and keep the size small

B.

Identify the technically minimal and achievable tasks

C.

Refer to the remaining prioritized backlog items

D.

Select some of the smallest items from the backlog

Buy Now
Questions 139

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Buy Now
Questions 140

What should the product owner do?

Options:

A.

Accept responsibility for the product's delay.

B.

Ensure that the project sponsor's priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Buy Now
Questions 141

What should the agile practitioner do?

Options:

A.

Review established ground rules with the team

B.

Ask team members specific questions to identify the cause

C.

Encourage the team to continue working to maintain the iteration's schedule

D.

Meet with the product owner and stakeholders to discuss the issue

Buy Now
Questions 142

A team is preparing to demonstrate new product capabilities to a leadership team. The demonstration will show working software and a listing of the projected value of the capabilities.

What should the team do to ensure the demonstration is successful?

Options:

A.

Provide an understanding of business value and customer feedback.

B.

Align with stakeholder expectations and releasable product increments.

C.

Show self-management and tailoring processes for continuous improvement.

D.

Provide collaboration and knowledge sharing of product increments.

Buy Now
Questions 143

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

Options:

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the Product Owner perform the initial investigation and present the outcome to the team.

C.

Request that the Product Owner include a spike in the next iteration's backlog so they can perform an initial investigation.

D.

Propose alternative components with which the team has experience.

Buy Now
Questions 144

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

Options:

A.

Coach the company director on agile approaches and good practices.

B.

Ask the product owner to speak to the director because their visits are delaying the project.

C.

Ask the director and team member to leave the room so they can have a private conversation.

D.

Coach the team member on how to report progress to directors and executives.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Aug 17, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$29.75  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$35  $99.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$47.25  $134.99