Black Friday Early Access - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save75geek

LEED-AP-BD+C LEED AP Building Design + Construction (LEED v5 AP BD+C) Questions and Answers

Questions 4

A design team pursuing LEED for a new office building project calculated that with the water fixtures specified for the project, a 24% water reduction can be achieved compared to the LEED baseline. What does this mean to the team in terms of pursuing LEED?

Options:

A.

The project cannot pursue LEED

B.

The project may pursue Water Efficiency Credit, Indoor Water Use Reduction

C.

The project does not meet Water Efficiency Prerequisite, Indoor Water Use Reduction, but can make up the points elsewhere in the rating system

D.

The project can meet the Water Efficiency Prerequisite, Indoor Water Use Reduction, but cannot earn any points under Water Efficiency Credit, Indoor Water Use Reduction

Buy Now
Questions 5

A school wants to incorporate natural daylighting in classrooms on all sides of the building. What can the project design team explain to the school district about how this strategy will affect the operational energy cost?

Options:

A.

Heat gain will reduce the air conditioning load

B.

Having the lights off reduces the electricity use

C.

Reduction in lighting fixture use reduces re-lamping

D.

There would be passive solar heating benefits to all of the classrooms

Buy Now
Questions 6

A new building containing private offices is pursuing Location and Transportation Credit, Access to Quality Transit. Which would comply?

Options:

A.

Locate the project¼ mile (0.4 km) walking distancefrom two campus bus system lines (only accessible to campus students) with two stops each

B.

Locate the project½ mile (0.8 km) walking distancefrom two bus lines with two stops each

C.

Locate the project¼ mile (0.4 km) walking distancefrom a planned, funded, and partially complete subway station

D.

Locate the project½ mile (0.8 km) walking distancefrom a planned, not funded commuter rail

Buy Now
Questions 7

The design team is attempting to achieve the Increased Ventilation strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality in a conference room. The associated ASHRAE standard requires 400 CFM (11.3 CMM) of ventilation air, but the local code requires 500 CFM (14.1 CMM) of ventilation air. What is the required minimum amount of ventilation air to achieve this credit?

Options:

A.

650 CFM (18.4 CMM)

B.

500 CFM (14.1 CMM)

C.

400 CFM (11.3 CMM)

D.

520 CFM (14.7 CMM)

Buy Now
Questions 8

The LEED project has a main entrance and two service entrances in an alley behind the building. Which entrances need non-smoking signage and at what maximum distance from the door(s) can the non-smoking signage be posted?

Options:

A.

At the main entrance, 10 ft. (3 m) from the door

B.

At the main entrance, 25 ft. (7.5 m) from the door

C.

At the main entrance and the two service entrances, 10 ft. (3 m) from the doors

D.

At the main entrance and the two service entrances, 25 ft. (7.5 m) from the doors

Buy Now
Questions 9

Which of the following contributes to the value of the commissioning process?

Options:

A.

Ensuring that the project budgetary goal is met

B.

Verifying that the building systems perform as intended

C.

Verifying that the building water fixtures are installed properly

D.

Ensuring that the project is delivered to meet the permitting requirements

Buy Now
Questions 10

What phase of the integrative process gives the team the greatest chance of success in meeting the project ' s environmental goals cost-effectively?

Options:

A.

Design

B.

Discovery

C.

Operations

D.

Construction

Buy Now
Questions 11

Which one of the following represents quality transit service as defined in Location and Transportation Credit, Access to Quality Transit?

Options:

A.

A bus stop served by two bus lines Monday through Friday, located 1/8 mi. (0.20 km) from the project building

B.

A rail station served by one train line Monday through Sunday, located 1/2 mi. (0.80 km) from the project building

C.

A rail station served by two train lines Monday through Sunday, located 1 mi. (1.60 km) from the project building

D.

A private shuttle bus stop providing hourly service Monday through Friday to a rail station two hours away, located across the street from the project building

Buy Now
Questions 12

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

Options:

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

Buy Now
Questions 13

Which system is eligible for EAc4: Renewable Energy?

Options:

A.

Tidal energy conversion

B.

Municipal solid waste combustion

C.

Ground-source heat pumps

D.

Passive solar and daylighting strategies

Buy Now
Questions 14

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, when should the Owner’s Project Requirements (OPR) be created and updated?

Options:

A.

Prior to beginning design and are generally not updated

B.

Once the project design is completed and edited throughout the project

C.

During predesign and are edited throughout the project

D.

After the design is completed and are generally not updated

Buy Now
Questions 15

The project needs to attempt WEp2: Minimum Water Efficiency. Which combination of process water, appliances, and flush/flow fixtures should the project show compliance for?

Options:

A.

Janitor sinks, kitchen dishwashers, toilets, and lavatories

B.

Pool water, ice maker, lavatories, and showers

C.

Showers, kitchen sinks, toilets, and cooling towers

Buy Now
Questions 16

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

Options:

A.

A, B, C

B.

B, C, D

C.

C, D, E

D.

A, B, D

Buy Now
Questions 17

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

Options:

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost

B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system

C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system

D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system

Buy Now
Questions 18

Which of the following is true regarding LEED Pilot Credits?

Options:

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project ' s scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

Buy Now
Questions 19

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project ' s

Options:

A.

environmental zone

B.

longitude and latitude

C.

ASHRAE 90.1 - 2010 climate zone

D.

Environmental Protection Agency Phase I Assessment

Buy Now
Questions 20

For major renovation and new construction projects, the required energy and water-related system analyses should be the same except for

Options:

A.

site conditions

B.

massing and orientation

C.

plug and process load needs

D.

building envelope performance

Buy Now
Questions 21

In order for a product to contribute to Materials and Resources Credit, Building Product Disclosure and Optimization, Environmental Product Declarations, Option 1. Environmental Product Declaration, the product needs to be

Options:

A.

Forest Stewardship Council (FSC)-certified

B.

cradle-to-cradle certified

C.

third-party verified in a Corporate Sustainability Report (CSR)

D.

critically reviewed life-cycle assessment conforming to ISO 14044

Buy Now
Questions 22

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Buy Now
Questions 23

During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?

Options:

A.

Green roof

B.

Site conditions

C.

Massing and orientation

D.

Programmatic and operational parameters

Buy Now
Questions 24

Which of the following types of water should a project team focus on utilizing to achieve water savings and acquire points under WEc2: Enhanced Water Efficiency, Option 6. Water Reuse, Path 1. Reuse-Ready System, while reducing reliance on potable water?

Options:

A.

Desalinated ocean water provided by a utility company

B.

Graywater collected and treated on-site

C.

Harvested and stored rainwater

Buy Now
Questions 25

Which strategy should be employed to improve daylighting when designing a new building?

Options:

A.

Increase the building depth

B.

Increase the number of skylights

C.

Increase the height of interior partitions

D.

Decrease the number of exterior light shelves

Buy Now
Questions 26

Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?

Options:

A.

Ceiling heights

B.

Building furniture

C.

Movable partitions

D.

Permanent interior obstructions

Buy Now
Questions 27

Which of the following ventilation strategies is essential for maintaining acceptable indoor air quality while balancing energy use?

Options:

A.

Natural ventilation through operable windows

B.

Mechanical ventilation with heat recovery

C.

Underfloor air-distribution systems

Buy Now
Questions 28

Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?

Options:

A.

Floor decking

B.

Asbestos insulation

C.

Exterior glazing

D.

Plumbing fixtures

Buy Now
Questions 29

Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?

Options:

A.

Use of natural plants rated for their effect in reducing the heat island effect, while also restoring a minimum of 20% (including the building footprint) of all portions of the site identified as previously disturbed

B.

Use of only native or adapted vegetation, along with not restoring a minimum of 36% (including the building footprint) of all portions of the site identified as previously disturbed

C.

Use of native or adapted vegetation, restoring a minimum of 30% (including the building footprint) of all portions of the site identified as previously disturbed

D.

Use of natural vegetation and not artificial greenery, restoring a minimum of 25% (including the building footprint) of all portions of the site identified as previously disturbed

Buy Now
Questions 30

Which of the following strategies can be used to reduce the internal load of a building?

Options:

A.

Decreasing lighting power

B.

Oversize the HVAC systems

C.

Install low reflective exterior facade

D.

Increase the insulating value of the glazing and window frame system

Buy Now
Questions 31

Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?

Options:

A.

Electrical, Mechanical, Plumbing, and Renewable Energy

B.

Electrical, Structural, Mechanical, and Lighting

C.

Electrical, Structural, Audio Visual, and Envelope

D.

Electrical, Plumbing, Telecommunications, and Fire Suppression

Buy Now
Questions 32

According to Location and Transportation Credit, Sensitive Land Protection, Option 2: Floodplains requirement, projects that do not have legally adopted flood hazard maps should locate on a site that is:

Options:

A.

Entirely outside any floodplain subject to a1% or greater chance of flooding in any given year

B.

Within afloodplain subject to a 3% or greater chance of flooding every other year

C.

Outside any floodplain subject to a2% or greater chance of flooding in any given 5-year period

D.

Entirely outside any floodplain subject to a3% or greater chance of flooding in any given 10-year period

Buy Now
Questions 33

The LEED AP has identified a pilot credit that is relevant to the project. This would be documented in LEED Online as a(n)

Options:

A.

Exemplary Performance for a related credit

B.

Special Circumstances within a related credit

C.

Regional Priority Credit

D.

Innovation Credit

Buy Now
Questions 34

When designing for operational decarbonization, a recommended practice when specifications call for refrigerants with a Global Warming Potential (GWP) above 700 is to develop a list of equipment options using:

Options:

A.

Refrigerants with a GWP less than or equal to 700

B.

Reclaimed refrigerants with a GWP less than or equal to 700

C.

Refrigerants with higher volumetric capacity to keep their GWP impact less than or equal to 700

Buy Now
Questions 35

Which of the following water management practices can be applied to identify and address hidden leaks in the water system of a commercial building?

Options:

A.

Implement a comprehensive reporting system for water usage

B.

Set up a separate meter for each floor of the building

C.

Install an advanced system with sensors throughout the plumbing network

Buy Now
Questions 36

IPp1: Climate Resilience Assessment identifies a high risk of extreme heat caused by the urban heat-island effect and flooding caused by an impervious site. Which combination identifies an appropriate strategy for heat and sea-level or flooding risks?

Options:

A.

Heat: High-albedo white roofSea level: Emergency backup generators

B.

Heat: High-efficiency variable refrigerant flow systemSea level: Green roof

C.

Heat: Exterior window shading and operable windowsSea level: Sump pumps with backup power

Buy Now
Questions 37

Which of the following requires standard appliances for indoor water reduction?

Options:

A.

CEE Tier 3A

B.

GreenSeal

C.

ASHRAE Standard 62.1-2010

D.

ISO 14044-2006

Buy Now
Questions 38

Which of the following actions is aligned with EQc3: Accessibility and Inclusion?

Options:

A.

Provide lactation rooms or lactation pods

B.

Install automated door systems for all entryways

C.

Incorporate visual contrast between architectural elements

Buy Now
Questions 39

A new theater is being designed to enhance acoustical comfort for its audiences. One of the main challenges the design team faces is minimizing excessive reverberation. The team plans to incorporate various materials and design strategies to control sound reflections.

Which of the following design strategies should effectively enhance acoustical comfort?

Options:

A.

Install hard flooring surfaces throughout the theater

B.

Maximize the use of soundproof glass walls and windows

C.

Utilize ceiling baffles and wall panels made from sound-absorbing materials

Buy Now
Questions 40

When preparing the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, the Construction General Permit must contain which of the following?

Options:

A.

Waste Management Plan

B.

Building orientation on the site

C.

Installation plan for perimeter control

D.

Minimum standards for equipment exhaust

Buy Now
Questions 41

To achieve LEED points under MRc2 Reduce Embodied Carbon, Option 3: Track Carbon Emissions from Construction Activities, it requires:

Options:

A.

On-site adherence to the AGC Playbook on Decarbonization and Carbon Reporting

B.

Documenting type and amounts of all on-site usage of fuel and utilities

C.

Creating a plan to achieve a reduction of on-site carbon emissions

Buy Now
Questions 42

The Exemplary Performance threshold for Sustainable Sites Credit, Rainwater Management requires:

Options:

A.

Utilizing a rain garden to manage the 98th percentile rainfall event

B.

Managing 100% of rainfall that falls within the project boundary

C.

Achievement of both Option 1. Percentile of Rainfall Events and Option 2. Natural Land Cover Conditions

D.

Utilizing a combination of both structural and non-structural measures to manage the 98th percentile rainfall event

Buy Now
Questions 43

According to LEED guidelines, which of the following project types should utilize the LEED BD+C rating system?

Options:

A.

A museum with extensive renovations that requires a new certificate of occupancy

B.

An apartment complex undergoing extensive repairs that affects a majority of the interior layout

C.

A theater with updated mechanical systems that retains its original structural components

Buy Now
Questions 44

A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?

Options:

A.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Indoor Water Use Reduction

B.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Outdoor Water Use Reduction

C.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Credit, Indoor Water Use Reduction

D.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Prerequisite, Indoor Water Use Reduction

Buy Now
Questions 45

When following the LEED Building Design and Construction Integrative Process credit, which of the following is the approach for the design team to follow?

Options:

A.

Locate a solid waste provider that has sorting capabilities

B.

Assure the aesthetics will match existing neighborhood conditions

C.

Identify synergies among building systems and equipment

D.

Determine if green vehicles will be applicable to the project

Buy Now
Questions 46

Where must a building ' s no-smoking signage be posted?

Options:

A.

Within 10 ft. (3 m) of all building entrances

B.

Within 10 ft. (3 m) of the main building entrance(s)

C.

Within 25 ft. (8 m) of all building entrances

D.

Within 25 ft. (8 m) of the main building entrance(s)

Buy Now
Questions 47

Which of the following projects are eligible for LEED certification?

Options:

A.

Prefabricated sandwich panel house

B.

New office building900 ft² (83.6 m²)

C.

Houseboat

D.

Mobile home

Buy Now
Questions 48

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

Options:

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Buy Now
Questions 49

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

Options:

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a post office and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

Buy Now
Questions 50

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner ' s Project Requirements

D.

Coordination of other contractors

Buy Now
Questions 51

When using the Integrative Process, what is the best way for the LEED AP to assess the impact of indoor and outdoor water consumption in a Building Design and Construction project?

Options:

A.

Perform a preliminary water budget analysis before the completion of schematic design

B.

Install permanent metering on both the water sources and the waste water leaving the site

C.

At the completion of schematic design, count the fixtures and apply the maximum flow rate

D.

Estimate consumption by using 20 gal. per day (76 I per day) for each Full Time Equivalent (FTE) scheduled to occupy the building

Buy Now
Questions 52

During a design charrette, community neighbors raise a concern about potential glare resulting from a project ' s highly reflective roof. Which option should the LEED AP recommend to best address these concerns?

Options:

A.

Install a vegetative roofing system

B.

Change the design to reduce the amount of roofing area

C.

Change the roofing material to a dark material to eliminate the issue

D.

Increase the parapet height

Buy Now
Questions 53

Which of the following standards needs to be followed to comply with Indoor Environmental Quality Credit, Thermal Comfort?

Options:

A.

ASHRAE 55-2010

B.

ASHRAE 62.1-2010

C.

ASHRAE 90.1-2010

D.

ASHRAE 189.1-2010

Buy Now
Questions 54

When designing a building that includes Electric Vehicle Supply Equipment (EVSE), which capability is needed to ensure maximum energy efficiency and cost savings?

Options:

A.

Install EVSE that operates only during peak hours to ensure availability

B.

Integrate EVSE with demand-response programs and load-management strategies

C.

Install Level 1 charging stations with 120-volt service for all spaces

Buy Now
Questions 55

Which of the following methods can be used for minimizing refrigerant leakage in buildings to align with EAc7: Enhanced Refrigerant Management?

Options:

A.

Replacing all refrigerants with chlorofluorocarbons (CFCs)

B.

Implementing automatic detection devices in the refrigerant systems

C.

Using ammonia-based systems

Buy Now
Questions 56

A project team is deciding on the impact of a proposed concrete walkway. Which of the following will be impacted as a result of adding the walkway?

Options:

A.

Site ' s impervious cover

B.

Project density calculations

C.

Erosion and sediment control plan during construction

D.

Air quality as a result of off gassing that occurs as concrete cures

Buy Now
Questions 57

The maximum number of points for Water Efficiency Credit, Cooling Tower Water Use can be obtained by

Options:

A.

utilizing a once-through system without recirculation

B.

limiting cooling tower make-up to 50% of a potable source

C.

conducting a one-time potable water analysis to determine acceptable non-potable sources

D.

achieving a minimum of 10 cooling tower cycles by increasing the level of make-up water treatment

Buy Now
Questions 58

Which of the following strategies enhances energy resilience by ensuring that critical loads are powered during a grid outage?

Options:

A.

Increase insulation in the building envelope

B.

Install a battery energy-storage system

C.

Implement energy-efficient lighting

Buy Now
Questions 59

Which of the following is an example of a nonroof measure for Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

A playground with artificial turf

B.

A vegetated shading structure

C.

A shade structure with a three-year aged Solar Reflectance Index (SRI) value of 0.2

D.

A paving material with a three-year aged SRI value of 0.2

Buy Now
Questions 60

Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space?

Options:

A.

Retail

B.

Hospitality

C.

Core and Shell Development

D.

New Construction

Buy Now
Questions 61

A design team working on a new building in a coastal city is considering climate resilience strategies. The team refers to the Intergovernmental Panel on Climate Change (IPCC) Sixth Assessment Report to incorporate different emissions scenarios on projected climate changes.

The design team can use emissions scenarios to enhance the climate resilience of their building project by utilizing the:

Options:

A.

Scenarios consistent with current global policies and historical emissions trends

B.

Mid-range scenarios, as they are most likely to occur

C.

Scenarios appropriate for the geographic location of the project that take into account local climate action plans

Buy Now
Questions 62

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

Options:

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Buy Now
Questions 63

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

Options:

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

Buy Now
Questions 64

Which of the following workforce development training types contributes to earning points under LTc2: Equitable Development, Option 3: Equitable Construction?

Options:

A.

Financial literacy courses provided on-site by a recognized organization or government entity

B.

Safety training workshops conducted monthly for all construction personnel

C.

Wellness programs offered by a recognized organization to workers on-site

Buy Now
Questions 65

The LEED AP is leading the first design charrette for a new LEED project with the project ' s owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner ' s Project Requirements (OPR)

B.

Owner ' s list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Buy Now
Questions 66

Which of the following should be analyzed when pursuing an Integrative Design Process focusing on Energy-Related

Systems?

Options:

A.

Site conditions

B.

Potable water availability

C.

Acoustic performance of the project

D.

Applicability of Green Vehicles to the project

Buy Now
Questions 67

A project team is designing a new mixed-use development that aims to achieve LEED certification. To encourage electric-vehicle use, the team plans to install EV charging stations in the parking garage. The project site is in a region where 70% of electricity comes from renewable sources.

To align with LEED strategies for sustainable transportation, what consideration should the project team prioritize when installing the EV charging stations?

Options:

A.

Availability of real-time energy-consumption monitoring at the charging stations

B.

Provision of free parking for EV users near the charging stations

C.

Number of charging stations in proportion to the total number of parking spaces

Buy Now
Questions 68

The project team achieved a strategy not addressed in the LEED Green Building Rating System, which proved to be a significant, measurable environmental benefit for the project. What can the project team do in order to get a benefit for this strategy?

Options:

A.

Submit a regional priority credit

B.

No benefit can be achieved since the strategy is not included in the rating system

C.

Submit the manufacturer ' s product declaration

D.

Submit an innovation credit

Buy Now
Questions 69

A building owner in an arid climate is trying to design an outdoor lunch area for the tenants. Which landscaping strategy is important to employ in order to reduce water demand?

Options:

A.

Large maple trees for shading

B.

Xeriscaping landscape beds

C.

Turf grass area for picnic benches

D.

Tropical flowers next to park benches

Buy Now
Questions 70

In the context of community connectivity, the purpose of promoting walkability in urban planning is to:

Options:

A.

Foster social engagement and interaction

B.

Improve public health and encourage active lifestyles

C.

Increase urban density and reduce urban sprawl

Buy Now
Questions 71

A new mixed-use development includes residential units and commercial spaces. The project is in an urban area with existing pedestrian paths and public transportation infrastructure. How can the project team minimize exposure to emissions from vehicle traffic around the property while ensuring compliance with LEED strategies?

Options:

A.

Establish mandatory carpooling arrangements for residents and employees

B.

Integrate indoor plants to absorb carbon dioxide

C.

Designate a no-idling zone around the building perimeter

Buy Now
Questions 72

A Core and Shell developer pursuing the IPc2 Green Leases credit has drafted lease language. Which provision meets the intent of the credit for binding tenant sustainability commitments?

Options:

A.

Tenant shall submit quarterly energy and water consumption reports and achieve a minimum 50% waste diversion rate verified through waste hauler documentation.

B.

Owner will provide tenant with LEED design guidelines and green building best-practices handbook within 30 days of lease execution for reference.

C.

Tenant acknowledges that the building has achieved LEED certification and agrees to maintain awareness of sustainable building operations during occupancy.

Buy Now
Questions 73

A new Science Education Center is pursuing LEED certification. Which of the following strategies could be submitted to earn an Innovation in Design credit?

Options:

A.

The selection of energy-efficient LED fixtures for all of the building ' s lighting

B.

The installation of an air-purifying facade material on the front entrance of the building

C.

The integration of rainwater management strategies to achieve a Regional Priority Credit

D.

The implementation of a comprehensive metering strategy to measure three individual energy end uses

Buy Now
Questions 74

Which of the following credits can be awarded an Innovation point for Exemplary Performance?

Options:

A.

Indoor Environmental Quality Credit, Daylight

B.

Indoor Environmental Quality Credit, Low-Emitting Materials

C.

Indoor Environmental Quality Credit, Minimum Indoor Air Quality Performance

D.

Indoor Environmental Quality Credit, Acoustic Performance

Buy Now
Questions 75

Which of the following strategies would be considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection?

Options:

A.

Build a two-story fitness facility

B.

Change the grade to install a security fence

C.

Provide a vehicular access drive that is less than 16 ft. (5 m) in width

D.

Remove trees that are less than 6 inches (15.24 cm) diameter at breast height

Buy Now
Questions 76

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

Options:

A.

Energy Modeler and Contractor

B.

Construction Manager and Energy Modeler

C.

Energy Modeler and Commissioning (Cx) Agent

D.

Commissioning (Cx) Agent and Facilities Manager

Buy Now
Questions 77

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project. Which of the following should remain the same for both the baseline building and the proposed building?

Options:

A.

Building operating schedule and occupancy hours

B.

Building operating schedule and total window area

C.

Building envelope construction and occupancy hours

D.

Total window area and building envelope construction

Buy Now
Questions 78

What issue must be present on the project site to achieve Location and Transportation Credit, High-Priority Site, Option 3. Brownfield Remediation?

Options:

A.

Mercury containing lamps

B.

Contaminated soil or groundwater

C.

Asphalt construction waste

D.

Asbestos tile and glue

Buy Now
Questions 79

While working on a 12,000 ft² (1,114.8 m²) medical building, a LEED AP asks the flooring manufacturer to submit the Environmental Product Declaration (EPD) for the flooring specified. The manufacturer doesn ' t have an EPD for their products, but all products meet ISO 14040/44 for Life Cycle Assessment (LCA). They ask if it would be acceptable to send the ISO 14040/44 LCA information in lieu of an EPD. How do you respond?

Options:

A.

Contact another manufacturer that has a comparable product with an EPD

B.

Exclude the flooring from the LEED credit as non-compliant

C.

Request recycled content information, as the ISO 14040/44 LCA is not sufficient for compliance

D.

Use the ISO 14040/44 LCA information just like an EPD to complete the documentation for the LEED credit

Buy Now
Questions 80

Which site preparation and construction method contributes to earning the Materials and Resources Credit, Construction and Demolition Waste Management?

Options:

A.

Reuse excavated soil and land-clearing debris

B.

Implement in situ soil remediation and post removal of the existing concrete pavement

C.

Salvage and recycle 50% of the existing materials (based on volume) generated during site demolition for three material streams

D.

Ensure reduction of pollution from construction activities by using airborne dust generation capture systems

Buy Now
Questions 81

For a task chair purchased for a healthcare facility, which portion of the product contributes toward Materials and Resources Credit, Furniture and Medical Furnishings?

Options:

A.

Wheels, 4% of product by weight, that do not contain lead, mercury, cadmium or antimony

B.

Fabric, 5% of product by weight, with stain resistant treatment containing Perfluorinated Compounds (PFCs)

C.

Metal base, 20% of product by weight, which do not contain heavy metals and is not plated with hexavalent chromium

D.

Plastic armrests, 30% of product by weight, with added antimicrobial treatment

Buy Now
Questions 82

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Options:

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

Buy Now
Questions 83

For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

Options:

A.

verification that a weighted daily average has been used for each qualifying route

B.

confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop

C.

verification that a weighted building average has been used for each qualifying functional entry

D.

confirmation that each qualifying route features paired route service (service in opposite directions)

Buy Now
Questions 84

U.S. Green Building Council (USGBC) ' s vision for using LEED internationally includes

Options:

A.

allowing more stringent credit requirements for countries outside of the U.S. so that all projects can achieve LEED

B.

creating multiple LEED rating systems for different countries

C.

modifying U.S. reference standards, such as ASHRAE 90.1, to be more appropriate for regions outside the U.S.

D.

providing opportunities for alternative compliance paths that meet the unique needs of a particular region

Buy Now
Questions 85

What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Options:

A.

One

B.

Two

C.

Four

D.

Six

Buy Now
Questions 86

In order to achieve the requirements of LEED, the Electrical Vehicle Supply Equipment (EVSE) must comply with:

Options:

A.

State, but not regional standards established for electrical vehicles operated within the state of vehicle operation

B.

Regional, state, or local standards for the electrical connectors to be used

C.

Level 1 charging capacity (110 volts AC)

D.

Manufacturer ' s standards established for electrical vehicles operated within the state of vehicle primary operation

Buy Now
Questions 87

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner ' s Project Requirements (OPR)?

Options:

A.

All applicable codes and standards

B.

Interior finishes related to the project

C.

All project team members and applicable roles

D.

Energy efficiency goals and training requirements

Buy Now
Questions 88

The Lakeside Resort is a hotel in a rural area located about 60 mi. (96.6 km) from the nearest town, which has a population of 10,500. There are no other towns for over 200 mi. (321.9 km). The surrounding community is largely made up of ranches and federal- and state-owned land.

The project consists of a single building that includes 150 guest rooms, a small restaurant, an indoor pool, conference spaces, event spaces, and six tenant spaces. A lease has been secured for a future spa, gift shop, coffee shop, and tour operator. Two tenant spaces have not yet been leased. The 10-acre property is adjacent to a lake and provides trail access to public lands.

When drawing the LEED boundary for this project, the project team should include all:

Options:

A.

Of the development footprint (parking lots, building, sidewalks, and paths around the property) plus the land extending 100 ft. from the development footprint

B.

Land associated with the project and adjacent areas that include attractions occupants are expected to use

C.

Contiguous land that is associated with the project and supports its typical operations

Buy Now
Questions 89

A project team wants to educate the facility manager on the installed building systems to improve Indoor Environmental Quality. They want the facility manager to maintain the systems so that they will continue to function as intended. Which of the following should be provided to the facility manager?

Options:

A.

Vendor invoices for mechanical equipment

B.

Preventive maintenance plan for the building

C.

As-built drawings and copies of material submittals

D.

A copy of the credit documentation for the credits that were approved by Green Business Certification Inc. (GBCI)

Buy Now
Questions 90

The design team for a school project finds that they can achieve an 18% savings in indoor water use from the baseline. If the team adds a rainwater harvesting system that reduces water use by another 10%, they can earn:

Options:

A.

Zero points because they have not fulfilled the Water Efficiency Prerequisite, Indoor Water Use Reduction

B.

Only the Water Efficiency Prerequisite, Indoor Water Use Reduction

C.

Two points for Water Efficiency Credit, Indoor Water Use Reduction

D.

One or two points for Water Efficiency Credit, Indoor Water Use Reduction depending on the type of metering installed

Buy Now
Questions 91

A real estate development company plans to build a mixed-use facility in an urban area. Which of the following strategies should the developer implement to support the local economy?

Options:

A.

Provide location-efficient affordable housing

B.

Provide workforce training

C.

Employ individuals from the local community

Buy Now
Questions 92

In the context of biophilic design, providing access to outdoor views contributes to enhancing occupant quality of life because doing so:

Options:

A.

Reduces indoor air pollutants by acting as a natural ventilator through improved air exchange

B.

Helps improve concentration and cognitive function by offering a visual connection to natural elements

C.

Promotes thermal comfort by allowing occupants to visually gauge outdoor weather conditions

Buy Now
Questions 93

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Options:

A.

The general contractor

B.

A LEED AP

C.

The project ' s mechanical engineer

D.

The owner or an owner ' s representative

Buy Now
Questions 94

What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

    Energy and Atmosphere Credit, Demand Response

    Energy and Atmosphere Credit, Advanced Energy Metering

    Energy and Atmosphere Credit, Building Level Energy Metering

Options:

A.

Energy and Atmosphere Credit, Green Power and Carbon Offsets

Buy Now
Questions 95

The results of a building energy model show that a building will consume 2,200,435 kilowatt-hours (kWh) per year (building is served solely by electricity). The building owner wants to achieve Energy and Atmosphere Credit, Green Power and Carbon Offsets. What is the minimum amount of green energy required to be purchased on an annual basis?

Options:

A.

770,152 kWh

B.

2,200,435 kWh

C.

550,109 kWh

D.

1,100,218 kWh

Buy Now
Questions 96

Under LTc3: Compact and Connected Development, Option 1. Surrounding Density, how far from the project site should project teams measure surrounding density?

Options:

A.

0.5 mi. (0.80 km)

B.

1 mi. (1.61 km)

C.

0.25 mi. (0.40 km)

Buy Now
Questions 97

A project team is planning a new office building in a cold climate. The team aims to achieve significant reductions in peak thermal loads. Which strategy should it apply to minimise peak thermal loads associated with infiltration?

Options:

A.

Increase wall-insulation thickness

B.

Install high-performance windows with low-emissivity coatings

C.

Seal potential air-leakage points and openings

Buy Now
Questions 98

Which of the following strategies under LTc2: Equitable Development, Option 3: Equitable Construction helps achieve the goal of enhancing the economic and social vitality of a community?

Options:

A.

Providing job-related skills training through a registered apprenticeship program

B.

Establishing affordable housing units within the project

C.

Engaging local business owners in the project design process

Buy Now
Questions 99

A consultant specifies the required U-value, solar heat gain coefficient, and visible light transmittance for a project. What type of building envelope assembly would require these attributes?

Options:

A.

Floors

B.

Roofs

C.

Walls

D.

Windows

Buy Now
Questions 100

A project has a potable water source as well as two alternative water sources. Which of the following statements is applicable for a project using two alternative water sources?

Options:

A.

A project may not use two alternative water sources

B.

Target the uses that require the least treatment first

C.

Match uses by location: indoor sources to indoor uses, outdoor sources to outdoor uses

D.

All alternative water sources should be treated to potable water standards

Buy Now
Questions 101

A rectangular office building is located in an extremely humid climate and is shaded by very large adjacent buildings

on all four sides. If the building owner wants to decrease the annual energy cost for operating the building, which of

the following would be the best design approach?

Options:

A.

Install glazing with a higher solar heat gain factor

B.

Install photovoltaic panels on the sides of the building

C.

Increase outdoor air intake quantities during summer months

D.

Recover waste energy through exhaust air energy recovery systems

Buy Now
Questions 102

An owner has insisted on using a non-native or non-adapted plant species on both the vegetated roof and ground level. What Sustainable Sites credit will this decision impact the most?

Options:

A.

Site Assessment

B.

Site Development - Protect or Restore Habitat

C.

Heat Island Reduction

D.

Light Pollution Reduction

Buy Now
Questions 103

Which of these is a method to assess the regional context of a building ' s design for sustainability?

Options:

A.

Conducting a site analysis

B.

Consulting with neighbors

C.

Improving a design threshold

D.

Performing an energy analysis of the building

Buy Now
Questions 104

A contractor wants to use an adhesive that exceeds the allowed Volatile Organic Compound (VOC) content limit under Indoor Environmental Quality Credit, Low Emitting Materials. This credit can be earned if

Options:

A.

the VOC budget method is applied for VOC content

B.

the adhesive is not included in the LEED documentation

C.

75% of the adhesives used comply with the VOC content limit and emissions requirements

D.

95% of the adhesives used comply with the VOC content limit and emissions requirements

Buy Now
Questions 105

An electrical team installs photovoltaic panels over a parking lot. This action contributes to which of the following credits?

Options:

A.

Optimize Energy Performance

B.

Light Pollution Reduction

C.

Low-Emitting Materials

D.

Demand Response

Buy Now
Questions 106

In order to achieve Indoor Environmental Quality Credit, Quality Views the project team increased the window-to-wall

ratio. Which prerequisite was impacted by this action?

Options:

A.

Energy and Atmosphere Prerequisite, Minimum Energy Performance

B.

Energy and Atmosphere Prerequisite, Building-Level Energy Metering

C.

Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management

D.

Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification

Buy Now
Questions 107

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced

Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

Options:

A.

Verify that training requirements are completed

B.

Develop systems manual for the commissioned systems

C.

Review contractor submittals for the commissioned systems

D.

Verify installation and performance of the commissioned systems

Buy Now
Questions 108

Innovation credits for exemplary performance can be awarded for

Options:

A.

achieving one pilot credit

B.

achieving double the credit requirements

C.

demonstrating significant environmental benefits

D.

demonstrating a qualitative improvement in environmental performance

Buy Now
Questions 109

Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?

Options:

A.

LEED Building Design and Construction: Healthcare has no Water Efficiency Credit, Cooling Tower Water Use

B.

LEED Building Design and Construction: New Construction has no Water Efficiency Credit, Cooling Tower Water Use

C.

LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

D.

LEED Building Design and Construction: New Construction has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

Buy Now
Questions 110

Which of the following scenarios contributes to earning credit under MRc1: Materials and Resources, Option 2. Materials Reuse?

Options:

A.

Donate salvaged wood to a local nonprofit organisation that repurposes materials

B.

Reuse salvaged metal beams in the construction of the new project

C.

Sell recovered bricks to a salvage retailer for off-site reuse

Buy Now
Questions 111

Which of the following strategies can increase the climate resilience of a project during site-specific natural hazard events?

Options:

A.

Enhancing roof insulation

B.

Utilizing drought-tolerant landscaping

C.

Increasing indoor ventilation rates

Buy Now
Questions 112

In new construction projects, EQc4: Resilient Spaces allows designs to earn points from which of the following management modes?

Options:

A.

Seismic risks

B.

Hurricane and tornado risks

C.

Infection risks

Buy Now
Questions 113

A neighborhood housing development organization has dual goals, promoting occupant ' s health and minimizing

energy costs. What LEED Building Design and Construction, New Construction credit might the LEED AP propose to best achieve the organization ' s dual goals?

Options:

A.

Location and Transportation Credit, Access to Quality Transit

B.

Energy and Atmosphere Credit, Optimize Energy Performance

C.

Indoor Environmental Quality Credit, Low Emitting Materials

D.

Indoor Environmental Quality Credit, Daylight

Buy Now
Questions 114

A project is designed to remodel an existing warehouse into multi-family housing. The exterior facade of the warehouse will remain, but 40% of the interior will be demolished and replaced for interior new construction. New materials will be used for the new construction. To achieve points in the Materials and Resources Credit, Building Life-Cycle Impact Reduction, which credit path option would apply?

Options:

A.

Historic Building Reuse

B.

Building and Material Reuse

C.

Whole-Building Life-Cycle Assessment

D.

Renovation of Abandoned or Blighted Building

Buy Now
Questions 115

An owner has insisted on using a non-native or non-adapted plant species on both the vegetated roof and ground level. What Sustainable Sites credit will this decision impact the most?

Options:

A.

Site Development-Protect or Restore Habita

B.

Site Assessment

C.

Heat Island Reduction

D.

Light Pollution Reduction

Buy Now
Questions 116

A project team member has prepared a map and accompanying table as documentation for the Location and Transportation Credit. Surrounding Density and Diverse Uses. Option 2. Diverse Uses. The map includes the location of each diverse use. the location of the project and the main entrance of the building. The table includes the distance to each use. the name of each use and the category of each use The team lead reviews the documentation and notes an important missing item. Which of the following is the most important item to add to the documentation?

Options:

A.

A description of each use

B.

The location of parking lots near each use

C.

Walking routes from the project to each use

D.

A calculation of the expected number of project occupants who will visit each use

Buy Now
Questions 117

Which of the following management measures is used to minimize the spread of infection in indoor environments?

Options:

A.

Promote natural ventilation in maintenance areas

B.

Monitor and adjust indoor humidity levels only for occupant comfort

C.

Implement regular air-filtration system inspections and maintenance

Buy Now
Questions 118

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

Options:

A.

Two Level (on, off)

B.

Three Level (on, 25%, off)

C.

Three Level (on, 50%, off)

D.

Three Level (on, 75%, off)

Buy Now
Questions 119

An office building design has demonstrated reductions in landscape water use of 30% over baseline and indoor water use of 40%. These reductions qualify the project for:

Options:

A.

Four points for Water Efficiency Credit, Indoor Water Use Reduction

B.

Zero points because the Water Efficiency Prerequisites are not met

C.

One point for Water Efficiency Credit, Outdoor Water Use Reduction

D.

One point for Water Efficiency Credit, Outdoor Water Use Reduction and four points for Water Efficiency Credit, Indoor Water Use Reduction

Buy Now
Questions 120

A project team is designing an office building and wants to ensure thermal comfort for occupants, especially in naturally conditioned spaces. How should the design team enhance thermal comfort in the naturally conditioned areas?

Options:

A.

Introduce radiant heating panels

B.

Increase air speed

C.

Use low-emissivity windows

Buy Now
Questions 121

A request to change the lighting fixtures in a conference room is made by a tenant. Which of the following credit scorecard changes will be directly and indirectly impacted by the change in lighting fixtures?

Options:

A.

Indoor Environmental Quality Credit, Interior Lighting and Sustainable Sites Credit, Light Pollution Reduction

B.

Energy and Atmosphere Credit, Optimize Energy Performance and Indoor Environmental Quality Credit, Interior Lighting

C.

Energy and Atmosphere Credit, Advanced Energy Metering and Indoor Environmental Quality Credit, Daylight

D.

Indoor Environmental Quality Credit, Thermal Comfort and Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies

Buy Now
Questions 122

A project pursuing LEED BD+C certification is designed with an electric air-source heat pump as the primary heating system to meet EAp1: Operational Carbon Projection and Decarbonization Plan. However, the client is considering adding a small natural-gas boiler for backup heating during extreme weather.

To earn maximum points under EAp1 while maintaining heating-system reliability, what should the LEED AP recommend regarding supplemental heating?

Options:

A.

Design an all-electric supplemental heating system using electric-resistance elements or auxiliary heat-pump capacity to eliminate on-site fossil-fuel combustion

B.

Install a natural-gas boiler with automated controls that limit operation to extreme conditions and include provisions for future conversion to an all-electric system

C.

Implement a wood-pellet biomass boiler as secondary heating because it qualifies as carbon-neutral without penalizing on-site combustion

Buy Now
Questions 123

The owner of a large multi-building property is seeking LEED certification. In determining the LEED project boundaries the LEED AP may include non-contiguous parcels of land if

Options:

A.

the parcels are used for temporary uses such as parking or staging that is owned and managed by a third party

B.

the parcels directly support or are associated with normal building operations and are accessible to the project ' s occupants

C.

the parcels are part of an existing public preservation easement or resource protection area that is directly adjacent to the LEED project boundary

D.

the parcels are part of a land trust or conservation organization for which the LEED project provides financial support for in the Sustainable Sites Credit, Site Development Credit, Protect or Restore Habitat, Option 2. Financial Support

Buy Now
Questions 124

When planning a water-efficient landscape design, the designer should consider including

Options:

A.

potable water

B.

sprinkler system

C.

native vegetation

D.

permeable pavement

Buy Now
Questions 125

When considering the Indoor Environmental Quality Credit, Thermal Comfort, what is the minimum percentage of building occupants that must have individual comfort controls?

Options:

A.

10%

B.

25%

C.

50%

D.

75%

Buy Now
Questions 126

In the calculations for Water Efficiency Credit, Outdoor Water Use Reduction, food gardens

Options:

A.

must be calculated using at least 20% from an alternative water source

B.

must be calculated using 100% potable water

C.

may be included or excluded from the calculations

D.

may be calculated using a standard 20% reduction from baseline

Buy Now
Questions 127

Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

Options:

A.

A standard garbage disposal

B.

Electronic submeter at the domestic water supply pipe to the building

C.

An open-loop HVAC system that discharges potable cooling water to a nearby lake

D.

Commercial dishwasher that is ENERGY STAR® labeled or performance equivalent

Buy Now
Questions 128

Which strategy can maximize the efficiency of water use in an irrigation system?

Options:

A.

Determine a set rate of irrigation and avoid adjustments

B.

Set the irrigation controllers on a timer

C.

Incorporate precipitation sensors with smart irrigation controllers

D.

Space irrigation sprinkler heads for overlapping coverage

Buy Now
Questions 129

Which federal agency designates Federal Renewal Community sites, which can be considered High Priority Sites for

project development?

Options:

A.

U.S. Internal Revenue Service

B.

U.S. Department of Agriculture

C.

U.S. Environmental Protection Agency

D.

U.S. Department of Housing and Urban Development

Buy Now
Questions 130

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

Options:

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission his own installations and share the results with the project owner

C.

The Cx agent for the project must conduct or oversee the Cx of the PV system

D.

The building ' s mechanical engineer should commission his own installations and share the results with the project owner

Buy Now
Questions 131

A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?

Options:

A.

Install a preferred drop-off lane for buses meeting the emission requirements

B.

Provide calculations showing that the average fleet bus meets the emission requirements

C.

Inventory the school fleet to develop and create a plan for all buses to meet the emission requirements

D.

Document that all buses serving the project achieve a minimum green score of 30 on the American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide

Buy Now
Questions 132

Which of the following filtration methods is recommended for an infection risk management mode to enhance indoor air quality (IAQ) in healthcare facilities?

Options:

A.

Activated carbon filtration

B.

Plate-and-frame filters

C.

Ultraviolet germicidal irradiation (UVGI)

Buy Now
Questions 133

One point can be achieved through Sustainable Sites Credit, Heat Island Reduction by providing:

Options:

A.

Preferred parking for green vehicles

B.

A minimum of 75% of parking spaces under cover

C.

Access to public transportation stops

D.

A roof with artificial turf grass

Buy Now
Questions 134

Which of the following criteria must a Commissioning Authority (CxA) comply with in order to meet the requirements of the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification of Building Energy Systems?

Options:

A.

Document commissioning authority experience for at least one building project

B.

Review the owner ' s project requirements (OPR) for project goals and expectations

C.

Be a part of the project ' s design and construction management team

D.

Report results, findings, and recommendations directly to the architect

Buy Now
Questions 135

Which of the following standards is used to perform a Whole-Building Life-Cycle Assessment to measure the Global Warming Potential of materials in LEED projects?

Options:

A.

ISO 50001:2018

B.

ISO 14044:2006

C.

ISO 21930:2017

Buy Now
Questions 136

A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

In addition to the vegetated terraces, the project team is considering installing a green roof with walkways, fountains, and seating areas for patients, visitors, and staff. If the project attempts SSc2: Accessible Outdoor Space, what percentage of the required outdoor space must be vegetated?

Options:

A.

20%

B.

25%

C.

30%

Buy Now
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED v5 AP BD+C)
Last Update: Nov 21, 2026
Questions: 454
LEED-AP-BD+C pdf

LEED-AP-BD+C PDF

$22.5  $89.99
LEED-AP-BD+C Engine

LEED-AP-BD+C Testing Engine

$28.75  $114.99
LEED-AP-BD+C PDF + Engine

LEED-AP-BD+C PDF + Testing Engine

$35  $139.99