A project manager has analyzed work performance information and identified alarming variances in the project deliverable. Which of the following would be the BEST response for the project manager?
Faced with a complex project with many stages, which of the following is the BEST action for the project manager to take?
A project manager needs to replace someone on the project team. Which of the following is the FIRST action they should take?
During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?
Monitoring and controlling project work is a control process function that spans from:
An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000.
Which of the following is the CPI of the project?
A project manager seeks to implement a change control system. Which of the following elements are essential for this system to be effective? (Select Three).
During a status meeting, a team member informs the project manager of a possible risk. Which of the following is the FIRST action the project manager should take?
Which of the following would require that the project risk register be updated?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
The project has been terminated. Which of the following should be conducted with the project team before they are released?
Which of the following are process groups in the project life cycle? (Select Three).
A project manager receives formal leadership authority from which of the following documents?
Which of the following tools would be used to determine the relationship between two changed variables?
Which of the following quality option costs BEST identifies the expense of inspecting deliverables to prevent flawed products from reaching the customer?
A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?
Several team members have criticized the project manager for requesting that they work overtime in order to complete a project on time. Which of the following steps should the project manager take to resolve the conflict?
A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
Refer to the attached Exhibit.
Which of the following dependencies is demonstrated between task 1 and task 2 in the following diagram?
Which of the following are components of an internal / external communication plan? (Select Two).
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
All of the following are taken into account when determining the critical path EXCEPT:
Which of the following represents the appropriate order of an effective change management process?
To ensure that project status meetings are effective and productive, the project manager should:
Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).
Which of the following components are included in a communication plan? (Select Two).
After identifying the activities in a work package, which of the following is the NEXT step that a project manager should complete?
A variance between the planned scheduled work and the actual work completed would initially be highlighted in which of the following performance statistics?
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
Which of the following are reasons why formal project closure is important? (Select Three).
The project manager has the MOST authority in which of the following organizational structures?
A project manager has just completed the work breakdown structure (WBS) with the project team. Which of the following would be used during activity sequencing?
A qualitative analysis identified a server crash as an internal project risk with a medium probability and high adverse impact to the project. The project manager decides to manage this risk by authorizing the purchase and installation of a tape backup unit for the server, to prevent the potential loss of documents. Which of the following risk response strategies was applied in this circumstance?
Which of the following is described when a company requires version control of project documents?
Work must be overlapped and completed in parallel rather than sequentially within the critical path in order to meet the end date of the project. Which of the following would be utilized?
By completing the lessons learned during project closure, the project manager can:
A manager and the head of engineering discuss a change to a major work package. After the meeting, the project manager contacts a third person and tells them to complete the paperwork to make the change. Who did the project manager contact?
A project manager is using a vendor with a fixed bid contract. The vendor would like to help out with other parts of the project.
Which of the following should the project manager do NEXT?
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
The frequency of measurement would be found in which of the following documents?
Which of the following activities would happen FIRST in procurement management?
The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?
Two employees will not work on the same project together. The project manager tells the employees to talk to their supervisors because the supervisors recommended they work together. This is an example of which of the following conflict resolution styles?
A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?
A key team member is performing poorly on a project. The project manager has verified that the team member knows the project expectations. The project manager has met repeatedly with this team member to outline expectations. Which of the following is the NEXT step the project manager should take to keep the project on schedule?
In pre-project setup, which of the following must be completed prior to validating a project?
The project manager needs to determine the relationship between two variables. Which of the following tools will the project manager use?