When reading books and watching recorded videos are used as a way to acquire skills and knowledge, which approach to competence development is typically being used?
You have been contracted to manage the user acceptance testing of a new reservation system for a travel agency. The reservation system is being developed by a third party. Detailed specifications are available, and an estimate of the total development effort exists. The system will be delivered in four agreed increments.
Which of the following estimation techniques would be most appropriate to use in this context?
Factors that are important to take into account when performing test estimation include:
i. The quality of the test basis
ii. The availability of test automation
iii. The amount of rework required
iv. The distribution of testing across several locations
The various factors can be grouped by characteristic. Examples of characteristics include:
Study the following characteristics:
Avoid re-inventing the wheel
Pool on experiences from earlier projects
They prompt thought in areas that are sometimes forgotten
Often used when compliance to specific standards is relevant
To which risk identification technique do these characteristics relate?
Which status would typically be assigned to a false-positive defect report during defect management?
For which type of testing would a test manager be involved with establishing benchmarks?
Which of the following characteristics of risk-based techniques is not appropriate to a more heavyweight risk-based technique?
To which category of cost of quality does "fixing a defect found during testing" belong?
A company that sells an established capture–replay execution tool is adding a test management tool. Same team, same technology, incremental development (V-model per increment), known first-year features; later features driven by customer demand.
Which two of the following factors are most likely to influence the estimation technique that would be selected in this scenario?
Following up on the situation, the team lacks drive and is performing tasks too slowly. You have been asked to recruit an extra person into the team. Which of the following team roles would be most appropriate to enhance the team?
Which of the following is not something you should do when performing a Belbin assessment with an Agile team?
Management is sceptical regarding the budget request (€25,000) for the next testing project. You are asked for a cost-benefit calculation. Based on historical data from several projects, you have come up with the following numbers:
Average prevention cost per defect: €200
Average cost of detection per defect: €400
Average cost of internal failure: €150
Average cost of external failure: €2,500
Expected number of defects to be found in this project during testing: 50
What is the result for the expected cost-benefit calculation for the upcoming project?