Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

Prince2-Foundation PRINCE2 Foundation Exam Questions and Answers

Questions 4

Which is one of the six aspects of project performance to be managed?

Options:

A.

Efficiency

B.

Timescales

C.

Estimate

D.

Work

Buy Now
Questions 5

What must be produced to meet the minimum requirements for applying the change theme?

Options:

A.

Documentation on the corrective action for an issue

B.

Details of the decisions taken on all issues

C.

Documentation on the version of each product

D.

Details of the status of all products being produced

Buy Now
Questions 6

Which is created during the Starting up a Project process?

Options:

A.

Project mandate

B.

Project management team role descriptions

C.

Communication Management Strategy

D.

Quality Register

Buy Now
Questions 7

Which is part of quality control?

Options:

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Buy Now
Questions 8

Which should be provided by corporate or programme management before the Starting up a Project process commences?

Options:

A.

A Project Brief

B.

Sufficient information to identify the prospective Executive

C.

The Project Initiation Documentation

D.

Authority to initiate a project

Buy Now
Questions 9

Which is a purpose of the business case theme?

Options:

A.

To identify which role is responsible for producing the business case

B.

To identify the project's outputs

C.

To establish the controls to manage changes that may impact the project benefits

D.

To establish a viable investment proposition

Buy Now
Questions 10

Which is a purpose of the plans theme?

Options:

A.

To identify, assess and control any potential changes to the baseline

B.

To establish the project's structure of accountability

C.

To assess and control uncertainty

D.

To understand whether the targets are achievable

Buy Now
Questions 11

Which process is used to define how baselines will be established and controlled?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Initiating a project

D.

Starting up a project

Buy Now
Questions 12

Which process monitors work that has been assigned to a team manager?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Buy Now
Questions 13

Identify the missing words in the following sentence.

The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

Options:

A.

change authority

B.

project assurance

C.

project support

D.

senior user

Buy Now
Questions 14

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To produce a team plan for the work to be assigned to a team manager

B.

To select and implement actions that will resolve deviations from a plan within tolerance

C.

To obtain approvals for products delivered in a work package

D.

To update a project plan to incorporate the actuals from a stage plan

Buy Now
Questions 15

What should be considered when defining the number of management stages in a project?

Options:

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Buy Now
Questions 16

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

Options:

A.

A description of the risk management procedure

B.

An explanation of the company's risk appetite

C.

The names of the assigned actionees for each risk

D.

Estimations of the likelihood and impact of risks

Buy Now
Questions 17

Why is a project brief produced?

Options:

A.

To act as a trigger for the 'starting up a project' process

B.

To record the how the project will communicate with its stakeholders

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the project board as a basis for reviewing the progress of a project

Buy Now
Questions 18

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

Options:

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Buy Now
Questions 19

Which is a minimum requirement for applying the business case theme?

Options:

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

Buy Now
Questions 20

Which is an objective of the Starting up a Project process?

Options:

A.

Identify who will be responsible for creating the Project Plan

B.

Agree how the project will be monitored and controlled after initiation

C.

Authorize the Project Manager to proceed with the initiation stage

D.

Agree how issues and changes will be identified, assessed and controlled

Buy Now
Questions 21

Which is a purpose of the 'managing a stage boundary' process?

Options:

A.

To enable the project board to approve the continuation of the project

B.

To exercise overall control over the project while delegating day-to-day management

C.

To assign work to be controlled by the team manager

D.

To define the work that needs to be done to deliver the project product

Buy Now
Questions 22

Which is a purpose of the Managing a Stage Boundary process?

Options:

A.

Provide the Project Board with sufficient information for approving the next stage

B.

Approve the next Stage Plan

C.

Review and close any risks and issues identified during the previous stage

D.

Control the link between the Project Manager and the Team Manager(s)

Buy Now
Questions 23

What is described as an organization's unique attitude towards risk taking

Options:

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Buy Now
Questions 24

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

Options:

A.

Enable the Project Board to decide whether or not to authorize the project

B.

Justify the continuing viability of the project

C.

Enable the Project Board to decide whether or not to authorize project closure

D.

Justify the initiation of a project

Buy Now
Questions 25

Which is a minimum requirement for applying the organization theme?

Options:

A.

Each member of the project management team must have a written role description

B.

The roles of the project management team must be combined, wherever possible

C.

The project manager must be appointed from the supplier organization

D.

The frequency of communication to the project's stakeholders must be documented

Buy Now
Questions 26

To meet the minimum requirements for applying the progress theme, what must be considered?

Options:

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Buy Now
Questions 27

Which describes a risk event?

Options:

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Buy Now
Questions 28

How does the project plan help to support the 'manage by stages' principle?

Options:

A.

By identifying the customer's quality expectations

B.

By defining products to ensure they are fit for purpose

C.

By identifying the major control points and milestones

D.

By estimating the timescales and costs of the project

Buy Now
Questions 29

Who represents the three project interests on a project?

Options:

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Buy Now
Questions 30

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 31

Where should decisions regarding the tailoring of the project be recorded?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Buy Now
Questions 32

Which is a factor when deciding the duration of a management stage?

Options:

A.

The work packages to be delivered

B.

The level of risk in the project

C.

The cost of the stage

D.

The number of products to be produced in the project

Buy Now
Questions 33

Which level of management sets the project level tolerances?

Options:

A.

Project board

B.

Team manager

C.

Corporate, programme management or the customer

D.

Project manager

Buy Now
Questions 34

Which is a purpose of the Risk theme?

Options:

A.

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place

B.

Establish a cost-effective procedure to identify, assess and control uncertainty

C.

Establish mechanisms to control any unacceptable deviations from plan

D.

Establish mechanisms to manage risks at the corporate or programme level of an organization

Buy Now
Questions 35

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Options:

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Buy Now
Questions 36

Which is a purpose of the Managing Product Delivery process?

Options:

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Buy Now
Questions 37

What takes place during the Closing a Project process?

Options:

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Buy Now
Questions 38

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Buy Now
Questions 39

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 40

Which product documents the information needed to demonstrate continued business justification?

Options:

A.

Business Case

B.

Communication Management Strategy

C.

Project Product Description

D.

Quality Management Strategy

Buy Now
Questions 41

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 42

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

Options:

A.

Principles

B.

Themes

C.

Processes

D.

Techniques

Buy Now
Questions 43

Which is NOT included in the PRINCE2 definition of a project?

Options:

A.

A project is a temporary organization

B.

A project's purpose is to deliver one or more business products

C.

A project is part of 'business as usual'

D.

A project is based on an agreed Business Case

Buy Now
Questions 44

Which is an objective of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Provide management control and direction

C.

Control the day-to-day running of the project

D.

Provide accurate progress information to the Project Manager

Buy Now
Questions 45

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Options:

A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Buy Now
Questions 46

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Buy Now
Questions 47

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Options:

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Buy Now
Questions 48

Which is one of the six aspects of project performance that needs to be managed?

Options:

A.

Progress

B.

Change

C.

Risk

D.

Security

Buy Now
Questions 49

Which is a purpose of a Lessons Log?

Options:

A.

Note any lessons that are raised in Checkpoint Reports

B.

Record that corrective action is being taken

C.

Escalate lessons to the Project Board

D.

Raise improvements with Project Assurance

Buy Now
Questions 50

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Buy Now
Questions 51

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Options:

A.

quality

B.

supplier

C.

risk

D.

product

Buy Now
Questions 52

Which does NOT reflect the PRINCE2 principle of continued business justification?

Options:

A.

There must be a justifiable reason for starting a project

B.

The business justification drives decision making

C.

If a project is no longer forecast to deliver a financial benefit, it should be stopped.

D.

If a project can no longer be justified, it should be stopped

Buy Now
Questions 53

Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

Options:

A.

define a coding system to provide a unique identifier for the products within

B.

summarize the results of the quality activities performed on

C.

provide a framework to design, develop and maintain

D.

define the project benefits to be achieved by each of

Buy Now
Questions 54

Which is part of quality control?

Options:

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Buy Now
Questions 55

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Buy Now
Questions 56

In what process is the authorization to deliver the project's products given?

Options:

A.

Starting up a Project

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Directing a Project

Buy Now
Questions 57

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Options:

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Buy Now
Questions 58

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Buy Now
Questions 59

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Buy Now
Questions 60

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

Options:

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Buy Now
Questions 61

Which is one of the three levels of plan in PRINCE2?

Options:

A.

Benefits Review Plan

B.

Programme Plan

C.

Team Plan

D.

Project Brief

Buy Now
Questions 62

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 63

Which is a true statement about acceptance criteria?

Options:

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Buy Now
Questions 64

Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

Options:

A.

Avoid

B.

Reduce

C.

Share

D.

Transfer

Buy Now
Questions 65

Which is a true statement about PRINCE2 event-driven controls?

Options:

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Buy Now
Questions 66

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

Options:

A.

controls

B.

products

C.

project management team

D.

stages

Buy Now
Questions 67

Which is a typical core activity within configuration management?

Options:

A.

Issue management

B.

Quality inspection

C.

Identification

D.

Preparation

Buy Now
Questions 68

Which is a benefit of using PRINCE2?

Options:

A.

Is a method specifically designed for technical projects

B.

Provides for the efficient and economic use of management time

C.

Includes many of the proven planning techniques, such as critical path analysis

D.

Can be used to manage both projects and programmes

Buy Now
Questions 69

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options:

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Buy Now
Questions 70

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

Options:

A.

a corporate

B.

a temporary

C.

an external

D.

a technical

Buy Now
Questions 71

Which principle helps to ensure that all changes to the outputs are agreed?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Buy Now
Questions 72

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

Options:

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Buy Now
Questions 73

What is a risk actionee responsible for?

Options:

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Buy Now
Questions 74

When is the 'managing a stage boundary' process used?

Options:

A.

Immediately alter the project board has authorized the previous stage

B.

Immediately after the project board has authorized the next stage

C.

Near the end of each stage

D.

Near the end of delivery stages

Buy Now
Questions 75

Which statement about applying the 'tailor to suit the project' principle is CORRECT?

Options:

A.

PRINCE2 can be tailored to be used with any type of project

B.

A technically complex project should NOT tailor PRINCE2

C.

The tailoring of PRINCE2 is MOST appropriate for agile projects

D.

A project which is part of a programme should NOT tailor PRINCE2

Buy Now
Questions 76

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

Options:

A.

One

B.

Two

C.

Three

D.

Six

Buy Now
Questions 77

What 15the purpose of the ‘progress! practice?

Options:

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Buy Now
Questions 78

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Buy Now
Questions 79

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Buy Now
Questions 80

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Buy Now
Questions 81

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

Options:

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

Buy Now
Questions 82

What is an advantage of dividing the project into stages?

Options:

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Buy Now
Questions 83

Which is an objective of the ‘directing a project’ process?

Options:

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Buy Now
Questions 84

Which are reasons for a benefits management approach?

1. To state how improvements will be measured

2. To confirm that the benefits are realized

3. To estimate the costs of improvement

4. To define the reason for delivering the improvement

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 85

Which process is used by the project board to respond to on exception report?

Options:

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Buy Now
Questions 86

What is documented in the project plan to support the 'manage by exception' principle?

Options:

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Buy Now
Questions 87

Why is it necessary to apply the 'defined roles and responsibilities' principle?

Options:

A.

Because the people involved in a project should know what is expected of them

B.

Because the project management team should be cross-functional

C.

Because the user and supplier interests should be involved on a need-to-know basis

D.

Because the project manager should represent all the stakeholders of the project

Buy Now
Questions 88

Which is a benefit of using PRINCE2?

Options:

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Buy Now
Questions 89

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Buy Now
Questions 90

Which is a minimum requirement for applying the 'change' theme?

Options:

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications

Buy Now
Questions 91

Which is an objective of the 'directing a project' process?

Options:

A.

To create the plan to deliver the project product

B.

To select and appoint the project manager

C.

To design the project management team roles

D.

To give authority to deliver the project product

Buy Now
Questions 92

Which process has the objective of confirming that acceptance criteria have been met?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Buy Now
Questions 93

Which process provides information for the project board to review an updated project plan?

Options:

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 94

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?

Options:

A.

Business case

B.

Plans

C.

Change

D.

Progress

Buy Now
Questions 95

Which statement describes the context of the 'initiating a project" process?

Options:

A.

The project is viewed from the perspective of the project board in this process

B.

This process should result in key stakeholders being committed to the project

C.

This process is triggered by the assembly of the project brief

D.

The 'controlling a stage' process will start immediately after this process

Buy Now
Questions 96

Which is a purpose of a quality register?

Options:

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

Buy Now
Questions 97

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 98

During the ‘initiating a project’ process, who specifies the required level of management control?

Options:

A.

Corporate, programme management or customer

B.

Project board

C.

Project manager

D.

Project assurance

Buy Now
Questions 99

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Buy Now
Questions 100

Which management level should approve a course of action if project-level tolerance is exceeded?

Options:

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 101

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 102

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Buy Now
Questions 103

What is an advantage of applying the 'manage by stages' principle?

Options:

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Buy Now
Questions 104

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Buy Now
Questions 105

What is a purpose of the communication management approach?

Options:

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

Buy Now
Questions 106

Which describes user's quality expectations?

Options:

A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

Buy Now
Questions 107

Which is a description of a purpose of the communication management approach?

Options:

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Buy Now
Questions 108

Which TWO are objectives of the 'closing a project’ process?

1. To confirm to the project board that each stage’s products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 109

When is a work breakdown structure MOST useful?

Options:

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Buy Now
Questions 110

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

Options:

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

Buy Now
Questions 111

Which plan should only be produced if the project is large and complex enough?

Options:

A.

Project plan

B.

Stags plan

C.

Team plan

D.

Exception plan

Buy Now
Questions 112

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

Options:

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Buy Now
Questions 113

What is a purpose of the ‘organizing practice?

Options:

A.

To define who is responsible for which project activities

B.

To compare the team's actual achievements against the team plan

C.

Ta understand what the users require of the project

D.

To assess modifications raised by team members

Buy Now
Questions 114

Which common project context relates to the need to engage with external suppliers to deliver part of the project?

Options:

A.

Commercial

B.

Delivery method

C.

Organizational

D.

Scale

Buy Now
Questions 115

The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

Options:

A.

The business objectives

B.

The business’ existing governance practices

C.

The project's delivery method

D.

The ways of working used on previous projects

Buy Now
Questions 116

Which is the BEST reason for a PRINCE? project to have at least two stages?

Options:

A.

It enables the project team to close the project in an orderly fashion

B.

it enables the project board to decide whether to proceed with the delivery of the project product

C.

It enables the project team to change the scope of the project by agreeing the impact on the business case

D.

It enables the project board to approve the appointment of external contractors, when required

Buy Now
Questions 117

Which control is time-driven?

Options:

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Buy Now
Questions 118

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

Options:

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Buy Now
Questions 119

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

Options:

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Buy Now
Questions 120

Which term is defined as the means by which an organization transitions to a desired future state?

Options:

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Buy Now
Questions 121

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Buy Now
Questions 122

According to the guidance for effective quality management, when should the requirements for a product be captured?

Options:

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Buy Now
Questions 123

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 124

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 125

When does the ‘directing a project’ process start?

Options:

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Buy Now
Questions 126

Which is a feature of PRINCE2?

Options:

A.

It is naturally right=sized to the scale of every project

B.

It promotes improving processes for every project

C.

It replaces the need to apply specialist Industry-specific lifecycles

D.

It focuses on completing the project on time as its main objective

Buy Now
Questions 127

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Buy Now
Questions 128

Which is a definition of management?

Options:

A.

Instructing the execution of tasks in line with agreed ways of working

B.

Translating stakeholder requirements into quality criteria

C.

Assigning people with specific skills and capabilities to work on multiple projects

D.

Defining, assuring, and accepting products back into the business

Buy Now
Questions 129

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 130

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

Options:

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Buy Now
Questions 131

What is the BEST reason to perform the risk practice?

Options:

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Buy Now
Questions 132

In which process are the key decisions to control the project made?

Options:

A.

Directing a project

B.

Initiating a project

C.

Managing a stage boundary

D.

Controlling a stage

Buy Now
Questions 133

Which statement describes a purpose of the 'starting up a project’ process?

Options:

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Buy Now
Questions 134

Which feature of a stage plan suggests that a project is in danger of scope creep?

Options:

A.

Stage plans are prepared by the project manager as the stage comes to an end

B.

Products identified in a stage plan cannot be traced back to the project plan

C.

The team delivering the stage plan includes staff from different parts of an organization

D.

it is not possible to implement remedial actions for an exception by updating a stage plan

Buy Now
Questions 135

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Buy Now
Questions 136

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Buy Now
Questions 137

Which should provide guidance on how and when prototyping is to be used?

Options:

A.

Product description

B.

Quality management approach

C.

Quality register

D.

Sustainability management approach

Buy Now
Questions 138

The project manager reviews the project product description to identify the detailed requirement for each product.

In which step of the quality management technique should the project manager do this review?

Options:

A.

Gathering user inputs

B.

Accepting products ay

C.

Describing the quality management approach

D.

Controlling quality

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 Foundation Exam
Last Update: May 3, 2024
Questions: 461
Prince2-Foundation pdf

Prince2-Foundation PDF

$28  $80
Prince2-Foundation Engine

Prince2-Foundation Testing Engine

$33.25  $95
Prince2-Foundation PDF + Engine

Prince2-Foundation PDF + Testing Engine

$45.5  $130