What must be produced to meet the minimum requirements for applying the change theme?
Which should be provided by corporate or programme management before the Starting up a Project process commences?
Which process is used to define how baselines will be established and controlled?
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
What should be considered when defining the number of management stages in a project?
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
To meet the minimum requirements for applying the progress theme, what must be considered?
Which process provides information for the project board to review a completed stage and confirm continued business justification?
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Which product documents the information needed to demonstrate continued business justification?
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Which is one of the six aspects of project performance that needs to be managed?
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
Which does NOT reflect the PRINCE2 principle of continued business justification?
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
The project manager reviews whether there has been a Change in the way team members relate to each other.
Which principle is the project manager applying as part of the 'people' element?
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
What is a goal of the 'implement' step within the recommended risk management procedure?
How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement
What is documented in the project plan to support the 'manage by exception' principle?
Why is it necessary to apply the 'defined roles and responsibilities' principle?
Which process has the objective of confirming that acceptance criteria have been met?
Which process provides information for the project board to review an updated project plan?
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits
During the ‘initiating a project’ process, who specifies the required level of management control?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
Which management level should approve a course of action if project-level tolerance is exceeded?
Which TWO are objectives of the ‘controlling a stage process?
1. To focus attention on achieving Work Within) the agree tolerances
2. To create follow on action recommendations for all open issues and risks
3. To understand how the quality required will be achieved
4. To ensure that the stage’s products meet-agreed quality expectations
What statement describes how the project manager should ensure effective communication within a project?
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?
Which plan should only be produced if the project is large and complex enough?
The project manager needs to know whether the response to a threat to the project has been actioned.
Which should the project manager review?
Which common project context relates to the need to engage with external suppliers to deliver part of the project?
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
The project manager needs to record what will make file Users satisfied with the final product
Where should the project manager record this?
Which term is defined as the means by which an organization transitions to a desired future state?
According to the guidance for effective quality management, when should the requirements for a product be captured?
The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.
In which process should the project manager define this information?
in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.
Which management product should the project manager produce?
Which feature of a stage plan suggests that a project is in danger of scope creep?
According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?
Identify the missing ward in the following sentence.
PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.
The project manager reviews the project product description to identify the detailed requirement for each product.
In which step of the quality management technique should the project manager do this review?