PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Questions and Answers

Questions 4

In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because the primary responsibility for improving team morale and overall productivity rests with each individual team manager, not the project manager

B.

Yes, because requiring team managers to attend regular coordination meetings diverts their time away from completing their work packages, thereby risking further delays

C.

No, because the project manager should create mechanisms that strengthen coordination and relationships across the project team

D.

No, because the project manager should formally escalate the missed work package deadlines to the project board via an exception report rather than attempting to resolve the issue through coordination meetings

Buy Now
Questions 5

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

Buy Now
Questions 6

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Buy Now
Questions 7

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion

B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process

C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work

D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio

Buy Now
Questions 8

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

Options:

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Buy Now
Questions 9

A product description contains only the following quality specification for the car-parking component: “The shopping centre will include an underground car park.”

Is this an effective application of the quality practice, and why?

Options:

A.

Yes, because confirming that a car park exists completely specifies its required quality

B.

Yes, because the statement provides sufficient information to confirm whether the required component has been delivered

C.

No, because all details of the car park should be recorded only in the quality management approach

D.

No, because the product description needs sufficiently detailed, measurable quality specifications and tolerances to support planning and verification

Buy Now
Questions 10

At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.

During which ‘controlling a stage’ activity should this instruction be given?

Options:

A.

Authorize a work package

B.

Evaluate work package status

C.

Capture issues and risks

D.

Take corrective action

Buy Now
Questions 11

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?

Options:

A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue

B.

Yes, because the project manager may dismiss an informally raised concern without further investigation

C.

No, because the project manager should assess an informally raised concern before deciding what action to take

D.

No, because the team manager should report the concern only in the next scheduled checkpoint report

Buy Now
Questions 12

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Buy Now
Questions 13

While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.

Is this an appropriate application of the risk practice, and why?

Options:

A.

Yes, because the contextual statement is itself a complete set of cause-event-effect risk descriptions

B.

Yes, because understanding the project’s context and objectives is necessary to design a risk management approach

C.

No, because risk responses must be selected before the risk management approach can be fully prepared

D.

No, because project objectives should not influence how risk is managed

Buy Now
Questions 14

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Buy Now
Questions 15

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

Options:

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

Buy Now
Questions 16

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

Options:

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 3, 2026
Questions: 56
PRINCE2-7-Practitioner pdf

PRINCE2-7-Practitioner PDF

$21.25  $84.99
PRINCE2-7-Practitioner Engine

PRINCE2-7-Practitioner Testing Engine

$25  $99.99
PRINCE2-7-Practitioner PDF + Engine

PRINCE2-7-Practitioner PDF + Testing Engine

$33.75  $134.99