Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

In reviewing the team ' s identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project ' s incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.

Exploit

B.

Accept

C.

Share

D.

Enhance 

Buy Now
Questions 5

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W & S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Buy Now
Questions 6

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.

Accept actively

B.

Mitigate

C.

Accept passively

D.

Share

Buy Now
Questions 7

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.

What should the risk management team leader do in the early stages of the project?

Options:

A.

Conduct qualitative risk analysis to prioritize potential risks.

B.

Plan a solid risk response plan and secure the necessary funding.

C.

Educate stakeholders on best practices to perform risk management.

D.

Benchmark to an organization which has executed a similar project,

Buy Now
Questions 8

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Buy Now
Questions 9

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.

Activity 3.2

B.

Activity 2.3

C.

Activity 3.5

D.

Activity 1.2

Buy Now
Questions 10

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Options:

A.

Study the change logs to implement the approved change requests.

B.

Close out the expired risk and update the relevant project documents.

C.

Get permission from stakeholders before documenting lessons learned.

D.

Continue monitoring the critical response plan on the delivered product.

Buy Now
Questions 11

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis 

Buy Now
Questions 12

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders ' ?

Options:

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

Buy Now
Questions 13

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Buy Now
Questions 14

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.

B.

Review the effectiveness of the risk process.

C.

Update the risk management plan.

D.

Escalate the project risks to upper management. 

Buy Now
Questions 15

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk ' s status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register. 

Buy Now
Questions 16

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Buy Now
Questions 17

A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project ' s midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 18

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Buy Now
Questions 19

A project manager was informed that the testing of the latest component in the project ' s software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.

Add contingencies to other tasks to mitigate similar risks.

B.

Reassess risks with a new assumptions and constraints analysis.

C.

Review the risk response plan looking for lessons learned.

D.

Log the event in the issue log and update the project management plan.

Buy Now
Questions 20

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.

Import a risk register from other industry chemical laboratories.

B.

Define chemical laboratory safety risk thresholds.

C.

Review published operational experience reports.

D.

Draft threat and opportunity risks that come to mind.

Buy Now
Questions 21

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.

Combine individual and focus groups to identify risks and create the overall risk register.

B.

Use focus groups to conduct group risk assessments of the project to identify risks.

C.

Request individual assessments of the project and its deliverables to identify risks.

D.

Use the external risk assessment of the project and its deliverables to identify risks.

Buy Now
Questions 22

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?

Options:

A.

Update the work breakdown structure (WBS).

B.

Analyze any potential impact.

C.

Escalate the issue to management.

D.

Add a new risk to the risk register.

Buy Now
Questions 23

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.

Include all stakeholders in the project ' s governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders ' tolerance.

D.

Consider stakeholders ' positions and opinions regarding the project’s output.

Buy Now
Questions 24

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.

Detailed work breakdown structure (WBS)

B.

Lessons learned from previous projects

C.

Baselines approved by the project team

D.

Actual data from the current project

Buy Now
Questions 25

During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.

What should the risk manager do?

Options:

A.

Assign a risk owner and develop the risk mitigations at the next scheduled risk meeting.

B.

Continue with the project as the risk identified is inconsequential.

C.

Assign risk responsibility to the project manager to determine how to proceed.

D.

Update the project stakeholders and seek their input on the resulting secondary risk.

Buy Now
Questions 26

A financial services company has implemented a risk response plan to mitigate potential cybersecurity threats. The project team has conducted a series of tests to ensure the new security measures are effective. However, some executives have expressed concerns about the impact of these measures on daily operations.

What should the risk manager do?

Options:

A.

Facilitate a risk identification session on security measures with the company executives.

B.

Organize a stakeholder workshop to discuss the effectiveness of the new security measures.

C.

Implement additional security measures to address the concerns expressed by the executives.

D.

Acknowledge the concerns and focus on monitoring the effectiveness of the new security measures.

Buy Now
Questions 27

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

Buy Now
Questions 28

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact 

Buy Now
Questions 29

A major data center initiative involves performing a sensitivity analysis to determine the center ' s required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor ' s advertised plans.

What should the risk manager do to quantify the risk?

Options:

A.

Initiate a 360-degree assessment.

B.

Consult environmental enterprise factors for benchmarks.

C.

Review organizational process assets for guidance.

D.

Consider leveraging the Delphi technique.

Buy Now
Questions 30

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.

What should the IT manager ' s role be in the project team meetings?

Options:

A.

The IT manager should be included as a risk owner.

B.

The IT manager should refine the project baseline plans.

C.

The IT manager should be added as a project sponsor.

D.

The IT manager should lead the infrastructure execution.

Buy Now
Questions 31

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

Options:

A.

Implement a strict, standardized approach to ensure consistency across all regions.

B.

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.

Adopt a fully flexible approach that allows teams to manage issues based on local context.

Buy Now
Questions 32

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Buy Now
Questions 33

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

Options:

A.

Major risk

B.

Residual risk

C.

Secondary risk

D.

Environment risk

Buy Now
Questions 34

A risk manager is facilitating a session to define a response to a critical risk. Stakeholders from several business units participate in the brainstorming, leading to a range of ideas for possible responses. However, the risk manager now needs to understand which solutions will be cost effective.

What should the risk manager do?

Options:

A.

Complete a comprehensive trend analysis.

B.

Validate assumptions and constraints analysis.

C.

Perform decision tree analysis.

D.

Conduct a variance analysis.

Buy Now
Questions 35

An agile project manager has noticed their team ' s declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Buy Now
Questions 36

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

Buy Now
Questions 37

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project ' s risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks 

Buy Now
Questions 38

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

B.

React to the secondary and residual risks only if they occur.

C.

Include secondary and residual risks as part of the response.

D.

Transfer secondary and residual risks to the project sponsor.

Buy Now
Questions 39

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options:

A.

Request a contingency reserve from management

B.

Arrange a team meeting, review the project ' s scope, and discuss dependency mapping

C.

Ensure participants review relevant documents before attending the meeting

D.

Ensure that all the relevant stakeholders participate

E.

Update the risk register during the team meeting.

Buy Now
Questions 40

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Questions 41

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 42

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Options:

A.

Review assumptions and constraints around risks.

B.

Develop the risk response plans for identified risks.

C.

Determine the likelihood and impact of the risks.

D.

Apply an iterative approach to risk identification.

Buy Now
Questions 43

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Options:

A.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

B.

Brainstorming technique

C.

Delphi technique

D.

Assumptions and constraints analysis

Buy Now
Questions 44

Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Buy Now
Questions 45

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Buy Now
Questions 46

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Buy Now
Questions 47

During the project ' s lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Buy Now
Questions 48

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Buy Now
Questions 49

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Questions 50

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Buy Now
Questions 51

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

Buy Now
Questions 52

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project ' s complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.

B.

Conduct the exercise with the key team members, excluding external stakeholders.

C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.

D.

Focus only on identifying the most obvious risks to save time and project resources.

Buy Now
Questions 53

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Buy Now
Questions 54

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

Buy Now
Questions 55

Which statement describes the risk portrayed on the risk matrix heat map below?

Options:

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Buy Now
Questions 56

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders ' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners. 

Buy Now
Questions 57

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Buy Now
Questions 58

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

Options:

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Buy Now
Questions 59

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Buy Now
Questions 60

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Buy Now
Questions 61

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?

Options:

A.

Concentrate on monitoring only high-visibility risks to conserve resources.

B.

Focus on tracking the risks identified at the project ' s start to maintain consistency.

C.

Reassess risk priorities carefully and update the risk register on a regular basis.

D.

Delegate all monitoring responsibilities entirely to individual team members for efficiency.

Buy Now
Questions 62

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

Options:

A.

Conduct risk workshops tailored to all stakeholders.

B.

Invite all stakeholders to daily coordination meetings.

C.

Distribute risk-policy documents to all stakeholders.

D.

Provide project management training to all stakeholders.

Buy Now
Questions 63

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

Options:

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

Buy Now
Questions 64

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

Options:

A.

Better schedule monitoring and controlling.

B.

Identify and analyze project plan assumptions.

C.

Have a detailed work breakdown structure (WBS).

D.

Use management reserves to cover delays.

Buy Now
Questions 65

A risk manager is overseeing the construction of a new office building and finds that some risks were underestimated in their impact on the project timeline and budget. The risk manager is reassessing the current risk levels to prevent further escalation.

Which two actions should the risk manager take? Choose two.

Options:

A.

Conduct a detailed risk audit to verify the accuracy of the risk assessments.

B.

Implement automation to track project risks in real time.

C.

Adjust risk priorities in the risk register based on the new assessment data.

D.

Facilitate a risk-planning workshop to select strategies for the high-priority risks.

E.

Reassess risk exposure using predictive analytics tools.

Buy Now
Questions 66

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Buy Now
Questions 67

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

Buy Now
Questions 68

During the planning phase of a construction project, the project manager is assessing the project environment for potential threats and opportunities, including market conditions, regulatory requirements, and technological changes. The risk manager is asked to support this assessment to ensure risks are consistently identified and analyzed.

What should the risk manager do?

Options:

A.

Coach the project manager on evaluating environmental factors using standard risk assessment techniques.

B.

Assign a specialized environmental expert to independently analyze external project factors separately.

C.

Collaborate with the project manager to define and apply appropriate risk analysis processes and tools.

D.

Recommend updating organizational process assets before completing the environmental risk assessment.

Buy Now
Questions 69

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Options:

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

Buy Now
Questions 70

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simul-ation

C.

The full risk description

D.

The risk response plan

Buy Now
Questions 71

A risk manager is working with a key project stakeholder who is concerned about the likelihood of quality issues such as product defects or process anomalies. The stakeholder has a low tolerance for any defects. The risk manager needs to tailor the risk management strategy to accommodate the stakeholder ' s risk appetite.

What should the risk manager do?

Options:

A.

Use Lean Six Sigma processes to ensure there are no defects.

B.

Request more funds in the risk reserve for defect management.

C.

Refine probability definitions to align with the stakeholder ' s risk tolerance.

D.

Conform to the stakeholder ' s risk tolerance levels by using Lean principles.

Buy Now
Questions 72

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Buy Now
Questions 73

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.

4 hours

B.

5 hours

C.

6 hours

D.

12 hours

Buy Now
Questions 74

During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier ' s delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Buy Now
Questions 75

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project ' s risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Buy Now
Questions 76

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:

A.

Risk thresholds

B.

Risk response strategies

C.

Risk management reports

D.

Risk breakdown structure (RBS)

Buy Now
Questions 77

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks ' severity, and update the risk register.

Buy Now
Questions 78

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.

B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.

C.

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.

D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.

E.

Focus attention and resources on identified risks with the highest potential to impact the project.

Buy Now
Questions 79

The customer expresses concern about the increasing likelihood of delays from one of the subcontractors on the project. This risk was previously identified and planned for during the project planning phase. The project sponsor reassured the customer that this is a known risk and will be handled accordingly by the risk manager.

What should the risk manager do?

Options:

A.

Call an emergency meeting.

B.

Reinforce the customer relationship.

C.

Implement the risk response plan.

D.

Escalate risk to the owner.

Buy Now
Questions 80

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Buy Now
Questions 81

A financial service firm adheres to heavily regulated compliance legislation. During the firm ' s latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project ' s risk management plan.

What is the organization ' s risk maturity level?

Options:

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Buy Now
Questions 82

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

Options:

A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.

B.

Engage with the team to enhance the project risk reports sent to the stakeholders.

C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.

D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.

Buy Now
Questions 83

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 84

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Buy Now
Questions 85

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented. 

Buy Now
Questions 86

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 20, 2026
Questions: 333
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$30  $99.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99