Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

Buy Now
Questions 5

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Buy Now
Questions 6

A major data center initiative involves performing a sensitivity analysis to determine the center's required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor's advertised plans.

What should the risk manager do to quantify the risk?

Options:

A.

Initiate a 360-degree assessment.

B.

Consult environmental enterprise factors for benchmarks.

C.

Review organizational process assets for guidance.

D.

Consider leveraging the Delphi technique.

Buy Now
Questions 7

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.

Scenario-based risk analysis

B.

Quantitative risk analysis

C.

Qualitative risk analysis

D.

Monte Carlo analysis 

Buy Now
Questions 8

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.

Issue log

B.

Change log

C.

Assumption log

D.

Risk-adjusted back log

Buy Now
Questions 9

in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.

Work breakdown structure (WBS)

B.

Affinity diagram

C.

Monte Carlo simul-ation

D.

Mind mapping

Buy Now
Questions 10

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation. 

Buy Now
Questions 11

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Buy Now
Questions 12

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks. 

Buy Now
Questions 13

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.

Ask the sponsor to define the risk strategy to align with client needs.

B.

Develop a framework and engage the team in creating a risk plan.

C.

Train the team on basic techniques and defer the risk strategy for later.

D.

Concentrate on high-priority risks to meet the sponsor's expectations.

Buy Now
Questions 14

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Buy Now
Questions 15

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.

B.

Communicate with the project manager on the topic.

C.

Assign owners who will be fully accountable to managing the risks.

D.

Define the response plans and take the lead in implementing them.

Buy Now
Questions 16

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Buy Now
Questions 17

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Questions 18

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Buy Now
Questions 19

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Buy Now
Questions 20

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.

B.

Refer to the team’s ground rules on how to resolve conflicts.

C.

Run a sensitivity analysis to check which risks have the most impact.

D.

Use the assumption analysis techniques to validate the assumptions.

Buy Now
Questions 21

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.

Process the freight invoices at higher shipping costs against the project's contingency allowance.

B.

Request a formal change order from the customer to increase the project's total budget.

C.

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.

Ask the project sponsor to cover the additional shipping costs on the company's reserves account.

Buy Now
Questions 22

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

Buy Now
Questions 23

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Options:

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

Buy Now
Questions 24

Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.

Which tool should the risk manager consider for assessing the test risk?

Options:

A.

Scenario analysis

B.

Sensitivity analysis

C.

Probability and impact matrix

D.

Monte Carlo simul-ation 

Buy Now
Questions 25

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register. 

Buy Now
Questions 26

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

Buy Now
Questions 27

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

Options:

A.

Go for a low-risk threshold of ±5% around a cost objective.

B.

Confirm stakeholders risk thresholds based on risk appetites.

C.

Conduct risk identification to populate the risk register.

D.

Go for a high-risk threshold of ±10% around a cost objective. 

Buy Now
Questions 28

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Buy Now
Questions 29

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Buy Now
Questions 30

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

Options:

A.

Actual outcomes and performance of risk management strategies

B.

Actual outcomes of the project's risks and risk responses

C.

Actual costs and schedule delays of risk events

D.

Actual cost impact of risk events

Buy Now
Questions 31

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

Buy Now
Questions 32

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Buy Now
Questions 33

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Buy Now
Questions 34

Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Options:

A.

Activate the contingency plan.

B.

Request a reserves increase.

C.

Add the alert to the risk register.

D.

Update the risk response plan.

Buy Now
Questions 35

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simul-ation

C.

The full risk description

D.

The risk response plan

Buy Now
Questions 36

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Buy Now
Questions 37

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

Buy Now
Questions 38

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.

What should the IT manager's role be in the project team meetings?

Options:

A.

The IT manager should be included as a risk owner.

B.

The IT manager should refine the project baseline plans.

C.

The IT manager should be added as a project sponsor.

D.

The IT manager should lead the infrastructure execution.

Buy Now
Questions 39

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Ensure sufficient resources are available

B.

Revise the risk management plan

C.

Update the risk register

D.

Meet with the project's stakeholders

Buy Now
Questions 40

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

Options:

A.

Updated probability and impact matrix

B.

Updated risk register

C.

Updated mitigation plans

D.

Updated project schedule 

Buy Now
Questions 41

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 

Buy Now
Questions 42

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Questions 43

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.

B.

Ensure the risk register includes all identified risks.

C.

Discuss the risk response strategies with the stakeholders.

D.

Develop a communication plan to share updates on risks.

Buy Now
Questions 44

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Buy Now
Questions 45

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Buy Now
Questions 46

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan 

Buy Now
Questions 47

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Buy Now
Questions 48

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?

Options:

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

Buy Now
Questions 49

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Buy Now
Questions 50

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?

Options:

A.

Check the schedule for constraints

B.

Use the P90 date on the risk report

C.

Decrease the number of iterations

D.

Decrease the risk consequences

Buy Now
Questions 51

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project's midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 52

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.

Earned value analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Root cause analysis

Buy Now
Questions 53

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

Options:

A.

Quantitative risk analysis

B.

Force field analysis

C.

Qualitative risk analysis

D.

Stakeholder analysis

Buy Now
Questions 54

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

Options:

A.

Agree with the external supplier on the timeline.

B.

Register the risk with a medium impact.

C.

Align with stakeholders on the risk threshold.

D.

Engage another supplier with shorter delivery times.

Buy Now
Questions 55

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Buy Now
Questions 56

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Buy Now
Questions 57

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart

B.

Ishikawa diagram

C.

Risk breakdown structure (RBS)

D.

Affinity diagram

Buy Now
Questions 58

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 59

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options:

A.

4 hours

B.

5 hours

C.

6 hours

D.

12 hours

Buy Now
Questions 60

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Buy Now
Questions 61

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

Buy Now
Questions 62

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Questions 63

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

Buy Now
Questions 64

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Buy Now
Questions 65

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

Options:

A.

Sensitivity analysis

B.

simul-ation analysis

C.

Monte Carlo simul-ation

D.

Quantitative analysis

Buy Now
Questions 66

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners. 

Buy Now
Questions 67

A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.

What should the risk manager advise the team to do first?

Options:

A.

Mitigate the risk by asking the team member to gather more information.

B.

Add the risk to the issue log and revisit it when there is more information.

C.

Arrange a meeting with the stakeholder to discuss the risk and information.

D.

Add the risk to the risk register and gather information about its probability and impact. 

Buy Now
Questions 68

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.

Include all stakeholders in the project's governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders' tolerance.

D.

Consider stakeholders' positions and opinions regarding the project’s output.

Buy Now
Questions 69

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Options:

A.

Update the assumptions/exclusions register

B.

Hire more resources and crash the schedule

C.

Perform a qualitative risk analysis for the project

D.

Mitigate risks identified on the sensitivity analysis

Buy Now
Questions 70

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project's complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.

B.

Conduct the exercise with the key team members, excluding external stakeholders.

C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.

D.

Focus only on identifying the most obvious risks to save time and project resources.

Buy Now
Questions 71

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 72

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.  

Buy Now
Questions 73

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?

Options:

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

Buy Now
Questions 74

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

Buy Now
Questions 75

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response. 

Buy Now
Questions 76

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Buy Now
Questions 77

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

Options:

A.

Develop a residual risk management plan to manage the residual risks.

B.

Analyze, document, and communicate the residual risks to stakeholders.

C.

Record the residual risks in the watch list for future reference.

D.

Implement the contingency plan when the residual risks occur.

Buy Now
Questions 78

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Buy Now
Questions 79

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 17, 2025
Questions: 264
PMI-RMP pdf

PMI-RMP PDF

$29.75  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$35  $99.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$47.25  $134.99