Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager

Buy Now
Questions 5

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Buy Now
Questions 6

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

Options:

A.

Implement a strict, standardized approach to ensure consistency across all regions.

B.

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.

Adopt a fully flexible approach that allows teams to manage issues based on local context.

Buy Now
Questions 7

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Buy Now
Questions 8

A project team is preparing a project plan for a government-funded project with multiple stakeholders, including government employees. The project sponsor requests the risk manager estimates the potential costs associated with delays that may arise from government employees, due to bureaucratic processes and other administrative factors.

How should the risk manager approach this task?

Options:

A.

Create a risk register to document all potential risks and estimated impacts, including delays due to government employees.

B.

Develop a risk response plan that includes specific mitigation strategies for government-related delays.

C.

Perform a quantitative risk analysis to determine the potential financial impact of government-related delays.

D.

Conduct a qualitative risk analysis to assess the likelihood and impact of potential delays.

Buy Now
Questions 9

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 10

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?

Options:

A.

Develop risk assessment processes and tools to quantify risk thresholds.

B.

Work with stakeholders to achieve consensus on risk thresholds.

C.

Use subject matter experts and historical data to estimate risk thresholds.

D.

Review regulatory requirements and the contract to identify risk thresholds.

Buy Now
Questions 11

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.

B.

Implement the strategies after completing the risk analysis.

C.

Implement the strategies immediately.

D.

Ensure the strategies are approved by the stakeholders.

Buy Now
Questions 12

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product ' s characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery. 

Buy Now
Questions 13

During a project ' s planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier ' s delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Buy Now
Questions 14

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

Options:

A.

Budget variance data from previously completed projects.

B.

Project scope and cost management plans from previous projects.

C.

Lessons learned from similar completed projects.

D.

Previous project risks that may be relevant to this project.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

Buy Now
Questions 15

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response. 

Buy Now
Questions 16

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

Buy Now
Questions 17

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.

Ask the sponsor to define the risk strategy to align with client needs.

B.

Develop a framework and engage the team in creating a risk plan.

C.

Train the team on basic techniques and defer the risk strategy for later.

D.

Concentrate on high-priority risks to meet the sponsor ' s expectations.

Buy Now
Questions 18

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Options:

A.

Being able to monitor and control risks throughout the project.

B.

Defining how risk management will be executed throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Buy Now
Questions 19

A financial services company has implemented a risk response plan to mitigate potential cybersecurity threats. The project team has conducted a series of tests to ensure the new security measures are effective. However, some executives have expressed concerns about the impact of these measures on daily operations.

What should the risk manager do?

Options:

A.

Facilitate a risk identification session on security measures with the company executives.

B.

Organize a stakeholder workshop to discuss the effectiveness of the new security measures.

C.

Implement additional security measures to address the concerns expressed by the executives.

D.

Acknowledge the concerns and focus on monitoring the effectiveness of the new security measures.

Buy Now
Questions 20

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Buy Now
Questions 21

A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.

What should the risk manager do to address the risk?

Options:

A.

Hold a meeting to assess the risk ' s impact and create a response plan with alternative timelines.

B.

Adjust the overall project schedule based on assumptions about the vendor ' s timeline.

C.

Defer the risk discussion until the vendor finalizes the timeline to prioritize the project ' s start.

D.

Focus on internal risks and assume the vendor will resolve the issue independently.

Buy Now
Questions 22

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Buy Now
Questions 23

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Options:

A.

Study the change logs to implement the approved change requests.

B.

Close out the expired risk and update the relevant project documents.

C.

Get permission from stakeholders before documenting lessons learned.

D.

Continue monitoring the critical response plan on the delivered product.

Buy Now
Questions 24

Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Buy Now
Questions 25

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

Options:

A.

Evaluating the project ' s probability of success

B.

Identifying threats and opportunities

C.

Evaluating the project ' s impact

D.

Performing a qualitative analysis

Buy Now
Questions 26

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.

What should the IT manager ' s role be in the project team meetings?

Options:

A.

The IT manager should be included as a risk owner.

B.

The IT manager should refine the project baseline plans.

C.

The IT manager should be added as a project sponsor.

D.

The IT manager should lead the infrastructure execution.

Buy Now
Questions 27

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Buy Now
Questions 28

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization ' s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk ' s response.

E.

Update and communicate assessments of the secondary risk ' s impact.

Buy Now
Questions 29

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.

US$20.000 loss

B.

US$20,000 profit

C.

US$40,000 loss

D.

US$100,000 profit

Buy Now
Questions 30

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Options:

A.

Engage with the team to present the actual results to the sponsor.

B.

Prepare a management of change (MOC) to adjust the project cost and duration.

C.

Move forward with the lessons learned from the sprint.

D.

Review the assumptions to understand any change.

Buy Now
Questions 31

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks. 

Buy Now
Questions 32

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

Options:

A.

Go for a low-risk threshold of ±5% around a cost objective.

B.

Confirm stakeholders risk thresholds based on risk appetites.

C.

Conduct risk identification to populate the risk register.

D.

Go for a high-risk threshold of ±10% around a cost objective. 

Buy Now
Questions 33

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

Options:

A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.

B.

Engage with the team to enhance the project risk reports sent to the stakeholders.

C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.

D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.

Buy Now
Questions 34

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Buy Now
Questions 35

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Options:

A.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

B.

Brainstorming technique

C.

Delphi technique

D.

Assumptions and constraints analysis

Buy Now
Questions 36

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Buy Now
Questions 37

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders ' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners. 

Buy Now
Questions 38

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted. 

Buy Now
Questions 39

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project ' s risk exposure to an acceptable level?

Options:

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

Buy Now
Questions 40

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores 

Buy Now
Questions 41

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project ' s profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment 

Buy Now
Questions 42

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.

Establish a formal and upfront risk identification process.

B.

Use a detailed and quantitative risk assessment process.

C.

Create an effective and clear risk communication process.

D.

Adopt a dynamic and frequent risk management process.

Buy Now
Questions 43

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

Options:

A.

72

B.

60

C.

40

D.

32

Buy Now
Questions 44

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simul-ation

C.

The full risk description

D.

The risk response plan

Buy Now
Questions 45

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Buy Now
Questions 46

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

Options:

A.

Remove the activity padding.

B.

Review the risk response plan.

C.

Update the risk contingency plan.

D.

Update the schedule constraints. 

Buy Now
Questions 47

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

Buy Now
Questions 48

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Buy Now
Questions 49

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

Options:

A.

Updated probability and impact matrix

B.

Updated risk register

C.

Updated mitigation plans

D.

Updated project schedule 

Buy Now
Questions 50

A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project ' s midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 51

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry ' s standard procedures

B.

Current request for proposal (RFP)

C.

Company ' s historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations 

Buy Now
Questions 52

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Buy Now
Questions 53

A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.

What should have been done to prevent this situation?

Options:

A.

The project manager should have requested and mandated that no vacations be taken during critical implementation activities or until all implementation had been completed for the project.

B.

The risk manager should have anticipated this situation and planned for schedule buffers in the project schedule to accommodate the likelihood of failed hardware.

C.

The risk owner should have communicated with the project manager so that a designated stakeholder could have been assigned to accept accountability for implementing risk responses.

D.

The risk manager should have taken the responsibility of responding to this risk instead of relying on and waiting for the risk owner to return from vacation.

Buy Now
Questions 54

An agile project manager has noticed their team ' s declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Buy Now
Questions 55

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Buy Now
Questions 56

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?

Options:

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes. 

Buy Now
Questions 57

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation. 

Buy Now
Questions 58

A project team is concluding the first monthly meeting on a new engineering project, with regular review of project risks. Which document should the risk manager update to reflect the risks ' current status?

Options:

A.

Maintain the risk response plan and continuously monitor actions taken to mitigate risks.

B.

Ensure that the risk management plan is reviewed to incorporate adjustments in risk strategies.

C.

Revise the risk register to reflect changes in risk status and include new mitigation actions.

D.

Update the project schedule to reflect the impacts of risks and adjustments to timelines.

Buy Now
Questions 59

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Buy Now
Questions 60

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.

Detailed work breakdown structure (WBS)

B.

Lessons learned from previous projects

C.

Baselines approved by the project team

D.

Actual data from the current project

Buy Now
Questions 61

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

Buy Now
Questions 62

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.

B.

Review the effectiveness of the risk process.

C.

Update the risk management plan.

D.

Escalate the project risks to upper management. 

Buy Now
Questions 63

An organization is executing two projects — Project A and Project B — simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B.

Which action should the risk manager for Project A take?

Options:

A.

Review the findings in Project A ' s closure documents and propose a new organizational process for portfolio risk management.

B.

Consult with Project B ' s risk manager and determine where synergies might exist between the risk management plans for both projects.

C.

Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.

D.

Continue executing the planned risk mitigation to avoid any additional schedule impact to Project A.

Buy Now
Questions 64

A project team is developing a software system for a financial organization and is conducting a failure modes and effects analysis (FMEA) to identify and evaluate potential failure points. The risk manager must guide the team on how to prioritize risks based on FMEA results for effective risk management.

What should the risk manager do?

Options:

A.

Direct the team to prioritize risks based solely on their likelihood to streamline the analysis.

B.

Encourage the team to focus on documenting the most severe FMEA risks and disregard others.

C.

Emphasize technical faults within the system as the highest priority for risk response planning.

D.

Advise the team to prioritize risks using severity, occurrence, and detection ratings.

Buy Now
Questions 65

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.

Issue log

B.

Change log

C.

Assumption log

D.

Risk-adjusted back log

Buy Now
Questions 66

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Buy Now
Questions 67

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis 

Buy Now
Questions 68

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

Buy Now
Questions 69

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Options:

A.

Ensured to include the stakeholders in the team discussions

B.

Encouraged involvement of the project team during the review meetings

C.

Enhanced communication with the sponsor regarding secondary risk impact

D.

Ensured the sponsor got more involved with the project risk planning

Buy Now
Questions 70

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project ' s risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Buy Now
Questions 71

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Buy Now
Questions 72

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Buy Now
Questions 73

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.

Highlight this situation to the project manager

B.

Conduct a cost-benefit analysis

C.

Change the risk response strategy

D.

Analyze the situation and meet with the risk owner

Buy Now
Questions 74

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Options:

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Buy Now
Questions 75

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Options:

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

Buy Now
Questions 76

A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.

What should the risk manager do?

Options:

A.

Gather the project ' s status reports and meeting minutes to determine when issues occurred and how quickly the issues were addressed.

B.

Conduct a retrospective meeting with stakeholders and inquire about what went well and what could be improved on future projects.

C.

Work with the project manager to determine if additional resources could have prevented or mitigated the issues that arose on the project.

D.

Review the project ' s risk register and determine how comprehensive and effective each risk and issue response was.

Buy Now
Questions 77

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Buy Now
Questions 78

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 79

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Buy Now
Questions 80

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks. 

Buy Now
Questions 81

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.

Execute the security risks contingency plan.

B.

Get a report of customers affected by the risk.

C.

Identify residual and secondary risks.

D.

Coordinate a response with the risk owner.

Buy Now
Questions 82

A risk manager is working with a key project stakeholder who is concerned about the likelihood of quality issues such as product defects or process anomalies. The stakeholder has a low tolerance for any defects. The risk manager needs to tailor the risk management strategy to accommodate the stakeholder ' s risk appetite.

What should the risk manager do?

Options:

A.

Use Lean Six Sigma processes to ensure there are no defects.

B.

Request more funds in the risk reserve for defect management.

C.

Refine probability definitions to align with the stakeholder ' s risk tolerance.

D.

Conform to the stakeholder ' s risk tolerance levels by using Lean principles.

Buy Now
Questions 83

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Buy Now
Questions 84

The project manager leading a company ' s digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization ' s professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Buy Now
Questions 85

A risk manager faces resistance as they try to implement the project ' s risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Jul 5, 2026
Questions: 278
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$30  $99.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99