PMI-PBA PMI Professional in Business Analysis Questions and Answers

Questions 4

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ”

What could have prevented the stakeholder from being surprised about the status change?

Options:

A.

The status should have been communicated to the requirement’s source.

B.

The status should have been reviewed prior to project launch.

C.

The status should have been communicated to all project stakeholders.

D.

The status should have been updated in the traceability matrix.

Buy Now
Questions 5

A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.

Which of the following components will the business analyst use as input to the business case?

Options:

A.

Project timeline

B.

Project scope

C.

Product scope

D.

Work breakdown structure

Buy Now
Questions 6

After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:

Options:

A.

some requirements having not yet been discussed in a work group session.

B.

the requirements’ reference codes not tracing to the attribute numbers in the work breakdown structure.

C.

the requirements documents having not yet received sign-off from the sponsor.

D.

the requirements not providing all of the information needed to define the work.

Buy Now
Questions 7

The requirements traceability matrix should primarily be used to:

Options:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Buy Now
Questions 8

A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.

The business analyst should:

Options:

A.

adhere to the project plan to achieve project objectives.

B.

voice user concerns to management and recommend that the project be closed.

C.

clearly communicate project objectives and attempt to defuse tensions.

D.

delay the application's deployment until the conflicts have been resolved.

Buy Now
Questions 9

A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation

process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume

reporting required by the company's financial department. The business analyst for the project determines that the selection criteria

needed was not specified in the system requirements or design specifications.

Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement

was missed?

Options:

A.

Root cause analysis, fishbone diagram, and/or the Five Whys

B.

Root cause analysis, problem tracking, and/or benchmarking

C.

Scope modeling, Ishikawa diagram, and/or the Five Whys

D.

Cause and effect diagram, brainstorming, and/or the Five Whys

Buy Now
Questions 10

Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.

What should the business analyst have documented?

Options:

A.

Sponsor approval in the requirements traceability matrix

B.

The source in the RACI matrix

C.

Roles and responsibilities in the RACI matrix

D.

The source in the requirements traceability matrix

Buy Now
Questions 11

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

Options:

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

Buy Now
Questions 12

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

Options:

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Buy Now
Questions 13

A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.

Which analysis technique has the business analyst used?

Options:

A.

Organization

B.

Decomposition

C.

Dependency

D.

Interface

Buy Now
Questions 14

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

Options:

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Buy Now
Questions 15

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

Options:

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Buy Now
Questions 16

Which of the following is a method for requirements change control?

Options:

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Buy Now
Questions 17

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Options:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.

Buy Now
Questions 18

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

Options:

A.

The tester identified in the testing strategy

B.

The person identified in the RACI matrix

C.

The project manager identified in the project charter

D.

The project sponsor identified in the scope document

Buy Now
Questions 19

What should a business analyst do after discovering that two solution requirements conflict?

Options:

A.

Consult the sponsor(s) and log the constraint.

B.

Perform an impact analysis and propose a lower-cost alternative.

C.

Update the requirements baseline and upload it to the project repository.

D.

Communicate the conflict to stakeholders and facilitate a resolution.

Buy Now
Questions 20

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

Options:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.

Buy Now
Questions 21

Which document best provides the boundaries for product development?

Options:

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Buy Now
Questions 22

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Options:

A.

verify that the test case is incorrect.

B.

let the users decide if the test result 1s acceptable.

C.

change the requirement according to the test result.

D.

ask the tester to perform the test again.

Buy Now
Questions 23

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

Options:

A.

MoSCoW

B.

SMART goals

C.

RACI models

D.

Storyboarding

Buy Now
Questions 24

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

Options:

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Buy Now
Questions 25

The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?

Options:

A.

It should remain because it specifies the reason why the business requirement is needed.

B.

It should be removed because it does not state how often the data should be synchronized.

C.

It should be revised because it states a solution to the problem rather than the business need.

D.

It should remain because it specifies the type of data and the source system.

Buy Now
Questions 26

Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:

Options:

A.

the risk associated with the change is not evaluated.

B.

changes must still be documented and captured.

C.

a change control board should be established.

D.

changes can be applied without further managerial involvement.

Buy Now
Questions 27

A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.

Where can the business analyst best reflect the intangible costs associated with this change?

Options:

A.

In the requirements specification document

B.

In the business case

C.

In the pay-back analysis

D.

In the balanced score card chart

Buy Now
Questions 28

When determining the value of a business case, which tool or technique should be used?

Options:

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Buy Now
Questions 29

A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.

Which metrics tool should the business analyst use to record the results?

Options:

A.

Business completion

B.

Sales and marketing

C.

Customer

D.

Focus group

Buy Now
Questions 30

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.

Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

Options:

A.

SMART Goals

B.

Moscow Analysis

C.

SWOT Analysis

D.

Timeboxing Analysis

Buy Now
Questions 31

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Buy Now
Questions 32

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

Options:

A.

Quantify the risks associated with the measurement errors and update the risk register.

B.

Ask the operations manager to formally accept the requirements documents.

C.

Plan a training session for the new system before it is handed over to the operations manager.

D.

Clearly define the maximum acceptable error rate for the new system.

Buy Now
Questions 33

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

Options:

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Buy Now
Questions 34

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

Options:

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Buy Now
Questions 35

A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.

What step should the business analyst take next?

Options:

A.

Schedule a requirements gathering sessions with the manager of the ordering department.

B.

Request information on the current ordering process and compare it with other companies.

C.

Identify testing resources to support the implementation.

D.

Select the software to implement and start working with the technical resources.

Buy Now
Questions 36

One of the main purposes for creating a requirements traceability matrix is to:

Options:

A.

track how requirements can be connected to the solution.

B.

provide test cases to validate solution deliverables.

C.

document stakeholder approval of project requirements.

D.

track the project solution scope.

Buy Now
Questions 37

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Options:

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Buy Now
Questions 38

Which of the following is a properly written requirement statement?

Options:

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Buy Now
Questions 39

Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?

Options:

A.

A work breakdown structure analysis of the service

B.

A Pareto analysis

C.

A flowchart of the service

D.

A cause-and-effect diagram

Buy Now
Questions 40

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Buy Now
Questions 41

What is one benefit of documenting the change control process?

Options:

A.

Stakeholders are shielded from how changes are assessed.

B.

Stakeholders know how to request changes.

C.

Stakeholders have a schedule of changes to be deployed.

D.

Stakeholders understand the difficulty of managing requirements.

Buy Now
Questions 42

A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.

Which critical field is needed to ensure that the traceability matrix is usable?

Options:

A.

Status

B.

Hierarchy

C.

Owner

D.

Requirements description

Buy Now
Questions 43

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

Options:

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Buy Now
Questions 44

In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.

Which technique could have prevented this problem from occurring?

Options:

A.

Prototyping

B.

Diagrams

C.

Use cases

D.

Document analysis

Buy Now
Questions 45

During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.

What should the business analyst have defined to avoid this?

Options:

A.

Communications approach in the business analysis plan

B.

Decision-making process in the project management plan

C.

Decision-making process in the business analysis plan

D.

Communications approach in the project management plan

Buy Now
Questions 46

What is a standardized, effective, and efficient way to manage changes to project documentation?

Options:

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Buy Now
Questions 47

Which solution should be chosen according to the completed weighted-ranking matrix?

Options:

A.

Outsource the development.

B.

Purchase off-the-shelf software.

C.

Develop in-house software.

D.

Enhance the existing system.

Buy Now
Questions 48

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

Options:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Buy Now
Questions 49

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

Options:

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Buy Now
Questions 50

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

Options:

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Buy Now
Questions 51

A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.

What should the business analyst do immediately after the discussion?

Options:

A.

Schedule time with the process owners.

B.

Put the information into a project plan.

C.

Develop an issues log.

D.

Assess the risks for the project.

Buy Now
Questions 52

Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.

In which reference material can the business analyst find information about the missing project stakeholders?

Options:

A.

Organizational chart

B.

Business case

C.

Business analysis plan

D.

Business analyst communication plan

Buy Now
Questions 53

Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments want to include specific requirements. The CEO has a requirement to deploy in three months.

Which of the following actions will have a greater influence on the project success?

Options:

A.

Prioritize and develop the requirements of the marketing department since the project will impact a greater number of people.

B.

Estimate the effort required for each requirement and develop as many functionalities as possible.

C.

Conduct a stakeholder analysis and balance requirements by understanding the relative power associated with each stakeholder group.

D.

Explain the situation to the CEO and try to obtain an extension of the contract for the actual time necessary to develop the system.

Buy Now
Questions 54

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

Options:

A.

Conduct a formal or informal review of the requirements.

B.

Create and maintain an audit history log of changes to requirements.

C.

Provide a defect tracking log for review.

D.

Send an email requesting approval of requirements.

Buy Now
Questions 55

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

Options:

A.

requirements gathering workshops with the stakeholders.

B.

requirements acceptance with the customer.

C.

requirements validation with the testers.

D.

requirements sign-off with the customer.

Buy Now
Questions 56

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?

Options:

A.

Multivoting

B.

MoSCoW

C.

Time-boxing

D.

Budget analysis

Buy Now
Questions 57

A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

Options:

A.

Work breakdown structure

B.

Requirements management plan

C.

Use cases

D.

Traceability matrix

Buy Now
Questions 58

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

Options:

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Buy Now
Questions 59

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Buy Now
Questions 60

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Buy Now
Exam Code: PMI-PBA
Exam Name: PMI Professional in Business Analysis
Last Update: Jun 30, 2025
Questions: 200