A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?
A project manager is working on an existing, large, complex project that involves regulatory and environmental considerations. The development of a detailed project plan will be critical. Which of the following should the project manager do first?
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
Which of the following activities should a project manager perform during the closing phase? (Select three).
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
Which of the following are primary features provided by a standard laaS solution? (Select two).
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
A project team member wrote a user guide over the past ten days. Given the following scatter diagram.
Which erf the following can be formally conducted?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?
During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?
A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
Which of the following would help a project manager identify that project goals have been reached?
A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?
A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
Which of the following offers administrators more direct control over operating systems?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?
A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
Which of the following best represents the project impact to a company's brand value?
When introducing a new information asset, what is the MOST important responsibility of the asset owner?
Which of the following best describes the difference between the current state and the desired future state in project management?
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?
Which of the following activities are performed during the closing phase? (Select three).
A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
• Purpose
• Scope of work
• Location of work
• Period of performance
• Deliverables schedule
• Applicable standards
• Acceptance criteria
• Special requirements
• Payment schedule
Which of the following documents did the client provide to the project manager?
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?
Which of the following would be best to utilize when managing communications for project teams across multiple time zones?
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?
Which of the following is a potential challenge that may arise from language barriers among a project team?
During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
Which of the following can a project manager infer from the following velocity chart?
Which of the following should be considered first when determining the privacy management for project data?
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
Which of the following BEST illustrates how team members with different roles should interact on the team?
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?