Questions 4

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Buy Now
Questions 5

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

Options:

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Buy Now
Questions 6

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

Options:

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Buy Now
Questions 7

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Buy Now
Questions 8

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

Options:

A.

Pareto

B.

Run

C.

Control

D.

Histogram

Buy Now
Questions 9

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Buy Now
Questions 10

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Buy Now
Questions 11

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

Options:

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

Buy Now
Questions 12

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Buy Now
Questions 13

A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?

Options:

A.

Scrum

B.

Extreme programming

C.

Waterfall

D.

Kanban

Buy Now
Questions 14

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Buy Now
Questions 15

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Buy Now
Questions 16

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Buy Now
Questions 17

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Buy Now
Questions 18

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

Options:

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

Buy Now
Questions 19

Which of the following tools is best to use for storing lessons learned?

Options:

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Buy Now
Questions 20

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

Options:

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Buy Now
Questions 21

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Buy Now
Questions 22

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

Options:

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Buy Now
Questions 23

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Options:

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Buy Now
Questions 24

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

Options:

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Buy Now
Questions 25

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Buy Now
Questions 26

A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?

Options:

A.

Run charts

B.

Fishbone/lshikawa diagrams

C.

Scatter plot

D.

Decision tree

Buy Now
Questions 27

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Buy Now
Questions 28

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Buy Now
Questions 29

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Buy Now
Questions 30

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

Options:

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

Buy Now
Questions 31

A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?

Options:

A.

Meeting minutes

B.

Action items

C.

Timeboxing

D.

Follow-up notes

Buy Now
Questions 32

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Buy Now
Questions 33

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 34

Which of the following can a project manager infer from the following velocity chart?

Options:

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Buy Now
Questions 35

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Buy Now
Questions 36

How does data discovery assist with data classification'?

Options:

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Buy Now
Questions 37

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Buy Now
Questions 38

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Buy Now
Questions 39

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Questions 40

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 41

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

Options:

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Buy Now
Questions 42

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

Options:

A.

The ticket system provided access by default without any approval.

B.

The project manager did not perform proper project planning.

C.

The system is lacking proper access controls.

D.

Sensitive data was incorrectly classified during the audit process.

Buy Now
Questions 43

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

Options:

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Buy Now
Questions 44

A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?

Options:

A.

Define access requirements.

B.

Develop a transition plan.

C.

Create a responsibility assignment matrix.

D.

Create a work breakdown structure.

Buy Now
Questions 45

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

Options:

A.

Avoid

B.

Transfer

C.

Accept

D.

Share

Buy Now
Questions 46

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

Options:

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Buy Now
Questions 47

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Buy Now
Questions 48

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

Options:

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

Buy Now
Questions 49

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Options:

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Buy Now
Questions 50

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Buy Now
Questions 51

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Buy Now
Questions 52

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options:

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Buy Now
Questions 53

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Buy Now
Questions 54

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Buy Now
Questions 55

A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).

Options:

A.

Feedback

B.

Financial summary

C.

Project schedule

D.

Organizational chart

E.

Approval

F.

Risks

Buy Now
Questions 56

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Buy Now
Questions 57

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Buy Now
Questions 58

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Buy Now
Questions 59

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Buy Now
Questions 60

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Buy Now
Questions 61

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

Buy Now
Questions 62

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Buy Now
Questions 63

Given the following information:

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Buy Now
Questions 64

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options:

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

Buy Now
Questions 65

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

Options:

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Buy Now
Questions 66

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

Options:

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Buy Now
Questions 67

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

Options:

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Buy Now
Questions 68

Which of the following pieces of data are examples of Pll?

Options:

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Buy Now
Questions 69

Which of the following activities would a project manager perform during the closing phase? (Select THREE).

Options:

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Buy Now
Questions 70

Which of the following is the best example of CapEx?

Options:

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Buy Now
Questions 71

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

Options:

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Buy Now
Questions 72

During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?

Options:

A.

Communicate the change status.

B.

Ask for a change request submission

C.

Escalate to the change control board

D.

Reject the change to prevent scope creep.

Buy Now
Questions 73

A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

Options:

A.

The project is ahead of schedule and under budget.

B.

The project is behind schedule and over budget

C.

The project is ahead of schedule and over budget.

D.

The project is behind schedule and under budget

Buy Now
Questions 74

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

Options:

A.

Perform a gap analysis.

B.

Escalate the issue.

C.

Submit a change request.

D.

Approve deliverables.

Buy Now
Questions 75

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Options:

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Buy Now
Questions 76

Which of the following is a consideration when determining a project's ESG factors?

Options:

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

Buy Now
Questions 77

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Buy Now
Questions 78

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Buy Now
Questions 79

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Questions 80

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 81

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Buy Now
Questions 82

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Buy Now
Questions 83

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

Options:

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

Buy Now
Questions 84

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Options:

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Buy Now
Questions 85

Which of the to and allowing interactive feedback from a project team?

Options:

A.

Text message

B.

Chat

C.

Email

D.

Videoconference

Buy Now
Questions 86

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 87

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Buy Now
Questions 88

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

Options:

A.

Call the previous PM for advice on risks and issues.

B.

Ask the project sponsor to provide previous final project report results.

C.

Complete the project charter using the other PM's subject matter expertise.

D.

Use existing artifacts and accommodate based on the current project success criteria.

Buy Now
Questions 89

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

Options:

A.

Awareness of the local environment

B.

Awareness of the brand value

C.

Awareness of the resource constraints

D.

Awareness of the company's mission

Buy Now
Questions 90

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Buy Now
Questions 91

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Options:

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Buy Now
Questions 92

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Buy Now
Questions 93

Which of the following statements best describes a content management system?

Options:

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Buy Now
Questions 94

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Questions 95

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Buy Now
Questions 96

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 97

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

Options:

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Buy Now
Questions 98

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Buy Now
Questions 99

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Options:

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Buy Now
Questions 100

A team member identifies a critical issue in production. Which of the following should the project manager apply?

Options:

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Buy Now
Questions 101

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

Options:

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Buy Now
Questions 102

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Buy Now
Questions 103

Which of the following provides the best justification for undertaking a project?

Options:

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Buy Now
Questions 104

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

Options:

A.

Forming, storming, performing, norming, adjourning

B.

Forming, performing, storming, norming, adjourning

C.

Forming, norming, storming, performing, adjourning

D.

Forming, storming, norming, performing, adjourning

Buy Now
Questions 105

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Buy Now
Questions 106

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options:

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Buy Now
Questions 107

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

Options:

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Jul 3, 2025
Questions: 362
PK0-005 pdf

PK0-005 PDF

$29.75  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$35  $99.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$47.25  $134.99