Your customer plans to replace a legacy HPE BladeSystem solution with the HPE Synergy platform.
The customer requirements include:
30 compute nodes to support their virtualization workloads
Redundancy within the management subsystem
An in-frame storage solution to support vSAN
A redundant networking subsystem with the ability to virtualize WWNs
Simplified management with a single logical enclosure
You are reviewing the following proposal:
3 x HPE Synergy 12000 frames
2 x HPE Virtual Connect SE 100Gb F32 Modules for Synergy
4 x HPE Synergy 50Gb Interconnect Link Modules
3 x HPE D3940 Storage Modules with maximum number of drives
6 x HPE Composer2 + 30 x HPE OneView Advanced licenses
30 x SY 480 Gen11 compute modules, each with 2 CPUs and appropriate mezzanine cards
Which statement about this proposal is true to help meet the customer requirements?
Your customer requires a data protection solution that will support their workloads running on an HPE Alletra MP B10000 storage array.
Your customer requirements include:
Protecting VMware vSphere workloads
Covering different hypervisors
Pay-per-use model
Near synchronous and block-level replication
Select the most appropriate solution.
Your customer has a combination of HPE and non-HPE equipment.
Which is the correct functionality available in Aruba Fabric Composer for this customer’s environment?
Your customer has requested a solution with HPE Alletra Storage MP B10000 that needs four SFP28 ports per node, for iSCSI connectivity.

A junior architect has prepared a BOM for the solution.
What needs to be changed in the BOM to meet the requirement?
Your customer has provided the CLI output of a switch to show how their devices are connected.
Refer to the output:
show arp
IPv4 Address MAC Port Physical Port State
10.0.255.2 ... vlan150 ... reachable
10.12.43.1 ... vlan1 ... reachable
10.0.255.3 ... vlan150 ... reachable
Total Number Of ARP Entries Listed: 3.
What should you consider while discussing upgrades to your customer’s environment and network components?
A customer is about to do a server refresh with the intent of using HPE ProLiant DL360 Gen11 servers, with CPUs exceeding 270 watt power usage. The customer has existing third-party, 42U, air-cooled racks they are planning to reuse.
Which cooling option will allow your customer to install the servers with their existing racks, with the least amount of changes to the setup?
Your customer plans to deploy multiple virtual machines running database workloads. They plan to re-use and extend an existing Synergy, 3PAR, and VMware infrastructure.
What is true regarding a possible upgrade?
You presented a solution to your customer that will replace their legacy HPE BladeSystem.
The new solution is based on the HPE Synergy platform and consists of the following components:
5 HPE Synergy 12000 frames
2 HPE Virtual Connect SE 100Gb F32 Modules for Synergy
8 HPE Synergy 25/50Gb Interconnect Link Modules
60 HPE Synergy 480 Gen11
Which statement about the business and financial benefit of the new solution for the customer is true?
You are designing a solution for a customer that will support a virtualization workload based on HPE Synergy. Your customer has the following requirements:
Dual-socket HPE Synergy compute nodes running ESXi 8.x with maximum memory supported
Each node should have access to shared storage from HPE Alletra Storage MP B10000
All virtual machines should be protected against host failure
All virtual machines with vGPU must be protected with Fault Tolerance
All compute nodes should boot from disks located in the D3940 Storage Modules protected with RAID 1
All frames should be managed as one logical enclosure to simplify management
All compute nodes should support two network ports with the maximum Ethernet connectivity speed
You are reviewing a proposal that you must verify. The proposal consists of:
3 x HPE Synergy 12000 frames
2 x HPE Synergy Composer2 modules
4 x HPE Virtual Connect SE 100Gb F32 Modules for Synergy
4 x HPE Synergy 50Gb Interconnect Link Modules
3 x HPE Synergy D3940 Storage Modules, each with 20 SSD drives
1152 core VMware vSphere Enterprise Plus subscriptions
36 x HPE Synergy 480 Gen11 compute nodes
Each SY480 Gen11 is configured with:
A single Platinum CPU with 32 cores
HPE Synergy 6820C 25/50Gb Converged Network Adapter
HPE Synergy 5830C 32Gb Fibre Channel Host Bus Adapter
HPE MR416i-o Gen11 12G SAS Mezzanine Controller
Which two statements are true regarding the proposal? (Select two.)
Your customer is currently using an HPE SimpliVity 380 Gen10 solution and is planning for a generation refresh to an HPE SimpliVity 380 Gen11.
The existing cluster is planned to be maintained as a test and dev platform for another 24–36 months while production workloads are moved to the new environment.
The new solution will be purchased as HPE GreenLake for Private Cloud Business Edition, and the customer would like to include the existing Gen10 cluster within the same management platform.
Which statement is true about combining the management of both the old and new generations?
Your customer has a combination of HPE and non-HPE equipment.
What is the correct functionality available in Aruba Fabric Composer for this customer’s environment?