CCBA Certification of Capability in Business Analysis (CCBA) Questions and Answers

Questions 4

What does the decomposition of activities and tasks based on the work breakdown structure create for the business analyst?

Options:

A.

Activity list

B.

Business analysis plan

C.

Network diagram

D.

Project management plan

Buy Now
Questions 5

What tool is best described as a spreadsheet to use when there's a relatively low amount of requirements that need to be traced?

Options:

A.

Roles and responsibilities chart

B.

Quantitative matrix

C.

Coverage matrix

D.

RACI Chart

Buy Now
Questions 6

Complete this sentence in regard to the level of abstraction. Requirements need to say needs to be done, not to do it.

Options:

A.

What, when

B.

Requirements, who needs

C.

What, how

D.

Requirements, how much

Buy Now
Questions 7

Which of the following are not appropriate for a plan-driven business analysis approach? Each correct answer represents a complete solution.

Options:

A.

Informal

B.

Face-to-face

C.

Ad hoc

D.

Formal

Buy Now
Questions 8

You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders located in offices around the world. Because these stakeholders are dispersed, what is likely to increase in this endeavor as opposed to a collocated group of stakeholders?

Options:

A.

Costs

B.

Face-to-face meetings

C.

Communication needs

D.

Risks

Buy Now
Questions 9

If you're a business analyst and using an event-based elicitation task, such as a requirements workshop, what can be considered as essential to establish with the participants?

Options:

A.

Cost management

B.

Deadlines

C.

Ground rules

D.

Purpose of the workshop

Buy Now
Questions 10

One of the techniques to assess capabilities in an organization is to use SWOT. What does SWOT accomplish?

Options:

A.

SWOT reviews your strengths, weaknesses, opportunities, and threats.

B.

It identifies how current capabilities match up against the influencing factors.

C.

It assesses the strength, weaknesses, opportunities, and threats.

D.

SWOT is a goal setting technique that means "Sweat Works Over Time."

Buy Now
Questions 11

The project plan called for deliverables to be handed over at the end of the project. Although the client's business team was satisfied, the client's technical team was extremely resistant to this approach. What could the business analyst (BA) do to mitigate the technical team’s resistance?

Options:

A.

Escalate to project sponsor

B.

Meet with technical team

C.

Reassess the project objectives

D.

Email the business team

Buy Now
Questions 12

A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?

Options:

A.

By ensuring the requirements are validated in time

B.

By demonstrating how to record elicitation results

C.

By outlining the level of stakeholder collaboration

D.

By determining when elicitation is complete

Buy Now
Questions 13

Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?

Options:

A.

Develop a data model diagram

B.

Create business process models

C.

Write functional requirements

D.

Establish a communication plan

Buy Now
Questions 14

A business analyst (BA) is assessing the completeness and coherence of the requirements. The BA has considered a variety of viewpoints and has a collection of views. What has the BA constructed?

Options:

A.

Requirements architecture

B.

Requirements traceability matrix

C.

Business knowledge model

D.

Solution design

Buy Now
Questions 15

There are three inputs needed to determine the solution approach process. What are these inputs?

Options:

A.

Business need, organizational process assets, and enterprise environmental factors

B.

Business need, enterprise environmental factors, and required capability

C.

Business need, organizational process assets, and assumptions

D.

Business need, organizational process assets, and required capability

Buy Now
Questions 16

The business need is considered to be the most critical step in the business analysis effort. Why is the definition of the business need considered the most critical step?

Options:

A.

The business need defines the problem the business analyst is finding a solution for.

B.

The business need defines the solution for the business problem.

C.

The business need takes the longest time and costs most of the business analysis efforts.

D.

The definition of the business need determines future solutions, stakeholders, and approaches.

Buy Now
Questions 17

You are the business analyst for your organization. Your current project is using a plan-driven approach for the requirements, business analysis, and monitoring. Which one of the following statements best describes the plan-driven approach to business analysis planning and monitoring?

Options:

A.

Plan-driven approaches encourage changes that prevent errors and omissions.

B.

Plan-driven approaches typically call for a significant amount of formality and detail.

C.

Plan-driven approaches determine how priorities will be diagnosed for the project solution.

D.

Plan-driven approaches typically have meetings daily to discuss the business analysis requirements process.

Buy Now
Questions 18

A business analyst (BA) has completed an impact analysis of a proposed change, gained approval for the change, and has updated the requirements. The project sponsor wants to be updated with an overview of the results. How should the BA communicate the results?

Options:

A.

Schedule a requirements workshop

B.

Present the requirements at a high-level

C.

Email the requirements package

D.

Create use case scenarios

Buy Now
Questions 19

There are four methods to generate the business need in an organization. Which approach is described as the need to achieve a strategic goal?

Options:

A.

From the bottom up

B.

From external drivers

C.

From the top down

D.

From middle management

Buy Now
Questions 20

You are the business analyst for your organization and management has asked you to select a model for your solution. Management wants you to describe the people within and without of your organization who will interact with the solution. What type of model has management asked you to create?

Options:

A.

Events

B.

Concept and relationship

C.

Process

D.

User classes, profiles, and roles

Buy Now
Questions 21

Beth is a business analyst for her organization and she's completing the tasks in the requirements management and communication knowledge area. As a result of these tasks, she'll create several things for her organization. Which one of the following, however, is not one of the outputs of the requirements management and communication tasks?

Options:

A.

Traced requirements

B.

Requirement management plan

C.

Requirement package

D.

Approved requirements

Buy Now
Questions 22

A business analyst has identified four different solutions for a business need. In the light of solution assessment, how many solution assessment iterations should he do?

Options:

A.

The business analyst can do multiple assessments, one for each solution or to compare multiple solutions.

B.

There is no limit, but the business analyst should perform the same type of assessments for each solution to be balanced.

C.

The business analyst can do one assessment per solution.

D.

There should only be one solution assessment - four is too many. Some of the solutions are better than others.

Buy Now
Questions 23

A business analyst (BA) is working to identity the business need, specifically the problems with the current state of a process. At which level of the enterprise can the BA identify problems with the current state?

Options:

A.

Bottom-up

B.

Top-down

C.

From external drivers

D.

From middle-management

Buy Now
Questions 24

A business analyst (BA) begins to suspect that the ongoing elicitation activities with stakeholders are not delivering the quality of business analysis information required due to a lack of stakeholder participation. What type of technique can the BA adopt to resolve this type of issue?

Options:

A.

Stakeholder Engagement

B.

Roles and Permissions Matrix

C.

Requirements Validation

D.

Risk Analysis and Management

Buy Now
Questions 25

A business analyst (BA) is planning the traceability approach for a project. Why should the BA conduct this planning activity?

Options:

A.

To verify that project information is represented at a high level of abstraction

B.

To document the relationship between the different phases of the project for different stakeholders

C.

To ensure the approach provides enough detail to add value without excessive overhead

D.

To associate information with individual or related groups of requirements

Buy Now
Questions 26

A business analyst (BA) is determining the current state as part of a new project. What is an internal enterprise asset that the BA must include in the analysis?

Options:

A.

Brand name

B.

Organizational structure

C.

Business need

D.

Enterprise mission statement

Buy Now
Questions 27

A business analyst (BA) is structuring requirements to ensure they are cohesive and tell the full story. Which of the following requirements is consistent with a stakeholder's need: “As a Product Manager, I want to review my general insurance sales performance so I track my sales performance against my annual target”?

Options:

A.

“Provide weekly new bank account sales reports on a shared drive.”

B.

“Increase customer retention across the life insurance division”

C.

“Segment insurance sales data between life and general”

D.

“Migrate the insurance web portal to a cloud platform."

Buy Now
Questions 28

Due to a change in regulation, a solution being implemented has a new compliance requirement that must be evaluated. The requirements change strategy focuses on total cost of change as the primary driver for decisions. The business analyst (BA) compiled the following impact assessment of the proposed change based on the new compliance requirement.

What recommendation should the BA make to the stakeholders based on the above information?

Options:

A.

Approve the requirement

B.

Request additional information

C.

Defer the requirement

D.

Reject the requirement

Buy Now
Questions 29

A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?

Options:

A.

Repository

B.

Document management

C.

Email

D.

Individual collaboration

Buy Now
Questions 30

A large online retailer is introducing new technology to upgrade its aging ordering process. The business analyst (BA) has drawn a stakeholder matrix showing information on how to engage with the stakeholders throughout the project.

Using the stakeholder matrix as a guide, how should the BA engage the suppliers?

Options:

A.

Meet with the suppliers to discuss their needs

B.

Ensure the suppliers are kept informed by showing interest in their needs

C.

Communicate changes to the suppliers by general communication

D.

Focus efforts to engage with the suppliers regularly

Buy Now
Questions 31

A business analyst (BA) is tasked with designing a method of ensuring that the requirements captured during the elicitation sessions satisfy the needs and expectations of the customer experience, within an initiative. The BA identifies a way that the stakeholder requirements can be structured to ensure realization of the desired customer experience. Which viewpoint describes the approach taken by the BA to structure the requirements?

Options:

A.

User interactions

B.

Business model

C.

Audit and security

D.

Business process model

Buy Now
Questions 32

Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?

Options:

A.

Project manager

B.

Suppliers

C.

Sponsor

D.

Operational support

Buy Now
Questions 33

You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?

Options:

A.

RAM Chart

B.

Affinity Diagram

C.

Stakeholder Analysis

D.

Text-Oriented Chart

Buy Now
Questions 34

During the analysis, synthesis, and refinement of elicitation results the business analyst (BA) has discovered that some information is missing. Which course of action would resolve the situation?

Options:

A.

Verify the requirements results

B.

Conduct elicitation activities

C.

Conduct traceability analysis

D.

Validate the requirements

Buy Now
Questions 35

One of the tasks that the business analyst (BA) needs to complete is to maintain the requirements. As much as the BA values and sees the benefits of maintaining the requirements, the project manager (PM) does not see the same. In order to help the PM understand the value of this task, which following benefit of maintaining the requirements should the BA communicate to the PM?

Options:

A.

They identify the financial projections of the project.

B.

They define the project schedule and future tasks.

C.

They describe how to setup the traceability tools.

D.

They can easily be traced and reused for future.

Buy Now
Questions 36

A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?

Options:

A.

Surveys or QUESTION NO:naires for the current initiative

B.

Functional Decomposition for the current initiative

C.

Lessons learned from previous initiatives

D.

Process modelling from previous initiatives

Buy Now
Questions 37

An organization is engaged in an effort to streamline the online customer experience. The business analyst (BA) prepares a business analysis information package to discuss the changes the customer will experience. Which one of the following tools will assist the BA in this discussion?

Options:

A.

Context Diagram

B.

Data Dictionary

C.

Visual Prototype

D.

Business Rules

Buy Now
Questions 38

A passport agency has recently deployed an online system where customers can apply for, amend, and renew passports. The expected volumes have not been realized and as a result, the agency has not achieved the projected savings. A business analyst (BA) has been asked to investigate the potential causes of this shortfall by understanding the trends, patterns. and volumes at a detailed level. What method of requirements elicitation should the BA start with?

Options:

A.

Data Mining

B.

Mind Mapping

C.

Business Rules Analysis

D.

Interviews

Buy Now
Questions 39

A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?

Options:

A.

Stakeholders may refuse the solution.

B.

Requirements metrics may not be measurable.

C.

The BA may significantly impact other aspects of the project timeline.

D.

The business need may change.

Buy Now
Questions 40

Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second BA. The other BA explains that these details, along with several other items mentioned in the checklist, are required to:

Options:

A.

select elicitation techniques.

B.

prepare stakeholders.

C.

secure supporting material.

D.

understand scope of elicitation.

Buy Now
Questions 41

A new regulation is introduced that the project must comply with to remain competitive and industry compliant. Management wants to understand the effect of this new requirement on the project. What will the business analyst (BA) use to evaluate the change?

Options:

A.

Process Modelling

B.

Domain Knowledge

C.

Traceability

D.

Impact Analysis

Buy Now
Questions 42

The business analysis (BA) team is evaluating a new commercial off-the-shelf (COTS) application that will be implemented in the coming months. The company has over 20 legacy systems deployed. The Chief Information Officer (CIO) is worried about the need for integration and that some key linkages are missing.

What is the BA team evaluating?

Options:

A.

Technology and infrastructure

B.

Industry standard architecture

C.

Service oriented architecture

D.

Business architecture

Buy Now
Questions 43

A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of requirements to the PM and director, while creating a summarized version for the VP and CIO. Which aspect of requirement specification and modeling was the BA performing?

Options:

A.

Perform stakeholder analysis

B.

Organize requirements categories

C.

Determine approval authority

D.

Implement appropriate level of abstraction

Buy Now
Questions 44

A business analyst (BA) has elicited requirements for a new system. A subset of these requirements refers to judging the performance of the system, such as efficiency, capacity, security, and scalability. What technique is used to examine and group these requirements?

Options:

A.

Functional decomposition

B.

Scope model

C.

Trace requirements

D.

Non-functional requirements analysis

Buy Now
Questions 45

A business analyst (BA) must model information characteristics across multiple information systems for a project. What type of model captures this information?

Options:

A.

Interface analysis

B.

Business capability analysis

C.

Decision analysis

D.

Force field analysis

Buy Now
Questions 46

A business analyst (BA) worked with two stakeholders to finalize the access rights related requirements for an internal software application. According to the first stakeholder “Comments, once entered in the application, should be stored for 365 days and should not allow the users to delete”. According to the second stakeholder, “The users with super administrator privileges should be able to add/delete/modify every page/section in the entire application.” Which characteristic does this pair of requirements fail to meet?

Options:

A.

Concise

B.

Consistent

C.

Complete

D.

Complex

Buy Now
Questions 47

The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system. Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:

Options:

A.

show all of the decision points in the business process.

B.

illustrate the relationships between relevant requirements.

C.

capture all users that will be impacted by the project.

D.

detail the inner workings of the system being changed.

Buy Now
Questions 48

A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group, individually, asking Questions about current business processes. The BA compares the information obtained during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?

Options:

A.

Verification of requirements

B.

Validation of requirements

C.

Confirmation of elicitation results

D.

Capture of elicitation outcomes

Buy Now
Questions 49

A business analyst (BA) is working on a complex project involving many stakeholders for which the business case has been previously completed and signed off. After an organizational restructure, new stakeholders have been assigned to the project working group, but do not see the value in the project outcomes and refuse to collaborate. What is a guideline or tool the BA can use to focus stakeholders on a common goal?

Options:

A.

A business requirements document

B.

An alternate stakeholder plan

C.

A stakeholder matrix

D.

A future state description

Buy Now
Questions 50

A business analyst (BA) is conducting a workshop with the purpose of analyzing a business process. Stakeholders of different business units are in attendance. Each stakeholder is able to explain their unit's contribution to the process, however, there is no end to end process owner who can provide a consolidated view. Which technique should the BA use to compare the stakeholder's inputs against each other in order to check for consistency and omissions?

Options:

A.

Schedule a follow-up workshop to give more time for additional input

B.

Create a use case scenario that describes the process step by step

C.

Develop a process model with swimlanes to highlight the handoff points

D.

Create a logical data model with the information elicited

Buy Now
Questions 51

The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change. What should the BA review before the meeting?

Options:

A.

Minutes from the last steering committee meeting

B.

Organizational structure of the impacted department

C.

Functional design specification of the existing system

D.

Current list of funded initiatives for the current year

Buy Now
Questions 52

You are the business analyst for your organization and you're creating a business analysis communication management plan. In your plan, you want to address the different locales and culture and the communication needs that may affect the business analysis approach. Which one of the following elements should not be included in the cultural analysis of the plan?

Options:

A.

Relationship to task completion

B.

Relationship to authority

C.

Relationship to religion

D.

Relationship to time

Buy Now
Questions 53

An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?

Options:

A.

Select an extreme programming approach

B.

Review current approach with key stakeholders

C.

Follow a predictive approach

D.

Choose an agile programming approach

Buy Now
Questions 54

Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?

Options:

A.

Project team directory

B.

Project organization chart

C.

Project scope statement

D.

Project charter

Buy Now
Questions 55

Which one of the following terms is not a business analysis planning and monitoring approach?

Options:

A.

Structured walkthroughs

B.

Decision analysis

C.

Requirements elicitation

D.

Process modeling

Buy Now
Questions 56

A business analyst (BA) has been hired to validate a project's requirements. A series of meetings with stakeholders have been scheduled to walk through each requirement as it relates to the desired future state of the organization. The desired outcome of this exercise is to ensure that all requirements:

Options:

A.

link to user stories.

B.

are articulated correctly.

C.

are funded by the business sponsors.

D.

support the delivery of needed value.

Buy Now
Questions 57

A business analyst in her organization has identified all of the terminology of the solution, the acronyms the organization will use, and the nomenclature of her department where the endeavor will take place. Where should all of this information actually be stored?

Options:

A.

WBS

B.

Business analysis register

C.

Terminology register

D.

Data dictionary

Buy Now
Questions 58

Which basis for prioritization allows the project team to work initially with lower-risk requirements first?

Options:

A.

Quantitative ranking

B.

Positive risk ranking

C.

Relationship to other requirements

D.

Implementation difficulty

Buy Now
Questions 59

Henry is meeting with Janet, the business analyst of the organization. They are discussing an opportunity to create a new service their company can provide, though the startup of the service would take time and an investment. Henry wants Janet to explore the possibility of this new venture. What activity is Henry asking Janet to complete?

Options:

A.

Brainstorm the business need.

B.

Create a data diagram for the service.

C.

Define the business need.

D.

Elicit the requirements of the proposal.

Buy Now
Questions 60

In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?

Options:

A.

Business analysis approach

B.

Stakeholder tolerance for risk

C.

Stakeholder list, roles, and responsibilities

D.

Business analysis performance assessment

Buy Now
Questions 61

A business analyst (BA) wants to check the completeness of requirements defined after meeting with project stakeholders. A group of subject matter experts (SMEs) has been identified and invited to a workshop to walk through the requirements. What must the BA do to ensure a shared understanding of requirements?

Options:

A.

Align requirements to the organizational strategy

B.

Prioritize requirements according to expected stakeholders value

C.

Ensure requirements attributes are consistent for ease of access

D.

Determine the format to present the requirements to the SMEs attending the workshop

Buy Now
Questions 62

Stakeholder requirements were approved for a business process reengineering initiative along with the creation of a roadmap.

Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) modify in the stakeholder requirements?

  • Requirement attribute values

  • Requirement description

  • Requirement performance measures

Options:

A.

Scope model

Buy Now
Questions 63

A business analyst (BA) has set up a number of elicitation workshops with key subject matter experts (SMEs) on a new project. All SMEs have accepted the workshop invitations except for the legal SME who has not responded to any invitations. The first workshop is scheduled for next week and the BA has tried unsuccessfully to reach the legal SME by phone. How should the BA proceed?

Options:

A.

Re-check the legal SMEs schedule and re-arrange all of the workshops based on vacancies in his or her public calendar

B.

Drop by the legal SMEs desk and have an informed chat about how important his or her involvement and input is on the project

C.

proceed with the first workshop and capture the non-response as a project issue for the project manager to address

D.

Escalate the non-response to the legal SMEs manager via email and request that they make the legal SME attend

Buy Now
Questions 64

A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?

Options:

A.

Decision modelling

B.

SWOT analysis

C.

Mind mapping

D.

Functional decomposition

Buy Now
Questions 65

In a project meeting, stakeholders presented conflicting views on how the business analysis process should be conducted, leading to the sponsor becoming very upset. If a similar situation arises in the future, what can the business analyst (BA) do to avoid the situation?

Options:

A.

Communicate with each stakeholder individually

B.

Obtain stakeholder signoff on the approach

C.

Develop a cleaner RACI matrix

D.

Obtain approval for the business case

Buy Now
Questions 66

A solution that was implemented several years ago has achieved its stated objective of consolidating data from multiple sources. However, end user feedback reveals problems and inefficiencies. What should the business analyst (BA) do first?

Options:

A.

Perform a root cause analysis

B.

Recommend corrective measures

C.

Identity any lessons learned

D.

Revise the business objectives

Buy Now
Questions 67

A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications which are not being updated. What is the first thing that a business analyst (BA) should consider?

Options:

A.

Conducting a vendor assessment

B.

Performing an interface analysis

C.

Identifying constraints and dependence

D.

Developing process and data models

Buy Now
Questions 68

While gathering information during a requirements workshop, a subject matter expert states that it is likely that an organizational restructure will occur in one of the business departments that will be utilizing parts of the new system. As such, the business analyst (BA) should:

Options:

A.

ask the project sponsor to confirm whether and when the restructure will occur.

B.

record a risk that requirements may change and further explore the likelihood and impact of the risk.

C.

note the constraint that the solution must be flexible to accommodate different roles after implementation.

D.

proceed as if the business unit will not be restructured and wait for the organization to confirm otherwise.

Buy Now
Questions 69

An organization is planning to launch an exciting new service that has never been offered before. The expectations are that the service will be extremely popular with young families but, because the organization wants to keep it a secret until launch day. there is no way of knowing whether this is correct. Why does the business analyst (BA) suggest identifying high customer demand by young families as an "assumption?

Options:

A.

To assess the costs and benefits accurately

B.

To prove the idea is correct

C.

To manage the associated risks

D.

To provide a benchmark future change

Buy Now
Questions 70

The business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?

Options:

A.

The level of experience with the repository tool

B.

The number of stakeholders to be consulted

C.

The size and complexity of the change

D.

The governance and engagement approach to be used

Buy Now
Questions 71

The business analyst (BA) is helping the business stakeholders prioritize requirements for a new customer portal for managing orders, delivery, and payment information. A number of requirements address compliance with regulations regarding access for people with disabilities. What factor should the BA use to guide the stakeholders when assigning a priority for these specific requirements?

Options:

A.

Dependencies

B.

Penalties

C.

Risk

D.

Stability

Buy Now
Questions 72

The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact to the staff once the strategy has been implemented. What must the business analyst (BA) do to address concerns of the CEO?

Options:

A.

Identify required cultural changes

B.

Perform a cost-benefit analysis of the strategy

C.

Ensure requirements are easily accessible

D.

Align the new capabilities to the company's architecture

Buy Now
Questions 73

A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?

Options:

A.

Ensure test scenarios conform to business requirements

B.

Choose an appropriate format to communicate requirements

C.

Analyze requirements to remove unnecessary components

D.

Align business requirements to organizational strategy

Buy Now
Questions 74

A business analyst (BA) has completed multiple workshops involving a number of stakeholders including the project manager however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?

Options:

A.

The project manager should decide which requirement is relevant.

B.

The BA should select which requirements are correct.

C.

The project manager should model requirements in a review meeting.

D.

The BA should model the elicited requirements in a review meeting.

Buy Now
Questions 75

A finance manager wants to begin a new project to replace the existing expenses processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?

Options:

A.

Submission processes to determine which activities can be fully automated

B.

Business process to uncover inefficiencies and falling control points

C.

Enterprise information model to ensure definitions are still valid

D.

Finance solution vendors for inclusion in a Request for information

Buy Now
Questions 76

A business analyst (BA) is defining relationships between business requirements and solution components. Which guideline will the BA use to accomplish this?

Options:

A.

Change Strategy

B.

Solution Scope

C.

Solution Objectives

D.

Domain Knowledge

Buy Now
Questions 77

A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?

Options:

A.

Ask the project sponsor for additional funding

B.

Escalate the request to the project manager for reevaluation of the plan

C.

Spend the required effort to develop the detail

D.

Explain that the degree of effort may not be necessary at this stage

Buy Now
Questions 78

A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?

Options:

A.

Change the priority of the requirements by performing are ranking

B.

Consult with the business owner to discuss possible trade-oils

C.

Implement the requirements that the project team considers important

D.

Execute the requirements that the business owner identified

Buy Now
Questions 79

Project work is taking place to evaluate whether a system's requirements can be met via creating internally, purchasing from others, or a combination of the two. What goal is addressed by this analysis?

Options:

A.

Developing the project plan

B.

Outlining the change control strategy

C.

Defining the solution approach

D.

Validating the requirements

Buy Now
Questions 80

You are the business analyst for your organization and you're using a plan-driven approach to business analysis processes. In this environment, what types of communications are most likely required to be used in regard to requirements?

Options:

A.

Informal

B.

Ad hoc

C.

Face-to-face

D.

Formal

Buy Now
Questions 81

You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?

Options:

A.

A change management system

B.

A repository

C.

Requirements register

D.

A project scope statement

Buy Now
Questions 82

Which one of the following statements best describes the purpose of allocating requirements?

Options:

A.

Optimize efficiency and link to productivity.

B.

Limit the risk exposure.

C.

Maximize the business value.

D.

Increase productivity through efficiency.

Buy Now
Questions 83

All of the following are inputs to the task assess organizational readiness except for which one?

Options:

A.

Enterprise architecture

B.

Solution Scope

C.

Stakeholder concern

D.

Risk register

Buy Now
Questions 84

There are three business analysis planning techniques that a business analyst can use to help plan business analysis processes. Which one of the following is not one of the three techniques?

Options:

A.

Process modeling

B.

Progressive elaboration

C.

Decision analysis

D.

Structured walkthrough

Buy Now
Questions 85

There are four inputs to the plan business analysis activities. Which one of the following is not an input to the plan business analysis activities process?

Options:

A.

Stakeholder list, roles, and responsibilities

B.

Organizational process assets

C.

Business analysis approach

D.

List of identified risks

Buy Now
Questions 86

When a business analyst is using alternative generation, what should she always include as an output?

Options:

A.

The cost of all requirements, some requirements, and a few core requirements

B.

The schedule of implementation for each solution

C.

The option of doing nothing

D.

The cost of each solution

Buy Now
Questions 87

What is the purpose of managing the solution scope and requirements from a business analyst's objective?

Options:

A.

To complete business analysis activities as quickly as possible

B.

To obtain and maintain requirements approval from the sponsoring client about the solution scope

C.

To obtain and maintain consensus among key stakeholders for the overall solution scope

D.

To complete business analysis activities as accurately as possible

Buy Now
Questions 88

A business analyst must consider the business value a solution brings in relation to the cost of implementing the desired solution. Suppliers will often be limited in the amount of requirements they can implement based on the allocated resources. If there are not enough resources to implement all of the solutions, what can the business analyst create to justify the additional funds for the implementation?

Options:

A.

Business case

B.

Cost analysis

C.

Risk assessment with positive risk analysis

D.

Benefits-cost ratio

Buy Now
Questions 89

In order to plan the business analysis approach, the business analyst must understand the organizational process needs and what other thing?

Options:

A.

Operation of organizations and the objectives of business analysis

B.

Consideration of risk and reward

C.

Purpose of the proposed solution

D.

Stakeholders' threats and perceived threats

Buy Now
Questions 90

The project manager has tasked the business analyst (BA) to collect a performance measure on the solution implemented in the latest release. Which of the following considerations can help the BA obtain that information?

Options:

A.

Sample size

B.

Solution size

C.

Performance variance

D.

Risk assessment

Buy Now
Questions 91

A business analyst (BA) is proposing design options and a number of opportunities are occurring that need to be understood further. One particular opportunity will prevent different stakeholders from performing the same function in distinctly different ways. What type of opportunity is this?

Options:

A.

Reduced barriers to entry

B.

improved access to information

C.

increased efficiency

D.

Additional capabilities

Buy Now
Questions 92

For a new account payable (AP) solution, the solution owner has provided the business analyst (BA) with goals the AP management team would like the solution to support. To ensure the solution meets these needs, the BA documents key performance indicators (KPIs). Which of the following is an example of a KPI?

Options:

A.

“The solution will send payment notification to the account holder after successful processing

B.

“The solution will report the average number of days an account payment is outstanding”

C.

“The solution will reduce the payment processing time from three days to two days”

D.

“The solution will enable account holders to make account payments via a web form”

Buy Now
Questions 93

A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?

Options:

A.

Predictive

B.

Reactive

C.

Proactive

D.

Adaptive

Buy Now
Questions 94

A business analyst (BA) is assigned a new project and is beginning to prepare for elicitation. Which task must the BA complete before preparation of the elicitation process can begin?

Options:

A.

Coordinate meeting logistics

B.

Approve anticipated expenses

C.

Gather contact information of stakeholder

D.

Collect information on the business need

Buy Now
Questions 95

A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the first activity the BA performs to understand the effect of the proposed change is to:

Options:

A.

determine whether stakeholders are available for further elicitation.

B.

consult with the technical team for technical feasibility.

C.

determine whether the additional requirement is traceable to a need.

D.

check with the project manager for timeline and budget metrics.

Buy Now
Questions 96

A general insurance company wants to enter a new segment that has the potential for high profit and little competition. The business analyst (BA) was asked to prepare a presentation for key stakeholders to show how the new segment will deliver value for stakeholders. Which of the following is best suited for this purpose?

Options:

A.

Capability analysis man

B.

Business architecture

C.

Business model canvas

D.

Business case

Buy Now
Questions 97

A business analyst (BA) is working on an effort to upgrade a system to take advantage of new technology. Most of the end users with the business knowledge and IT staff with technical knowledge of the system are no longer with the company. What can the BA evaluate to better understand the extent of the effort?

Options:

A.

Benefits of upgrading the system

B.

Communication platform to be used

C.

Number of business areas impacted

D.

Collection of performance measures

Buy Now
Questions 98

A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modelling formats will show the requirements for both systems side by side?

Options:

A.

Activity Flow

B.

Matrix

C.

Glossary

D.

Bubble Chart

Buy Now
Questions 99

A company has bought a customizable software product and the vendor's business analyst (BA) is visiting the company's office to perform a requirements assessment. The business sponsor expresses an interest in improving a specific process that is in scope. What should the BA do?

Options:

A.

Develop a data model

B.

Create a process model

C.

Review data flow diagrams

D.

Observe the activity

Buy Now
Questions 100

A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?

Options:

A.

Compare requirements with compliance requirements

B.

Determine the communication plan for requirements

C.

Reassure the project sponsor that testing will be conducted diligently

D.

Ensure requirements are traceable up to user acceptance testing

Buy Now
Questions 101

A business analyst (BA) is managing stakeholder collaboration to ensure positive reactions are capitalized upon. There is uncertainty as to whether the correct stakeholders have been identified. Which technique can be used to correct this situation?

Options:

A.

Functional decomposition

B.

Lessons learned

C.

Risk analysis

D.

Interviews

Buy Now
Questions 102

An organization is experiencing long contracting life cycles when establishing annual contracts with its customers. Upon initial investigation, the outdated application was thought to be the cause, however based on further analysis the business process is found to be flawed. The business analyst (BA) wants to model the people involved in the process. Which of the following techniques models the responsibilities of these stakeholders?

Options:

A.

Roles and Permissions Matric

B.

Data Flow Diagram

C.

Use Cases and Scenarios

D.

Activity Flow

Buy Now
Questions 103

After a number of requirements elicitation workshops, the business analyst (BA) notices that two business stakeholders did not speak up during any of the discussions. What should the BA do in the next workshop?

Options:

A.

Allow only the two stakeholders to speak, so that other stakeholders are able to hear their input.

B.

Proceed as normal, assuming that the two business stakeholders will speak up if and when they are ready

C.

Ask all attendees for their input, ensuring that each stakeholder is given time to speak and provide their opinion

D.

Omit the two stakeholders from the next meeting since they do not seem to be engaged or interested

Buy Now
Questions 104

Two stakeholders are arguing over which model to use for describing requirements. One insists that using an activity diagram is superior while the other prefers a state diagram. How should the business analyst (BA) resolve the conflict?

Options:

A.

Explain that the models are complementation to each other

B.

Allow both stakeholders to work on the models independently

C.

Introduce a third model type so that neither stakeholder prevails

D.

Suggest a fusion model that integrates activity and state diagrams

Buy Now
Questions 105

A business analyst (BA) plans to organize a focus group to bring all the interested parties together and discuss the issues and possible risks for the new initiative. Due to the geographical differences of each participant a videoconferencing service will be used to satisfy stakeholder preferences. Which approach is the BA defining?

Options:

A.

Stakeholder analysis

B.

Issue management

C.

Release planning

D.

Stakeholder collaboration

Buy Now
Questions 106

A deployed loan product was funded with the expectation of prepayment risk reduction. Initially key performance indicators would be to take similar loan prepayment rates over the previous 10-year period and compare it with the new product. After implementation, the business analyst (BA) determines that the decade old housing market is vastly different. Which of the following should the BA consider for validity of performance measures?

Options:

A.

Currency

B.

Timing

C.

Sample size

D.

Frequency

Buy Now
Questions 107

A government agency has initialed a project to implement a customer registry that will be shared across multiple agencies. Early estimates indicate there will be hundreds of requirements. While determining the requirements traceability approach, what factor takes precedence?

Options:

A.

Number of defects

B.

Cost of tracing

C.

Number of stakeholders

D.

Cost of testing

Buy Now
Questions 108

A recent survey shows that a newly implemented system has features that the users have never used. Upon reviewing the survey report, the Chief Executive Officer (CEO) highlighted that the company must avoid future implementations with functionality that does not provide any business value. What must the business analyst (BA) do to ensure future requirements meet a business need?

Options:

A.

Consider business relevance while tracing requirements

B.

Choose appropriate format to communicate requirements

C.

Ensure test scenarios align to business requirements

D.

Facilitate a focus group with users to get feedback

Buy Now
Questions 109

A business analyst (BA) is defining constraints for a project. Which of the following is a valid constraint?

Options:

A.

“The solution must be implemented in six (6) months.”

B.

“The solution must increase sales by 20%.”

C.

“The solution must promote workplace safety.”

D.

“The solution must reduce support calls by 20%.”

Buy Now
Questions 110

There are competing needs from the different business areas that will use a new system. The business analyst (BA) sets up a weekly meeting with a structured agenda to review the total effort, cost, business impact and risk of each requirement with the business leads to determine what is included in each release of the solution. What approach has the BA defined?

Options:

A.

Prioritization approach

B.

Communication approach

C.

Collaboration approach

D.

Traceability approach

Buy Now
Questions 111

A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?

Options:

A.

Ensure users are trained based on requirements

B.

Apply quality control on requirements

C.

Utilize requirements documentation template

D.

Maintain requirements based on priority

Buy Now
Questions 112

A business analyst (BA) is reviewing the elicitation results of several workshops in order to decide which technique to use to model the requirements. The elicitation identified user roles needed in a future solution, the functionality needed by each of these roles, and how the desired interaction with the solution should look.

Which technique allows the BA to model this type of information?

Options:

A.

Process models

B.

Roles and permission matrix

C.

Use cases and scenarios

D.

Sequence diagrams

Buy Now
Questions 113

Verification of requirements on the projects have highlighted an issue regarding misunderstanding of design models among key stakeholders. A major reason cited for the misunderstanding was the technical jargon and models used in the documentation. What must the business analyst (BA) do to improve the understanding?

Options:

A.

Ensure completeness within the models used

B.

Verify that elements within the models are used consistently

C.

Represent design models using common terminology

D.

Check for compliance with organization standards

Buy Now
Questions 114

A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases. Which requirements attribute can the BA include to allocate the requirements to the proper phase?

Options:

A.

Status

B.

Author

C.

Priority

D.

Source

Buy Now
Questions 115

A business analyst (BA) is currently verifying the accuracy and consistency of information obtained from the stakeholders. The BA needs to identify additional information. What should the BA do next?

Options:

A.

Perform data modelling

B.

Conduct elicitation activities

C.

Meet with the sponsor

D.

Consult with the project manager

Buy Now
Questions 116

A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?

Options:

A.

Record a defect for fixing

B.

Consult with the project manager

C.

Revert back the changes

D.

Check the audit history of changes

Buy Now
Questions 117

A business analyst (BA) is creating a business process model (BPM) showing how the organization will handle errors reported on its website. The BA held a workshop with stakeholders about how the process might work. The BA was also given an instruction manual about a similar error-handling situation, but was advised that some minor aspects are not applicable to the new process. How can the BA use the manual?

Options:

A.

Ignore the manual's information when creating the BPM since it is about a different situation

B.

Identify the discrepancies in process between the manual and the workshop results and resolve these with stakeholders

C.

Create a new version of the manual based on the original

D.

Rely on the manual to create the BPM and ignore the interview results because no single stakeholder has the whole picture of the process

Buy Now
Questions 118

You are the business analyst for a large project in your organization. While your company prefers face-to-face communications there are many stakeholders located in different geographical locations. How can you still effectively serve as a business analyst when the stakeholders are not collocated?

Options:

A.

You will need the stakeholders to periodically gather in one locale.

B.

You will need to travel on a regular rotation to each of the geographical locations to complete the business analyst duties.

C.

Add more business analysts in each of the geographical location.

D.

You will need to implement videoconferences.

Buy Now
Questions 119

You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which of the following will help determine whether a plan- driven or change-driven approach is appropriate?

Each correct answer represents a complete solution.

Options:

A.

Organizational process assets

B.

Expert Judgement

C.

Business need

D.

Penalty of not seizing the opportunity

Buy Now
Questions 120

Which of the following describes the organizational policies, procedures, forms, and methodologies the business analyst is to follow?

Options:

A.

Organizational process asset

B.

Enterprise architecture

C.

Business need

D.

Matrix structure

Buy Now
Questions 121

Which of the following are documented approaches to the business analysis work? Each correct answer represents a complete solution.

Options:

A.

Deming's Quality Circle

B.

Lean

C.

Six Sigma

D.

Waterfall approach

Buy Now
Questions 122

You are working with the project stakeholders to analyze and prioritize their requirements for the project. One of the project requirements is to achieve a high-level of customer satisfaction for the project deliverable. What is the danger in this project requirement?

Options:

A.

Achieving customer satisfaction is a risk, as the project manager cannot control how satisfied the customer will be with the project deliverables.

B.

Achieving customer satisfaction is an assumption and should be documented in the project scope.

C.

Achieving customer satisfaction should always map to the quality requirements for the project.

D.

Achieving customer satisfaction is a subjective requirement and entails a high level of risk of being successfully accomplished.

Buy Now
Questions 123

According to 'A Guide to the Business Analysis Body of Knowledge', when should the business analyst and an organization actually start requirements allocation?

Options:

A.

As soon as a budget has been created

B.

After approval of the requirements

C.

After the project charter

D.

As soon as the solution approach is determined

Buy Now
Questions 124

The RGQ Organization utilizes a change log. What is a change log?

Options:

A.

It is a document that tracks all unauthorized changes to the project solution.

B.

It is a document that records all change requests for the project.

C.

It is a document that tracks the changes that have been received, including their implementation to the project solution.

D.

It is a document that tracks all characteristics and status of changes that have been received.

Buy Now
Questions 125

All of the following stakeholders participate in the prioritization of requirements except for which one?

Options:

A.

Project team

B.

Implementation subject matter expert

C.

Domain subject matter expert

D.

Project manager

Buy Now
Questions 126

You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders who are located in offices around the world. Because these stakeholders are dispersed, what are likely to increase in this endeavor as opposed to a collocated group of stakeholders?

Options:

A.

Face-to-face meetings

B.

Communication needs

C.

Risks

D.

Costs

Buy Now
Questions 127

You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis. Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

Options:

A.

Requirements-driven approach

B.

Change-driven approach

C.

Plan-driven approach

D.

Value-driven approach

Buy Now
Questions 128

You are the business analyst for your organization and you're preparing to elicit requirements from the stakeholders. You've gathered several inputs to help with the elicitation process. Which input(s) will be used to ensure that you understand the type of information that should be elicited from the stakeholders?

Options:

A.

Stakeholder list

B.

Risk assessment

C.

Business need

D.

Roles and responsibility

Buy Now
Questions 129

You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which one of the following is a primary input to the business analysis approach?

Options:

A.

The business analysis approach will be shaped by the problem or opportunity faced by the organization.

B.

The business analysis approach will be shaped by the penalty of not seizing the opportunity.

C.

The business analysis approach will be shaped by the time allowed for business analysis planning.

D.

The business analysis approach will be shaped by the risks faced by the organization.

Buy Now
Questions 130

When a business analyst completes the task of organizing requirements, he is completing two key objectives. What are the two objectives?

Options:

A.

The business analyst should categorize the requirements first by functional or non-functional decomposition and then structure the categories by identified prioritization elements.

B.

The business analyst should strive to find logic in the organizational structure and to establish a prioritization approach on key elements.

C.

The business analyst should aim to understand which models are appropriate for the business domain and solution scope and to identify model interrelationships and dependencies.

D.

The business analyst should work with stakeholders to organize defined categories and then to structure each category by a key performance indicator.

Buy Now
Questions 131

You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?

Options:

A.

Parametric estimate

B.

Planning

C.

Report project

D.

Timeboxing

Buy Now
Questions 132

Which one of the following business analysis techniques for analyzing business goals converts the business goals into achievable objectives and measures?

Options:

A.

Benchmarking

B.

Root cause analysis

C.

Functional decomposition

D.

Business rules analysis

Buy Now
Questions 133

Which one of the following is not an event-based elicitation technique?

Options:

A.

Focus group

B.

Interface analysis

C.

Interview

D.

Workshop

Buy Now
Questions 134

You are the business analyst for your organization and are leading a presentation about an identified problem. This presentation will help the stakeholders to understand the problem and it will help you when you begin to elicit requirements from the stakeholders. Which type of learner learns best through the presentation of models?

Options:

A.

Kinesthetic learners

B.

Auditory learners

C.

Communication model learners

D.

Visual learners

Buy Now
Questions 135

As a business analyst, you'll often have to coach stakeholders on the processes, knowledge areas, and tasks

you'll complete for an organization. One of the knowledge areas is enterprise analysis. This knowledge area completes all of the following activities except for which one?

Options:

A.

It defines the nature of a solution that meets that need.

B.

It identifies business needs, problems, or opportunities.

C.

It justifies the investment necessary to deliver that solution.

D.

It manages and expresses requirements to a broad and diverse audience.

Buy Now
Questions 136

According to the business analysis book 'A Guide to the Business Analysis Body of Knowledge', which your exam is largely based on, almost all methodologies fit somewhere along a spectrum between plan-driven and what other methodology?

Options:

A.

Risk-driven

B.

Cost-driven

C.

Change-driven

D.

Reward-driven

Buy Now
Questions 137

What do business goals and objectives of enterprise analysis actually describe?

Options:

A.

Business goals and objectives describe the increased revenue that the organization is seeking to gain.

B.

Business goals and objectives describe the solution scope that the organization is seeking to accomplish.

C.

Business goals and objectives describe the ends that the organization is seeking to achieve.

D.

Business goals and objectives describe the desired future state of problems.

Buy Now
Questions 138

You are the business analyst for your organization. You are currently working with Steve on the organize requirements process. You and Steve have elected to use the user stories approach for this process. What is the user stories approach for requirements organization?

Options:

A.

Stakeholders' objectives are described to identify the requirements that the solution will need to support.

B.

Stakeholders are interviewed and their stories are recorded as part of the requirements.

C.

Stakeholders are interviewed and their experiences are recorded to help identify the requirements.

D.

Stakeholders' experiences equate to the stakeholder requirements.

Buy Now
Questions 139

Beth is the business analyst for her organization and she wants to be certain that she and her team follow the correct procedures for enterprise analysis. What document can provide the governances for enterprise analysis efforts?

Options:

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Business analysis plans

D.

Project charter

Buy Now
Questions 140

Tracy is a business analyst for her organization and she's gathered and identified the needed requirements for the solution scope. What must Tracy do before she can begin managing the requirements? Choose the best answer.

Options:

A.

Tracy must decompose the requirements in WBS.

B.

Tracy must create cost-benefits analysis of each requirement to manage the benefits first.

C.

Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.

D.

Tracy must communicate the requirements to the stakeholders for their consent and approval.

Buy Now
Questions 141

When a business analyst completes the elicitation process, she will create four outputs. Which one of the following is an output of the elicitation process?

Options:

A.

Requirements management plan

B.

Resource identification

C.

Stakeholder Concerns

D.

Solution scope

Buy Now
Questions 142

Beth is the business analyst for her organization and she's creating a data dictionary for her organization. All of the following information should be included in the data dictionary for an endeavor Beth is leading except for which one?

Options:

A.

Description

B.

Aliases

C.

Name

D.

Code of account identifier

Buy Now
Questions 143

You are the business analyst for your organization and you're working with the key stakeholders to validate the requirements. In your review, you have determined the business value of each requirement and you've discovered three requirements that do not deliver direct or indirect value to the stakeholders. What should you do with these requirements?

Options:

A.

Determine their purpose in the requirements set.

B.

Justify their existence.

C.

See if the requirements are integrated with other requirements.

D.

Remove them from the requirements set.

Buy Now
Questions 144

A business analyst has just completed an elicitation event. What stakeholder(s) is/are involved in the documentation of the elicitation results?

Options:

A.

Business analyst and key stakeholders

B.

Business analyst

C.

Project manager, project team, and business analyst

D.

Project manager, business analyst, and project sponsor

Buy Now
Questions 145

You are the business analyst for your organization. You've believed that your solution can actually be purchased from outside vendor rather than trying to create the solution internally. You decide to ask the vendor to provide a fee for their services based on the statement of work. What document will you give the vendor along with the statement of work?

Options:

A.

Request for quote

B.

Contract terms

C.

Request for proposal

D.

Purchase order

Buy Now
Questions 146

You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. This approach helps to find out the following except for which one?

Options:

A.

Which stakeholders need to be involved in the decision?

B.

Who will be consulted regarding and informed of the approach?

C.

Who will be observed in job shadowing?

D.

What is the rationale for using it?

Buy Now
Questions 147

What is problem tracking?

Options:

A.

It's the identification of missing requirements.

B.

It's the assumption that there will be defects in the requirements that must be resolved.

C.

It's the documentation of known defects in the requirements.

D.

It's the identification and management of any issues for resolution.

Buy Now
Questions 148

There are three inputs for stakeholder analysis. Which input describes the existing organizational units and their interactions with one another?

Options:

A.

Business need

B.

Enterprise architecture

C.

Matrix structure

D.

Organizational process asset

Buy Now
Questions 149

What type of requirements elicitation technique is the Delphi Technique?

Options:

A.

Survey

B.

Workshop

C.

Prototyping

D.

Round table

Buy Now
Questions 150

You are the business analyst for your organization and you're working to identify all of the stakeholders within your organization and outside

your organization to ensure that you've captured the correct requirements for a project. Which one of the following techniques can be best suited for identifying stakeholders?

Options:

A.

Interviews

B.

User stories

C.

Acceptance and Evaluation Criteria

D.

Risk analysis

Buy Now
Questions 151

You are documenting the requirements attribute for your requirements management plan. Which attribute would you use if you want to identify the person who created the requirements?

Options:

A.

Absolute reference

B.

Ownership

C.

Requirements sponsor

D.

Author of the requirements

Buy Now
Questions 152

You are the business analyst for your organization and you've identified a business need. In order to satisfy this business need, you believe that your organization will need to hire three electrical engineers, purchase equipment, and likely provide training to existing resources. What process is being described in this scenario?

Options:

A.

Communication needs

B.

Assessment of capability gaps

C.

Resource allocation

D.

Resource procurement

Buy Now
Questions 153

Before requirements can actually be approved to be managed, what must be true about the requirements?

Options:

A.

Requirements must support the solution scope.

B.

Requirements must be approved by the technical review board.

C.

Requirements must support the requirements management plan.

D.

Requirements are governed by the requirements management plan.

Buy Now
Questions 154

A business analyst has determined that there are five possible solutions to a business need. If the business analyst completes the solution assessment on multiple solutions, what is the goal of the assessment?

Options:

A.

The business analyst should determine which solution has the greatest business value.

B.

The business analyst should determine the opportunity cost of each assessment.

C.

The business analyst should only have one solution, not five.

D.

The business analyst should determine which solution is quickest to implement.

Buy Now
Questions 155

Management comes to you and asks you to complete some specifications and models about the current state of the organization.

Management wants you to complete this business analysis activity as soon as possible and report back to them with your findings. What is the primary purpose of the specify and model requirements process?

Options:

A.

To analyze the roles and responsibilities of users within the organization to determine how the processes may be improved.

B.

To analyze the utility function within the organization to determine how risk tolerance may allow for new opportunities.

C.

To analyze the functioning of an organization and to provide an insight into opportunities for improvement.

D.

To analyze the processes of an organization to determine what processes can be improved, removed, or added.

Buy Now
Questions 156

Which technique in organizing requirements is best described as showing the concepts and relationships relevant to the solution or business domain?

Options:

A.

Data flow diagram

B.

Business rules analysis

C.

Data modeling

D.

Functional decomposition

Buy Now
Exam Code: CCBA
Exam Name: Certification of Capability in Business Analysis (CCBA)
Last Update: Apr 29, 2024
Questions: 522
CCBA pdf

CCBA PDF

$28  $80
CCBA Engine

CCBA Testing Engine

$33.25  $95
CCBA PDF + Engine

CCBA PDF + Testing Engine

$45.5  $130