C_TS422_2021 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Questions 4

What are the consequences if the Dispatched operation status is set for a production order operation?

Options:

A.

You can reschedule the operation using midpoint scheduling in a planning table.

B.

You can reschedule the operation using finite scheduling in planning table

C.

You can reschedule the operation using lead time scheduling in a planning table

D.

You can reschedule the order using infinite scheduling in a planing table

Buy Now
Questions 5

Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?

Options:

A.

Planning with final assembly (40)

B.

Make-to-order production (20)

C.

Make-to-stock production (10)

D.

Planning without final assembly (50)

Buy Now
Questions 6

Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider?

Options:

A.

The maximum mater all number length is 40 for external numbers and 18 for internal numbers

B.

The number of leading zeros for internal numbers is client-specific.

C.

In Customizing you can decide by material type whether to use the long material number.

D.

The display template for material numbers applies to all clients.

Buy Now
Questions 7

Your project used process orders for the production of liquid chemicals.

What can you define to ensure that the production flow happens only in physically connected tanks?

Options:

A.

Operation network

B.

Work center hierarchy

C.

Setup matrix

D.

Resource network

Buy Now
Questions 8

Which of the following questions do you have to answer before you start creating a BOM?

Options:

A.

In which storage location is the BOM required?

B.

Which Valid To information is necessary?

C.

Is the material type allowed in the BOM?

D.

What status does the BOM have?

Buy Now
Questions 9

Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

Options:

A.

When multiple operations are maintained for one product

B.

When alternate resources are used within one operation

C.

When multiple planned orders exist on one resource

D.

When multiple production versions are maintained for one product

Buy Now
Questions 10

Which business processes are affected by setting in the order type-dependent parameters?

Options:

A.

Intiate quality inspections.

B.

Select master data.

C.

Define integration to cost accounting.

D.

Implement engineering changes.

Buy Now
Questions 11

Which materials have a negative quantity in a bill of materials or in a recipe?

Options:

A.

Bulk materials

B.

Co-products

C.

By-products

D.

Waste products

E.

Continuous flow materials

Buy Now
Questions 12

Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Non-stock item

B.

Work item

C.

Variable-size item

D.

WBS item

Buy Now
Exam Code: C_TS422_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
Last Update: Feb 5, 2023
Questions: 82
C_TS422_2021 pdf

C_TS422_2021 PDF

$32  $80
C_TS422_2021 Engine

C_TS422_2021 Testing Engine

$38  $95
C_TS422_2021 PDF + Engine

C_TS422_2021 PDF + Testing Engine

$52  $130