Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

C_S4PPM_2021 SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Questions and Answers

Questions 4

Where can you define the scheduling type?

NOTE: There are 3 correct answers to this question.

Options:

A.

In customizing

B.

ON phase level

C.

On project definition level

D.

On task level

Buy Now
Questions 5

You have assigned two resources to the same role resource 1 to calendar week 10 and resource 2 to calendar week 11. You want to re-assign resource 2 to calendar week 10 bar the system does not allow you to do so.

What could be a reason for the system behavior?

Options:

A.

The role demand for the timeframe is too low

B.

The flexible Assignment indicator is active for the rile type in customizing

C.

The edit in parallel indicator is inactive for the role type in customizing

D.

The assigned effort for either of the resource assigned is to high

Buy Now
Questions 6

In project management, a WBS element for accounting integration was created automatically.

What is used to calculate the planned costs of this WBS element?

NOTE: There are 3 correct answers to this question

Options:

A.

Staffing of work in the role

B.

Duration planned on project tasks

C.

Demand planned on project roles

D.

Work planned on project task

Buy Now
Questions 7

What data influence the bottom-up scheduling of a project in portfolio management?

NOTE: There are 3 correct answers to this question.

Options:

A.

Duration of tasks

B.

Project type

C.

Role demands

D.

Relationships between phases

E.

Relationships between tasks

Buy Now
Questions 8

You have defined a financial view for portfolio bucket so that financial values are rolled up.

Which of the following are possible sources for the rollup?

NOTE: There are 3 correct answers to this question

Options:

A.

Project system project

B.

Project management projects

C.

Standalone items

D.

Initiatives

Buy Now
Questions 9

Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question

Options:

A.

10 days

B.

3 months

C.

1 year

D.

2 weeks

Buy Now
Questions 10

You want to control the execution of subsequence phases in project management.

Which indicators must you activate in the phase type in customizing?

NOTE: There are 2 correct answers to this question

Options:

A.

The Release Success phase only after Approval indicator

B.

The approval phase indicator

C.

The completion required indicator

D.

The complete phase when Granting Approval indicator

Buy Now
Questions 11

Which customizing activity do you use to integrate capacity planning of an item with financial planning?

Options:

A.

Define financial integration scenarios

B.

Define portfolio type

C.

Define financial and capacity views

D.

Define financial planning settings

Buy Now
Questions 12

What must you do before you can use multiple currencies in financial planning in portfolio management?

Options:

A.

Select multiple currencies in the portfolio definition

B.

Define a subnet of currencies in portfolio and project management

C.

Select multiple currencies in the portfolio item

D.

Define a subnet of currencies in project system

Buy Now
Exam Code: C_S4PPM_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management
Last Update: Apr 22, 2024
Questions: 82
C_S4PPM_2021 pdf

C_S4PPM_2021 PDF

$28  $80
C_S4PPM_2021 Engine

C_S4PPM_2021 Testing Engine

$33.25  $95
C_S4PPM_2021 PDF + Engine

C_S4PPM_2021 PDF + Testing Engine

$45.5  $130