Questions 4

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 5

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Buy Now
Questions 6

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Buy Now
Questions 7

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Buy Now
Questions 8

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Options:

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Buy Now
Questions 9

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Buy Now
Questions 10

What is the primary benefit of meeting quality requirements?

Options:

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Buy Now
Questions 11

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 12

Managing procurement relationships and monitoring contract performance are part of which process?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Buy Now
Questions 13

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Buy Now
Questions 14

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Buy Now
Questions 15

Which of the following characteristics are found in a functional organizational structure?

Options:

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Buy Now
Questions 16

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Buy Now
Questions 17

Co-location is a tool and technique of:

Options:

A.

Develop Human Resource Plan.

B.

Manage Project Team.

C.

Develop Project Team.

D.

Acquire Project Team.

Buy Now
Questions 18

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Buy Now
Questions 19

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Buy Now
Questions 20

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Buy Now
Questions 21

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Buy Now
Questions 22

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 23

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Questions 24

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Buy Now
Questions 25

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Buy Now
Questions 26

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Buy Now
Questions 27

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 28

A reward can only be effective if it is:

Options:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Buy Now
Questions 29

Stakeholder satisfaction should be managed as a key project:

Options:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Buy Now
Questions 30

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Buy Now
Questions 31

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Buy Now
Questions 32

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 33

The process of identifying and documenting relationships among the project activities is known as:

Options:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Buy Now
Questions 34

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Buy Now
Questions 35

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Buy Now
Questions 36

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Buy Now
Questions 37

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Buy Now
Questions 38

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Buy Now
Questions 39

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 40

Which process involves developing an approximation of the monetary resources needed to complete project activities?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Buy Now
Questions 41

Scope, schedule, and cost parameters are integrated in the:

Options:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

Buy Now
Questions 42

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Buy Now
Questions 43

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 44

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Buy Now
Questions 45

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Buy Now
Questions 46

Which type of graphic is displayed below?

Options:

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Buy Now
Questions 47

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Buy Now
Questions 48

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Buy Now
Questions 49

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Buy Now
Questions 50

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Buy Now
Questions 51

Which element does a project charter contain?

Options:

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Buy Now
Questions 52

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members

B.

possibility of communication misunderstandings

C.

costs associated with travel

D.

costs associated with technology

Buy Now
Questions 53

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Buy Now
Questions 54

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

Options:

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Buy Now
Questions 55

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

17

Buy Now
Questions 56

Perform Integrated Change Control is the process of:

Options:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Buy Now
Questions 57

Which project risk listed in the table below is most likely to occur?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 58

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Buy Now
Questions 59

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Buy Now
Questions 60

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Buy Now
Questions 61

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 62

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Buy Now
Questions 63

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

Options:

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

Buy Now
Questions 64

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Buy Now
Questions 65

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Options:

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Buy Now
Questions 66

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 67

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Questions 68

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

Options:

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Buy Now
Questions 69

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 70

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Buy Now
Questions 71

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7

B.

8

C.

14

D.

16

Buy Now
Questions 72

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Buy Now
Questions 73

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Buy Now
Questions 74

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 75

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

Options:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Buy Now
Questions 76

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Buy Now
Questions 77

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Buy Now
Questions 78

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Buy Now
Questions 79

Organizations perceive risks as:

Options:

A.

events that will inevitably impact project and organizational objectives.

B.

the effect of uncertainty on their project and organizational objectives.

C.

events which could have a negative impact on project and organizational objectives.

D.

the negative impact of undesired events on their project and organizational objectives.

Buy Now
Questions 80

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Buy Now
Questions 81

The product scope description is used to:

Options:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Questions 82

To which process is work performance information an input?

Options:

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 83

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Buy Now
Questions 84

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders' tolerances.

Buy Now
Questions 85

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Buy Now
Questions 86

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Buy Now
Questions 87

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Buy Now
Questions 88

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Buy Now
Questions 89

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Questions 90

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 91

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Questions 92

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Buy Now
Questions 93

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Buy Now
Questions 94

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 95

What are the identified risks for doing excessive decomposition in a WBS?

Options:

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources

Buy Now
Questions 96

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Buy Now
Questions 97

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Buy Now
Questions 98

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 99

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Buy Now
Questions 100

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project

B.

Scope

C.

Contract

D.

Program

Buy Now
Questions 101

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Buy Now
Questions 102

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Buy Now
Questions 103

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Options:

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Buy Now
Questions 104

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Questions 105

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Buy Now
Exam Code: PMI-100
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Aug 17, 2025
Questions: 704
PMI-100 pdf

PMI-100 PDF

$29.75  $84.99
PMI-100 Engine

PMI-100 Testing Engine

$35  $99.99
PMI-100 PDF + Engine

PMI-100 PDF + Testing Engine

$47.25  $134.99