After performing a hardware upgrade from an //M20R2 to a //X20R3-EMEZZ, a customer wants to add a Direct Flash Modules data pack to replace the existing SAS Chassis Data Packs (2x 20TB DPs). What extra hardware is required?
In a situation where iSCSI cards need to be re-used during a controller upgrade, which is a valid transfer path?
An Implementation Engineer is scheduled to install a FlashArray and a DirectFlash Shelf (DFS).
What action should the Implementation Engineer perform?
A customer has purchased a FlashArray//XL. What power cables are required in order to connect this array to rack PDUs?
An Implementation Engineer is beginning a controller upgrade. Which command should be run to stop Purity?
After runningpuredb run giveback --safecommand once CT0 has been upgraded, how long should the Implementation Engineer wait before continuing with the controller upgrade?
Which enablement feature will cause Mirrored Write statistics to appear in the Analysis section of the FlashArray Purity 6.x GUI?
An Implementation Engineer needs to run the puresetup replace procedure on the FlashArray//X during a controller upgrade.
Which command should the Implementation Engineer run on the new controller to determine its model?
A customer needs to have arrays installed and configured with ActiveCluster and ETH replication. The installation document contains 3 IP addresses. How many additional IP addresses are needed?
An Implementation Engineer performs a controller upgrade. What is the command to check I/O health?
Which Purity command can be used to validate I/O is balanced across initiators?
A FlashArray arrives with Purity 5.3.8 applied out of the factory. The account team requests that the array configured with Purity 6.1.21. Which steps should the Implementation Engineer select to meet this requirement?
An Implementation Engineer performing an inventory of hardware for an NDU from an FlashArray//X70R2 to an FlashArray //X90R3 and discovers c complete FlashArray//X90R3 was shipped in place of an NDU kit. What is the minimum hardware the Implementation Engineer should use from this array to complete the NDU?
Which command should an Implementation Engineer use to allow Support access to an array?
A customer has ordered several FlashArrays and wants to have ActiveCluster configured. What is the maximum quantity of arrays supported with ActiveCluster?
A customer has purchased a DirectFlash Shelf, but lacks available space in the same rack as the chassis. There is available space in a rack 6m away. What step should be taken prior to implementation?