Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Which of the following is a strategy to deal with positive risks or opportunities?
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Activity cost estimates are quantitative assessments of the probable costs required to:
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Which of the following is a tool or technique used in the Determine Budget process?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
Which tool or technique is an examination of industry and specific vendor capabilities?
Which document describes the necessary information to determine if a project is worth the required investment?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which input to the Plan Risk Management process provides information on high-level risks?
Which process determines the risks that may affect the project and documents their characteristics?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which process in Project Time Management includes reserve analysis as a tool or technique?
Which process numerically analyzes the effect of identified risks on overall project objectives?
A large portion of a projects budget is typically expended on the processes in which Process Group?
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Change requests are processed for review and disposition according to which process?
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
Which document defines how a project is executed, monitored and controlled, and closed?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Which type of dependency is contractually required or inherent in the nature of the work?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which of the following tools and techniques is used in the Verify Scope process?
In which process is a project manager identified and given the authority to apply resources to project activities?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
Managing procurement relationships and monitoring contract performance are part of which process?
Which of the following project documents is an input to the Control Scope process?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
Which of the following types of a dependency determination is used to define the sequence of activities?
Which of the following characteristics are found in a functional organizational structure?
A tool or technique in Perform Quality Control that a project manager would use is:
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Which of the following set of elements is part of an effective communications management plan?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
What is the project manager's responsibility in Project Integration Management?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?
Which of the following is an example of an internal factor that influences the outcome of the project?
Match each dimension of the communications management plan to its corresponding focus.
A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.
Which entities will the project manager attempt to influence?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
Which set of activities should a project manager use as part of the Develop Team process?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
Which of the following documents ate created as part of Project Integration Management?
How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?
Once the make-or-buy analysis is completed, which document defines the project delivery method?
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
Match the project manager's sphere of influence with the associated primary role.
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
What is a tailoring consideration for the application of Project Risk Management processes?
Which is the tool or technique that is used to obtain the list of activities from the work packages?
What can increase the complexity of the Manage Stakeholder Engagement process?
Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
Which is a list of organizational systems that may have an impact on a project?
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
What does expert judgment provide as an input to the resource management plan?
A project stakeholder is requesting changes to the project plan. Which process group addresses this?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
A team receives four different requests from separate stakeholders related to one application Match each requirement with its corresponding type of change request.
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?
A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
A graphic display of project team members and their reporting relationships is known as a:
Analytical techniques are a tool and technique of which process in Project Procurement Management?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
When the business objectives of an organization change, project goals need to be:
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
Which Manage Communications tool or technique focuses on identifying and managing barriers?
A project manager who communicates to the project team though email is using which type of communication?
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Those who enter into a contractual agreement to provide services necessary for a project are:
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Progressively elaborating high-level information into detailed plans is performed by the:
A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
The following is a network diagram for a project.
What is the critical path for the project?
A risk that arises as a direct result of implementing a risk response is called a:
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
The following is a network diagram for a project.
The total float for the project is how many days?
Which document in the project management plan can be updated in the Plan Procurement Management process?
Lessons learned are created and project resources are released in which Process Group?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
Which technique helps to determine the risks that have the most potential impact on a project?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
What provides information regarding the ways people, teams, and organizational units behave?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which of the following is an output of the Perform Integrated Change Control process?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
As the project progresses, which of the following is routinely collected from the project activities?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Who determines which dependencies are mandatory during the Sequence Activities process?
The process of identifying the stakeholders' information needs is completed during:
Which of the following is an input to the Direct and Manage Project Execution process?
Which can be used to determine whether a process is stable or has predictable performance?
Which of the following is an information gathering technique in Identify Risks?
Which of the following documents allows the project manager to assess risks that may require near term action?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which is the correct formula for calculating expected activity cost for three-point estimating?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
Project contracts generally fall into which of the following three broad categories?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
Which of the following reduces the probability of potential consequences of project risk events?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
What is the number of stakeholders, if the project has 28 potential communication channels?
Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
Which illustrates the connection between work that needs to be done and its project team members?
Which action should a project manager take to ensure that the project management plan is effective and current?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
The procurement process that documents agreements and related documentation for future reference is known as:
Which of the following is contained within the communications management plan?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
The individual or group that provides resources and support for a project and is accountable for success is the:
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Which schedule network analysis technique modifies the project schedule to account for limited resources?
What type of project structure is a hierarchically organized depiction of the resources by type?
Which tool is used to develop technical details within the project management plan?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
Change requests are an output from which Project Integration Management process?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
Which of the following is an output of the Monitor and Control Project Work process?
It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?
An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage. What effective tools should the project teams use to collaborate?
A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis. Which technique is the team using?
A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?
Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?
A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project of what should the project manager be aware?
A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence. What should the project manager do first?
The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?
A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?
Match the method for categorizing stakeholders with its corresponding description
What type of stakeholder is part of a project manager 's sphere of influence on a project?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?
During what project management process does the project team begin identifying risks?
A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
What process is used to identify quality requirements and/or standards for a project and its deliverables'?
What risk response strategy involves removing high- risk scope elements from a project?
Company A’s accountant sends notification about a change in the company’s tax classification.
What would a project have to be initiated?
A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?
A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?
The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.
Which of the 5Cs of written communications does the project manager need to address?
The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?
Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)
Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?
During a project's execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?
A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?
A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.
Which evaluation technique is most effective for this situation?
A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone. To reduce the risk with this approach, which step should the business analyst take?
A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?