You are the project manager of a project. Your project just went into integration mode. This means that your project __________.
Customer formally accepts the deliverables of each project phase. This process is known as ________.
Which process must occur after a project manager has been assigned to the project?
In which type of organization, a project manager is in complete control of the project?
Which of the following must be measured regularly to identify variances from the plan.
Identification of Mandatory Dependencies is done during which of the following process:
You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?
Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:
Which document is best suited for tracking the assignment of all resources to specific tasks in a project?
Which of the following project document is best suited for tracking costs of resources?
Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.
You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?
Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
Who has the responsibility for informing the final deliverable to all stakeholders?
Who is responsibility for making sure that a message in the project team is understood
Which of the following is the most important task of the project manager during the Execution and Control phase?
_________ is always the lowest risk for the buyer if the scope of work is not well defined.
Which of the following is a common characteristic of most project life cycle descriptions?
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?
An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:
The product description of a project can help to create procurement details. Which one of the following best describes product description?
You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?
In which domain of project management would a Pareto chart provide useful information?
When communicating with large audiences, which communication method works most effectively?
What tool and technique includes all costs incurred over the life of a product by investment in preventing nonconformance to requirements?
What quality control tool graphically represents how various elements of a system interrelate?
__________ is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.
Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which tool is used to develop technical details within the project management plan?
Which type of control tool identifies whether or not a process has a predictable performance?
Which stakeholder is responsible for managing related projects in a coordinated way?
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
Reserve analysis is a tool and technique used in which of the following processes?