Combustible construction forming concealed spaces shall be protected with noncombustible protection with an assigned time of 40 minutes in which construction type?
In mass timber construction of Type IV-C, the fire-resistance ratings of bearing walls are permitted to be reduced by _____ where supporting a roof only.
Buildings of Types IV-A, IV-B, and IV-C construction designed to be greater than six stories above grade plane shall meet which of the following requirements for fire safety practices during construction?
Refer to the exhibit by clicking on the EXHIBIT button above.

Given: The connections between the glulam beam and CLT panels all require a fire-resistance rating of 2 hours, and wood cover is designed per AWC Technical Report 10 to provide the entire 2 hours of protection.
The bearing area between the CLT and glulam is the minimum required.
What are the minimum dimensions, in inches, for the wood block shown in red?
Periodic special inspection of sealants or adhesives shall be conducted where sealants or adhesives are part of a mass timber building element as designated in the approved construction documents.
All of the following statements are correct in reference to sealants or adhesives in mass timber buildings except:
In Type IV-C construction, the fire-resistance rating provided by protection over a connection can be determined by which of the following?
Both surfaces of a two-hour-rated mass timber wall that serves as a required separation between a Group R and Group I-2 occupancy in a Type IV-C building must be protected by at least which of the following?
Are mass timber elements permitted to serve as a fire barrier to an adjacent occupancy if they are separated from the interior of the building with an approved thermal barrier consisting of a minimum of 1/2 in. gypsum board or a noncombustible equivalent?
Regarding water supply for the protection of buildings under construction, when combustible building materials of the building under construction are delivered to a site, the minimum fire flow provided shall be _____ gpm.
Each of the following is true for special inspection of mass timber construction except:
Which of the following is true regarding Type IV-B unprotected portions of mass timber ceilings and walls?
Refer to the exhibit by clicking on the EXHIBIT button above.


In the detail shown, which fasteners require fire protection according to AWC Technical Report 10?
For Type IV-A construction, noncombustible protection shall provide what fraction of the required fire-resistance rating for building elements?
Where Type X gypsum board serves as noncombustible protection for interior surfaces of wall and ceiling assemblies, all of the following code provisions are correct except:
Refer to the figure by clicking on the EXHIBIT button above.


In Type IV-B construction, based on a 900 sq. ft. floor area, a 30 ' room width, and a 12 in. x 18 in. beam as shown in the Figure, the maximum length of the unprotected portion of the mass timber ceiling (dimension X) is _____ feet.
Periodic special inspection of sealants or adhesives as specified by the International Building Code Section 703.7 shall be conducted at which of the following locations?
The building owner shall be responsible for each of the following for fire safety during construction except:
For Type IV-A, IV-B, and IV-C construction, each of the following materials on the exterior side of mass timber exterior walls is required to be noncombustible except:
Which of the following best describes the required protection for mass timber hoistway enclosure walls in Type IV-C construction?
In mass timber construction of Type IV-B, each of the following is suitable for use as fireblocking except:
The maximum allowable height for a Group I-4 building of Type IV-B construction provided with an automatic sprinkler system in accordance with Section 903.3.1.1 is _____ ft.